Grice v. Vermont Elec. Power Co., Inc.

2008 VT 64, 956 A.2d 561, 184 Vt. 132, 2008 Vt. LEXIS 64
CourtSupreme Court of Vermont
DecidedMay 16, 2008
Docket06-352 & 06-510
StatusPublished
Cited by18 cases

This text of 2008 VT 64 (Grice v. Vermont Elec. Power Co., Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Grice v. Vermont Elec. Power Co., Inc., 2008 VT 64, 956 A.2d 561, 184 Vt. 132, 2008 Vt. LEXIS 64 (Vt. 2008).

Opinion

Reiber, C.J.

¶ 1. These two related appeals involve a petition by the Vermont Electric Power Company (VELCO) to condemn an easement for an electrical-transmission line across the property of landowners, Harley Grice, individually and as trustee of the Harley Grice Trust, Wendy Butler, Penny Curler and Heather Grice (the Grices). The Public Service Board granted VELCO’s petition to condemn a strip of the Grice property, but denied VELCO’s request to install excess fiber-optic capacity along the corridor. Concurrent to the Board proceedings, the Grices filed a declaratory action in superior court challenging the Board’s statutory and constitutional authority to condemn their property. The court concluded that the Board had constitutional and statutory authority. The Grices appeal both the Board’s condemnation order and the superior court’s judgment. VELCO cross-appeals from the Board’s order denying its request to add excess fiber-optic capacity to its transmission line. We affirm the superior court decision and the Board’s condemnation order, but amend the Board’s order to allow VELCO to install the requested fiber-optic capacity.

¶ 2. The procedural history and facts of the case are briefly as follows. VELCO initiated a plan to increase the capacity of the electrical grid in Vermont by installing along a thirty-five-mile corridor a 345 kilovolt (kV) electrical line as part of the Northwest Reliability Project (NRP). VELCO petitioned the Board for a certificate of public good (CPG), and in January 2005 the Board concluded that the NRP was necessary for the reliability of the electrical system in Vermont and issued a CPG. See 30 V.S.A. § 248(a) (requiring an electric company to obtain approval from the Board that a project “will promote the general good” before beginning to construct a new transmission facility). Several parties challenged the Board’s decision to grant a CPG, and, on appeal, this Court affirmed. In re Vt. Elec. Power Co., 2006 VT 69, 179 Vt. 370, 895 A.2d 226.

*136 ¶ 3. Following the Board’s issuance of the CPG, VELCO attempted to negotiate with the landowners along the proposed corridor, including the Grices, to obtain the necessary easements. VELCO already has a 150-foot-wide easement across the Grices’ land where an 115kV electric line is installed. In September 2005, after VELCO failed to reach an agreement with the Grices, VELCO petitioned the Board to condemn a 100-foot-wide strip of the Grice property, about a mile in length that would run parallel to the existing lower-voltage easement. VELCO asked for permission to remove so-called “danger trees” outside of the easement and for access to the easement at all points in the case of an emergency. As part of its proposal, VELCO also planned to install an optical ground wire (OPGW) cable across the easement with seventy-two optical fibers to transmit data, and video and voice communication. VELCO explained that the OPGW cable would be used for internal communication and was necessary to insure reliability of the line, but acknowledged that it did not need all seventy-two fibers for internal communication. VELCO planned to trade any excess capacity to other communication service providers in return for use of their capacity in other parts of the state where VELCO does not have optical fibers and must pay for their use.

¶ 4. The hearing officer granted VELCO’s request for condemnation, and for unlimited access to the easement. The officer concluded that it was necessary for VELCO to be able to reach the easement to remove trees or restore power in the case of an emergency. The hearing officer denied VELCO’s request to install excess capacity in the OPGW, concluding that this was not necessary for VELCO’s business of providing electrical services, and therefore VELCO could not condemn the property for such a purpose.

¶ 5. On appeal, the Board adopted the hearing officer’s findings, affirmed the hearing officer’s conclusion that the easement was necessary, and granted VELCO condemnation of the easement. The Board also granted VELCO unlimited access to the easement, concluding that it was necessary to maintain reliability of the line in emergency situations. The Board assessed damages for the Grices at $25,000. In response to VELCO’s request to install excess capacity in the OPGW, the Board concluded that VELCO was not authorized to sell, lease or exchange excess capacity. In a subsequent order clarifying this conclusion, the Board specified *137 that VELCO was not authorized to install all seventy-two fibers because VELCO only needed twenty-four fibers to insure the reliability of the line. The Board reasoned that if VELCO could buy capacity from other providers in other parts of the state then it was not necessary to have excess capacity to trade.

¶ 6. While the Board action was pending, the Grices also filed an action for declaratory judgment in Addison Superior Court, challenging VELCO’s statutory and constitutional authority to condemn their land in a proceeding before the Board. The Grices argued that the Board’s assertion of jurisdiction violated its authorizing statute, was preempted by federal law and violated the Vermont Constitution because the energy running through the transmission lines would be regulated by federal, not state, law. The superior court dismissed the complaint, concluding that the condemnation action did not violate any statute or the Vermont Constitution, and was not preempted by federal law. The Grices appealed. The Grices also appealed the Board’s decision, challenging the Board’s authority to adjudicate the condemnation action. VELCO filed a cross-appeal, arguing that the Board erred in not granting it the right to install excess fiber-optic capacity along the easement. We consolidated the appeals from the Board and the superior court.

¶ 7. We review de novo the superior court’s decision interpreting the statute and the Vermont Constitution. Wright v. Bradley, 2006 VT 100, ¶ 6, 180 Vt. 383, 910 A.2d 893. Our review of decisions from the Board is more deferential; we defer to the Board’s “expertise and informed judgment,” and “apply a strong presumption of validity” to its orders. In re Verizon New England Inc., 173 Vt. 327, 334, 795 A.2d 1196, 1202 (2002). “Absent a compelling indication of error, we will not disturb an agency’s interpretation of statutes within its particular area of expertise.” Id. at 334-35, 795 A.2d at 1202. With these standards in mind, we turn to the issues on appeal.

I.

¶ 8. We first address the Grices’ claims in their direct appeal. In three related claims, the Grices argue that the Board had no authority to grant VELCO’s condemnation request because the condemnation action: (1) is contrary to the Board’s statutory mandate, (2) is preempted by federal law, and (3) violates Article 2 of the Vermont Constitution. The Grices also contend that if the *138 Board did have authority to adjudicate the condemnation action, the Board erroneously granted VELCO overly broad access to the property. Finally, the Grices request attorney’s fees and expert witness costs. We consider these claims in turn.

A.

¶ 9.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Aerie Point Holdings, LLC v. Vorsteveld Farm, LLC
2024 VT 29 (Supreme Court of Vermont, 2024)
Mdu v. Parkshill Farms
2017 SD 88 (South Dakota Supreme Court, 2017)
Arapaho Owners Association, Inc. and Kattalia v. Alpert
199 Vt. 553 (Supreme Court of Vermont, 2015)
Arapaho Owners Ass'n, Inc. v. Alpert
2015 VT 93 (Supreme Court of Vermont, 2015)
In re Programmatic Changes to the Standard-Offer Program
2014 VT 29 (Supreme Court of Vermont, 2014)
Farrell v. Vermont Electric Power Co., and Vermont Transco, LLC
2012 VT 96 (Supreme Court of Vermont, 2012)
Toor and Toor Living Trust NOV
Vermont Superior Court, 2011
In Re Central Vermont Public Service Corp.
2010 VT 7 (Supreme Court of Vermont, 2010)
Massey v. Hrostek
2009 VT 70 (Supreme Court of Vermont, 2009)
Ovitt v. American Home Assurance Co.
2009 VT 26 (Supreme Court of Vermont, 2009)
Grice v. Vermont Electric Power Company, Inc.
Supreme Court of Vermont, 2008

Cite This Page — Counsel Stack

Bluebook (online)
2008 VT 64, 956 A.2d 561, 184 Vt. 132, 2008 Vt. LEXIS 64, Counsel Stack Legal Research, https://law.counselstack.com/opinion/grice-v-vermont-elec-power-co-inc-vt-2008.