In re Investigation into Programmatic Adjustments to the Standard-Offer Program (Renewable Energy Vermont, Appellant)

2018 VT 52, 191 A.3d 113
CourtSupreme Court of Vermont
DecidedMay 11, 2018
Docket2017-165
StatusPublished
Cited by9 cases

This text of 2018 VT 52 (In re Investigation into Programmatic Adjustments to the Standard-Offer Program (Renewable Energy Vermont, Appellant)) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re Investigation into Programmatic Adjustments to the Standard-Offer Program (Renewable Energy Vermont, Appellant), 2018 VT 52, 191 A.3d 113 (Vt. 2018).

Opinion

REIBER, C.J.

*114 ¶ 1. Appellant Renewable Energy Vermont (REV) asks this Court to reverse and remand an order of the Vermont Public Utility Commission 1 that altered technology allocations in the standard-offer program for renewable energy projects. We conclude that REV seeks an advisory opinion and therefore dismiss the appeal for lack of jurisdiction.

¶ 2. The standard-offer program was established by the Legislature in 2005 as part of an effort to promote development of renewable energy in Vermont. See 30 V.S.A. §§ 8001, 8005, 8005a. The standard-offer statute directs the Commission to authorize "long-term power-purchase contracts with electrical providers in Vermont for renewable energy projects that have a nameplate capacity of 2.2 megawatts (MW) or less and meet certain other criteria." In re Programmatic Changes to Standard-Offer Program , 2014 VT 29 , ¶ 2, 196 Vt. 175 , 95 A.3d 999 (citing 30 V.S.A. § 8005a(b) ). "Once a plant owner executes a standard-offer contract, the [Commission] guarantees a set price for that plant's energy for the duration of the contract regardless of whether the market price changes." Id . (citing 30 V.S.A. § 8005a(f)(4) ). Vermont electric utilities are then required to purchase the electricity generated by these projects at that price. 30 V.S.A. § 8005a(k)(2).

¶ 3. The standard-offer program has a cumulative plant capacity of 127.5 MW, a portion of which is made available to new projects each year. Id . § 8005a(c). For 2017, the available new capacity was 7.5 MW. Id . § 8005a(c)(1)(A). This was increased to 8.625 MW due to unsubscribed capacity from 2016. A portion of each year's capacity, known as the "provider block," is reserved for new plants proposed by Vermont retail electricity providers. Id . § 8005a(c)(1)(B). The remaining capacity-the "developer block"-is reserved for independent developers. Id . The Commission is required to allocate the cumulative 127.5 MW capacity among the following designated categories of renewable energy technologies: solar power; wind power with a plant capacity of 100 kW or less (referred to by the Commission as "small wind"); wind power with a plant capacity greater than 100 kW (referred to as "large wind"); landfill methane; hydroelectric power; and biomass power. Id . § 8005a(c)(2). This requirement furthers the stated legislative goal of "[p]romoting the inclusion, in Vermont's electric supply portfolio, of renewable energy plants that are diverse in plant capacity and type of renewable energy technology." Id . § 8001(a)(8).

¶ 4. The Commission solicits bids for qualifying projects through an annual request-for-proposal (RFP) process. Prior to issuing the annual RFP, the Commission determines the maximum price that utilities will be required to pay for electricity generated by new projects in each category of renewable technology, "with a goal of ensuring timely development at the lowest feasible cost." Id . § 8005a(f). These price caps operate as a ceiling for bids. Id .

¶ 5. In 2016, the Department of Public Service observed that solar projects were on track to fill three-quarters or more of the cumulative capacity if the RFP process was not modified. To address this disparity, the Commission issued an order in February 2016 that set aside a "technology *115 diversity developer block" that would be allocated on an equal basis to each of the nonsolar technology categories. Only projects using the designated technology would be permitted to bid for the set-aside capacity for that technology. The remaining capacity in the developer block would be available to projects in any technology category and would be awarded based solely on bid price. This was called the "price-competitive developer block." The Commission ordered that the new allocation arrangement was to remain in effect for the remainder of the standard-offer program, unless changed by a subsequent order.

¶ 6. After the Commission issued its 2016 order, the Legislature passed Act 174, which created a temporary pilot program for standard-offer projects located at "preferred locations." 2 2015, No. 174 (Adj. Sess.), § 12a (effective July 1, 2016) (codified at 30 V.S.A. § 8005a(c)(1)(D) ). Act 174 required that for one year beginning on January 1, 2017, the Commission was to allocate one-third of the annual capacity increase to these projects. Id . In September 2016, the Commission announced that due to Act 174, it planned to revisit the allocations set forth in its February 2016 order as part of its annual price review.

¶ 7.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2018 VT 52, 191 A.3d 113, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-investigation-into-programmatic-adjustments-to-the-standard-offer-vt-2018.