Petition of Vermont Electric Power Company, Inc.

306 A.2d 687, 131 Vt. 427, 1973 Vt. LEXIS 328
CourtSupreme Court of Vermont
DecidedJune 5, 1973
Docket169-72
StatusPublished
Cited by19 cases

This text of 306 A.2d 687 (Petition of Vermont Electric Power Company, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Petition of Vermont Electric Power Company, Inc., 306 A.2d 687, 131 Vt. 427, 1973 Vt. LEXIS 328 (Vt. 1973).

Opinion

Shangraw, C.J.

This appeal concerns a proposed 115-KV transmission line for which Vermont Electric Power Company (VELCO) commenced this action on September 1, 1970, before the Public Service Board by filing a petition under 30 V.S.A. § 248 in which it prayed that the Board, after hearing, issue it a certificate of general good authorizing construction of the proposed transmission line. The proposed transmission line for which VELCO sought the certificate was to run a distance of approximately five miles from the present VELCO Essex-Middlebury line in Williston to a point near the Burlington-South Burlington boundary in the vicinity of Queen City Park Road, terminating at a proposed new substation.

Notice of the petition and of the hearing thereon was sent to all persons, organizations and planning officials specified in 30 V.S.A. § 248. In addition, notice was also published in a local newspaper. Substantial public interest arose on the transmission line proposed in the petition and lengthy public hearings followed on six separate occasions, commencing on October 20,1970, and ending on March 16,1972.

Initially VELCO presented three routings of the proposed transmission line, all involving overhead construction on wood-pole H-frame structures. VELCO’s recommended route, known as Route No. 3, or the “northern route”, would begin at a point on its Essex-Middlebury 115-KV line approximately *430 4,500 feet south of Interstate 1-89, travel westerly generally paralleling 1-89, and Interstate 1-189, cross U.S. Route 7 near the intersection of 1-189, and terminate at the proposed new substation adjacent to the Queen City Park Road. Route No. 1, the “southern route”, would begin at a point on the EssexMiddlebury 115-KV line approximately two miles south of Interstate 1-89, travel westerly on the north side of Brownell Mountain, jog northerly west of Spear Street, then jog back in a westerly direction, crossing U.S. Route 7 near Shearer Chevrolet and then northerly along the railroad tracks to the proposed substation. The other route, known as Route No. 2, would be located roughly midway between Route No. 1 and Route No. 3.

During the course of the proceedings below the public gave considerable attention to the aesthetic and environmental impact of the proposed transmission line, as well as the effect of the line on the orderly development of the region. In this regard, both the Board and the parties expended considerable effort in exploring the feasibility of placing all, or a portion, of the line underground along Route No. 3.

On July 25, 1972, the Board filed its findings and issued a certificate of general good to VELCO, pursuant to the provisions of 30 V.S.A. § 248, which provides in part:

“(b) Before the public service board issues a certifi- , cate of public good, it shall find that the construction:
(1) will not unduly interfere with the orderly development of the region with due consideration having been given to the recommendations of the municipal and regional planning commissions and the municipal legislative bodies;
(2) is required to meet the need for present and future demand for service;
(3) will not adversely affect system stability and reliability and economic factors; and
(4) will not have an undue adverse effect on esthetics, historic sites, air and water purity, the natural environment and the public health and safety.”

In its findings the Board discussed the features and limitations of the several alternatives before it approved the loca *431 tion of the transmission line overhead along what was known as Route No. 1, or the southern route. Because VELCO had not done its right-of-way investigation and because additional changes in the route could occur due to some additional development, the Board certified a general route. In certifying a general route rather than a specific route, the Board retained jurisdiction over the matter so it could review the detailed plans and approve them before VELCO began the clearing and construction of the line. The Board also provided that the plans were to be submitted to the other parties in the proceeding and they were to be given two weeks in which to comment to the Board upon them.

Following the denial of a motion for reconsideration and for leave to present additional evidence by the Board, an appeal was taken to this Court by the City of South Burlington, and a group of interested citizens and property owners of the City of South Burlington.

In this appeal three of the appellants’ arguments are presented in the form of a somewhat oblique attack upon the findings of fact the Board made relative to certain of the criteria of 30 V.S.A. § 248(b), as being unsupported by the evidence or contrary to the evidence. More specifically, the appellants challenge the findings of fact made by .the Board pursuant to 30 V.S.A. § 248(b)(1) and (4), which require that the Board find that the proposed transmission line will not unduly interfere with the orderly development of the region, and it will not have an undue adverse effect on aesthetics and the natural environment. To support these arguments, the appellants resort to the record and recite a quantity of the evidence introduced in favor of locating the transmission line underground along Route No. 3, or the “northern route”.

In reviewing the findings of fact made by the Board pursuant to 30 V.S.A. § 248(b), we as a reviewing Court, will accept them unless they are clearly erroneous. Petition of Green Mountain Power Corporation, 131 Vt. 284, 305 A.2d 571, 575 (1973); 30 V.S.A. § 11(b). It is not the function of this Court to require the facts be found in accordance witlr our view of the evidence, thereby substituting our judgment for the Board. Rather, we will support their weighing of the evidence if there is evidence to support it. In this respect *432 it is not for this Court to review the rightness of the Board’s findings, rather it is only for this Court to review the reasonableness of its findings. Petition of Green Mountain Power Corporation, supra; see also Petition of Lyndonville Village, 121 Vt. 185, 190, 151 A.2d 319 (1959). Only when we have reviewed the entire record and have been left with the definite and firm conviction that a mistake has been committed will we hold a finding to be clearly erroneous. United States v. United States Gypsum Co., 333 U.S. 364, 395 (1948).

At the outset it must be noted that no party has disputed the evidence presented below by VELCO which demonstrated a compelling need for a 115-KV transmission line into the Queen City area of South Burlington. Moreover, the Board recognized this need as early as 1968 when, ip its planning capacity, it began to urge VELCO to plan for this line.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Petition of TruConnect Communications, Inc.
2021 VT 70 (Supreme Court of Vermont, 2021)
Massey v. Hrostek
2009 VT 70 (Supreme Court of Vermont, 2009)
In Re Amended Petition of UPC Vermont Wind, LLC
2009 VT 19 (Supreme Court of Vermont, 2009)
Grice v. Vermont Electric Power Company, Inc.
Supreme Court of Vermont, 2008
Grice v. Vermont Elec. Power Co., Inc.
2008 VT 64 (Supreme Court of Vermont, 2008)
In Re Vermont Elec. Power Co., Inc.
2006 VT 21 (Supreme Court of Vermont, 2006)
In Re Adelphia Business Solutions of Vermont, Inc.
2004 VT 82 (Supreme Court of Vermont, 2004)
Petition of Twenty-Four Vermont Utilities
618 A.2d 1295 (Supreme Court of Vermont, 1992)
Vermont Elec. Power Co., Inc. v. Bandel
375 A.2d 975 (Supreme Court of Vermont, 1977)
Devost v. New Hampshire Electric Coop., Inc.
349 A.2d 896 (Supreme Court of Vermont, 1975)
City of So. Burlington v. Vermont Elec. Power Co., Inc.
344 A.2d 19 (Supreme Court of Vermont, 1975)
Auclair v. VERMONT ELECTRIC POWER COMPANY, INC.
329 A.2d 641 (Supreme Court of Vermont, 1974)
Auclair v. VERMONT ELECTRIC POWER CO., INC.
323 A.2d 578 (Supreme Court of Vermont, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
306 A.2d 687, 131 Vt. 427, 1973 Vt. LEXIS 328, Counsel Stack Legal Research, https://law.counselstack.com/opinion/petition-of-vermont-electric-power-company-inc-vt-1973.