Apple Hill Solar LLC v. Cheney

CourtDistrict Court, D. Vermont
DecidedAugust 23, 2024
Docket2:23-cv-00644
StatusUnknown

This text of Apple Hill Solar LLC v. Cheney (Apple Hill Solar LLC v. Cheney) is published on Counsel Stack Legal Research, covering District Court, D. Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Apple Hill Solar LLC v. Cheney, (D. Vt. 2024).

Opinion

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF VERMONT

APPLE HILL SOLAR LLC, ) ) Plaintiff, ) ) v. ) Case No. 2:23-cv-644 ) MARGARET CHENEY and ANTHONY ) ROISMAN, ) ) Defendants. )

OPINION AND ORDER

Plaintiff Apple Hill Solar LLC (“Apple Hill”) has filed a Complaint against Margaret Cheney and Anthony Roisman (“Defendants”) for actions taken in their capacities as Commissioners of the Vermont Public Utility Commission (“PUC”). The case arises out of Apple Hill’s efforts to develop a solar energy facility in Bennington, Vermont, and the related PUC permitting process. The Complaint asserts that in the course of that process, Defendants failed to adhere to state law and subsequently misled the Vermont Supreme Court. Apple Hill’s claims allege violations of the Takings Clause, as well as due process, equal protection, and ethical violations. The Complaint seeks primarily injunctive and declaratory relief. Now before the Court is Defendants’ motion to dismiss in which they assert a host of defenses including judicial immunity, collateral estoppel, and failure to state plausible causes of action. Defendants also contend that Defendant Roisman should be dismissed from the case because he is no longer on the PUC. For the reasons set forth below, the motion to dismiss is granted. Factual and Procedural Background

The Complaint alleges that over the past ten years, Apple Hill has been seeking to develop a 2.0 megawatt solar energy facility (the “Project”) on land in Bennington, Vermont. In doing so, Apple Hill has appeared before the PUC on several occasions in an effort to obtain a Certificate of Public Good (“CPG”). The allegations in this case focus on Apple Hill’s most recent appearance before the PUC and appeal to the Vermont Supreme Court. The procedural history begins in or around 2013, when counsel for Apple Hill first sought standard-offer contracts for two solar facilities, including Apple Hill. The PUC found that the proposed facilities did not qualify for standard-offer

contracts because they were actually a single facility “located on the same parcel of land” and with “similar interconnection points,” which when combined exceeded the statutory limit on generation capacity. In re Programmatic Chances to the Standard Offer Program, 2014 VT 29, ¶¶ 1, 7. On appeal, the Vermont Supreme Court concluded that the two facilities were sufficiently independent and remanded to the PUC for further agency action. Id., ¶¶ 10-16. In 2018, the PUC granted a CPG for the Apple Hill facility. The Project’s neighbors appealed the decision. The Vermont Supreme Court again reversed, concluding that the PUC had

improperly interpreted the Town of Bennington’s lack of opposition to the Project as an indication that the Project complied with the Town Plan. In re Apple Hill Solar LLC, 2019 VT 64, ¶ 30. The court thus remanded the matter to the PUC “to assess the impact of the project on the orderly development of the region in light of the Town Plan without consideration of the selectboard’s purported position on the subject.” Id., ¶ 31. On remand, “[t]he parties agreed that no additional evidence was necessary.” In re Apple Hill Solar, 2021 VT 69, ¶ 8. The PUC appointed a hearing officer to address issues identified by the Vermont Supreme Court, and the hearing officer

recommended that the PUC deny the CPG petition. Specifically, the hearing officer concluded that the Project would violate two Town Plan standards insofar as it was a commercial development that was incompatible with the rural character of the area and would be sited in a prominently visible location on a hillside. ¶ 7. The PUC issued a proposed decision and provided the parties the right to file briefs and present oral argument. Apple Hill availed itself of those rights. After hearing argument, the PUC adopted the hearing officer’s recommendation and denied the request for a CPG. Apple Hill appealed to the Vermont Supreme Court. The court reversed in part, concluding that the cited provision in

the Town Plan regarding rural character of the area was too broad and general to constitute a clear, written community standard. Id., ¶ 42. The court affirmed the PUC’s conclusion that the Project would violate the Town Plan standard prohibiting development in prominently visible locations on hillsides. Id., ¶ 50. The court then remanded the matter to the PUC to reassess the application without the conclusion that the proposed siting “would interfere with orderly development and cause an undue adverse aesthetic impact,” since Vermont law only required the PUC to give such a standard “due consideration” and did not compel denial of the permit. Id., ¶ 67 (citing 30 V.S.A. § 248(b)(1)). “Ultimately,” the court

concluded, “the PUC is charged with determining whether the project will serve the public good.” Id. On remand, after receiving additional briefing from the parties, the PUC again denied the CPG petition. The PUC “concluded that the placement of the proposed project in a prominently visible location on a hillside would result in undue interference with the orderly development of the region and have an undue adverse impact on aesthetics.” In re Petition of Apple Hill Solar LLC, 2023 VT 57, ¶ 9, reargument denied (Dec. 12, 2023). The PUC further “found that the potential benefits of the project did not outweigh these impacts because the state could realize similar benefits from other solar projects located

in areas that did not run afoul of town and regional plans.” Id. Apple Hill appealed the PUC’s ruling. On appeal, Apple Hill argued that the PUC’s decision violated certain “provisions of the Vermont Administrative Procedures Act (VAPA), relied on evidence not in the record, contained impermissible post-hoc rationalizations, ignored [the Vermont Supreme Court’s] remand order, and was arbitrary and capricious.” Id., ¶ 10. Apple Hill further argued that the PUC ought to have allowed additional evidence and denied it due process and equal protection. Id. The Vermont Supreme Court affirmed the PUC’s ruling. The court found that Apple Hill had not been entitled to an

additional evidentiary hearing since the parties stipulated the record was complete, and that its previous remand did not require an additional hearing. Id., ¶¶ 23-24. The Vermont Supreme Court also rejected Apple Hill’s constitutional challenges, in which it claimed the PUC’s application of Vermont law was unconstitutionally vague and standardless. Id., ¶ 32. The court found that Apple Hill had failed to preserve those issues in the most recent PUC proceeding, and that even if the issues had been preserved, they were essentially a facial challenge to a statute which the PUC had no jurisdiction to address. As part of its VAPA claim, Apple Hill claimed that the PUC

should have issued a proposal for decision and given the parties an opportunity to comment. Apple Hill argued that such a proposal was required because the majority of the three-member PUC did not hear the case or read the record. Id., ¶ 12. Vermont law, 30 V.S.A. § 811, provides that no proposal for decision is required “where the [PUC] does read the record or hear the case, or both. In such situations, the [PUC] is not accepting the determination of its hearing officer without itself evaluating the facts.” The Vermont Supreme Court acknowledged that the evidence in the case was heard by a hearing officer, but found that Apple Hill “provide[d] no support for its assertion that a majority of

the Commission members did not read the record, and the facts do not support such an inference.” In re Petition of Apple Hill Solar LLC, 2023 VT 57, ¶ 14.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ali v. Mukasey
529 F.3d 478 (Second Circuit, 2008)
Clubside, Inc. v. Valentin
468 F.3d 144 (Second Circuit, 2006)
Pennsylvania Coal Co. v. Mahon
260 U.S. 393 (Supreme Court, 1922)
Penn Central Transportation Co. v. New York City
438 U.S. 104 (Supreme Court, 1978)
Butz v. Economou
438 U.S. 478 (Supreme Court, 1978)
United States v. Riverside Bayview Homes, Inc.
474 U.S. 121 (Supreme Court, 1985)
Mireles v. Waco
502 U.S. 9 (Supreme Court, 1991)
Palazzolo v. Rhode Island
533 U.S. 606 (Supreme Court, 2001)
Lingle v. Chevron U. S. A. Inc.
544 U.S. 528 (Supreme Court, 2005)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Ruston v. Town Bd. for Town of Skaneateles
610 F.3d 55 (Second Circuit, 2010)
Constantine v. Teachers College
448 F. App'x 92 (Second Circuit, 2011)
Rodriguez v. Mcloughlin
214 F.3d 328 (Second Circuit, 2000)
Ashmore v. Prus
510 F. App'x 47 (Second Circuit, 2013)
Langdon v. Swain
29 F. App'x 171 (Fourth Circuit, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
Apple Hill Solar LLC v. Cheney, Counsel Stack Legal Research, https://law.counselstack.com/opinion/apple-hill-solar-llc-v-cheney-vtd-2024.