In re Miami Conservancy Dist.
This text of 2025 Ohio 116 (In re Miami Conservancy Dist.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
[Cite as In re Miami Conservancy Dist., 2025-Ohio-116.]
IN THE COURT OF APPEALS OF OHIO SECOND APPELLATE DISTRICT MONTGOMERY COUNTY
IN THE MATTER OF: THE MIAMI : CONSERVANCY DISTRICT : : C.A. No. 30193 : : Trial Court Case No. 36847 : : (Civil Appeal from Common Pleas : Court) : :
...........
OPINION
Rendered on January 17, 2025
JASON P. CONTE & EMILY H. DAVIS, Attorneys for Appellant
GREGORY J. DEGULIS & LEE A. SLONE, Attorneys for Appellee
.............
EPLEY, P.J.
{¶ 1} Sunesis Construction Company appeals from the trial court’s judgment
overruling Sunesis’s motion for partial summary judgment and granting summary
judgment to the Miami Conservancy District (MCD) on Sunesis’s claims and on MCD’s
counterclaim. For the following reasons, the trial court’s judgment will be affirmed in part, -2-
reversed in part, and remanded for further proceedings regarding Payment Items 11, 20,
and 26.
I. Facts and Procedural History
{¶ 2} The following facts are undisputed. The MCD, established after the 1913
flood, is a public organization responsible for flood protection in the Great Miami River
watershed. Between 1918 and 1922, MCD constructed five dry dams along major
waterways – the Lockington, Germantown, Englewood, Taylorsville, and Huffman Dams.
{¶ 3} Given the technology at the time, the
concrete used in the dams’ construction was highly
susceptible to deterioration from freezing and
thawing in the presence of moisture. Over time, it
has suffered deterioration in the form of cracking,
spalling, and delamination. Some surface repairs were performed in the 1970s using
shotcrete, but those repairs have delaminated as well and the original concrete has
continued to deteriorate. See O’Connor Dep., Ex. 10. Due to the dams’ aging
infrastructure, MCD had a pilot concrete repair project performed on the southwest
abutment wall (downstream right side, when looking downstream) of the Lockington Dam
in 2017, with a report issued in February 2018. Id.
{¶ 4} In 2019, MCD sought bids for the Lockington Dam Right Wall Drain System
and Concrete Repair Project (“the Project”), Contract No. 2019-021C, which primarily
focused on repairing the right spillway walls. On October 11, 2019, MCD hired Sunesis
for the Project; the original agreed cost was $2,614,347. MCD Motion for Summary -3-
Judgment (MSJ), Ex. K. MCD subsequently agreed to pay an additional $62,896.84 in
two change orders. MCD MSJ, Ex. L.
{¶ 5} The Contract consisted of several complementary documents. General
Condition 35 set forth an order of precedence for the contract documents: (1) Contract,
(2) Change Orders, (3) Addenda, (4) Detailed Specifications, (5) Plans/Drawings, (6)
General Conditions, (7) Proposal, (8) Instructions to Bidders, (9) Other documents
specifically referenced in the Contract, and (10) ODOT Specifications. In the event of a
conflict between the documents, the interpretation of MCD’s Engineer governed. GC-
35.
{¶ 6} Sunesis’s tasks were delineated in 35 Payment Items, which were part of the
Detailed Specifications. For each Payment Item, the Contract provided a general
description of the work to be performed, a description of any required submittals, any
material requirements, any required methods and processes, and instructions on
measurement and payment. Final payment for the contract was based on “actual
quantities realized and unit prices of payment items.” GC-17 (Final Payment); O’Connor
Dep. 46.
{¶ 7} The Contract also contained 36 General Conditions. Of particular relevance
here, GC-8 provided:
GC-8. Direction of Work and Interpretation of Plans and Specifications
It is mutually agreed that the ENGINEER shall have the right to direct the
manner in which all work under this Contract is to be conducted, insofar as
may be necessary to secure the safe and proper progress and quality of the -4-
work. Upon all questions concerning the execution of the work,
interpretation of the Specifications and Plans, determination of all quantities
and amounts of work done, the decision of the ENGINEER shall be final
and binding on both parties, and compliance with its estimates and
decisions shall be a condition precedent to the right of the CONTRACTOR
to receive any payment under the Contract.
(Emphasis added.) The term “Engineer” was defined as MCD’s Chief Engineer or
properly authorized agents. GC-1 (Definitions). It included the terms “owner’s
representative,” “project manager,” and “consultant.” Throughout the contract, Donald
O’Connor served as project manager for MCD.
{¶ 8} Sunesis agreed to begin work within 10 days after the date of the Notice of
Commencement and to complete the Project within 180 days, unless extended by a
written change order. The initial project completion date was April 11, 2020.
{¶ 9} A week after contracting with Sunesis, MCD hired DLZ, its design engineer
consultant, to provide construction administration, concrete and materials testing, and as
needed construction-phase engineering services. MCD MSJ, Ex. B. O’Connor testified
that he and DLZ were the “Engineer” for the Project. O’Connor Dep. 45. For the
majority of the time, Kyle Sparks of DLZ served as an observer engineer, documenting
what happened each day, taking measurements, and performing testing. MCD’s
contract with DLZ expired prior to the completion of the project. At that point, Jim Kittel
of MCD assumed Sparks’s role. O’Connor Dep. 26.
{¶ 10} By a written change order in June 2020, the Project deadline was extended -5-
to July 30, 2020. Sunesis substantially completed its work in the spring of 2021.
{¶ 11} On November 12, 2021, Sunesis filed suit against MCD, raising claims of
breach of contract, unjust enrichment, and promissory estoppel. Sunesis alleged that it
had fulfilled all conditions and obligations under the Contract and that MCD had breached
the agreement by failing to pay Sunesis for work performed under Payment Items 11
(concrete apron), 20 (concrete), 26 (concrete revetment), and 31 (patching concrete
structure). The company further alleged that it had performed additional concrete work
for which MCD had been unjustly enriched.
{¶ 12} In its answer, MCD asserted that Sunesis had been paid in full for the work
it performed and denied that Sunesis was entitled to any additional compensation. MCD
also asserted a counterclaim for expenses incurred due to Sunesis’s failure to complete
the Project on time.
{¶ 13} In December 2021, the parties agreed to Change Order #2, which modified
some aspects of the Project and increased the contract amount, but did not expressly
extend the July 30, 2020 completion deadline. The parties also signed an “Agreement
on Change Order #2” in which they agreed that the change order and the payment made
by MCD to Sunesis “shall not affect or impact, nor shall these actions act as a waiver of
the claims or defenses of Sunesis or MCD in the litigation.” O’Connor Dep., Ex. 12.
{¶ 14} After extensive discovery, Sunesis filed a motion for partial summary
judgment on Payment Item 31. MCD countered with its own motion for summary
judgment on all of Sunesis’s claims, as well as a motion for summary judgment on its
counterclaim. -6-
{¶ 15} On June 4, 2024, the trial court granted MCD’s motions and denied
Sunesis’s motion.
Free access — add to your briefcase to read the full text and ask questions with AI
[Cite as In re Miami Conservancy Dist., 2025-Ohio-116.]
IN THE COURT OF APPEALS OF OHIO SECOND APPELLATE DISTRICT MONTGOMERY COUNTY
IN THE MATTER OF: THE MIAMI : CONSERVANCY DISTRICT : : C.A. No. 30193 : : Trial Court Case No. 36847 : : (Civil Appeal from Common Pleas : Court) : :
...........
OPINION
Rendered on January 17, 2025
JASON P. CONTE & EMILY H. DAVIS, Attorneys for Appellant
GREGORY J. DEGULIS & LEE A. SLONE, Attorneys for Appellee
.............
EPLEY, P.J.
{¶ 1} Sunesis Construction Company appeals from the trial court’s judgment
overruling Sunesis’s motion for partial summary judgment and granting summary
judgment to the Miami Conservancy District (MCD) on Sunesis’s claims and on MCD’s
counterclaim. For the following reasons, the trial court’s judgment will be affirmed in part, -2-
reversed in part, and remanded for further proceedings regarding Payment Items 11, 20,
and 26.
I. Facts and Procedural History
{¶ 2} The following facts are undisputed. The MCD, established after the 1913
flood, is a public organization responsible for flood protection in the Great Miami River
watershed. Between 1918 and 1922, MCD constructed five dry dams along major
waterways – the Lockington, Germantown, Englewood, Taylorsville, and Huffman Dams.
{¶ 3} Given the technology at the time, the
concrete used in the dams’ construction was highly
susceptible to deterioration from freezing and
thawing in the presence of moisture. Over time, it
has suffered deterioration in the form of cracking,
spalling, and delamination. Some surface repairs were performed in the 1970s using
shotcrete, but those repairs have delaminated as well and the original concrete has
continued to deteriorate. See O’Connor Dep., Ex. 10. Due to the dams’ aging
infrastructure, MCD had a pilot concrete repair project performed on the southwest
abutment wall (downstream right side, when looking downstream) of the Lockington Dam
in 2017, with a report issued in February 2018. Id.
{¶ 4} In 2019, MCD sought bids for the Lockington Dam Right Wall Drain System
and Concrete Repair Project (“the Project”), Contract No. 2019-021C, which primarily
focused on repairing the right spillway walls. On October 11, 2019, MCD hired Sunesis
for the Project; the original agreed cost was $2,614,347. MCD Motion for Summary -3-
Judgment (MSJ), Ex. K. MCD subsequently agreed to pay an additional $62,896.84 in
two change orders. MCD MSJ, Ex. L.
{¶ 5} The Contract consisted of several complementary documents. General
Condition 35 set forth an order of precedence for the contract documents: (1) Contract,
(2) Change Orders, (3) Addenda, (4) Detailed Specifications, (5) Plans/Drawings, (6)
General Conditions, (7) Proposal, (8) Instructions to Bidders, (9) Other documents
specifically referenced in the Contract, and (10) ODOT Specifications. In the event of a
conflict between the documents, the interpretation of MCD’s Engineer governed. GC-
35.
{¶ 6} Sunesis’s tasks were delineated in 35 Payment Items, which were part of the
Detailed Specifications. For each Payment Item, the Contract provided a general
description of the work to be performed, a description of any required submittals, any
material requirements, any required methods and processes, and instructions on
measurement and payment. Final payment for the contract was based on “actual
quantities realized and unit prices of payment items.” GC-17 (Final Payment); O’Connor
Dep. 46.
{¶ 7} The Contract also contained 36 General Conditions. Of particular relevance
here, GC-8 provided:
GC-8. Direction of Work and Interpretation of Plans and Specifications
It is mutually agreed that the ENGINEER shall have the right to direct the
manner in which all work under this Contract is to be conducted, insofar as
may be necessary to secure the safe and proper progress and quality of the -4-
work. Upon all questions concerning the execution of the work,
interpretation of the Specifications and Plans, determination of all quantities
and amounts of work done, the decision of the ENGINEER shall be final
and binding on both parties, and compliance with its estimates and
decisions shall be a condition precedent to the right of the CONTRACTOR
to receive any payment under the Contract.
(Emphasis added.) The term “Engineer” was defined as MCD’s Chief Engineer or
properly authorized agents. GC-1 (Definitions). It included the terms “owner’s
representative,” “project manager,” and “consultant.” Throughout the contract, Donald
O’Connor served as project manager for MCD.
{¶ 8} Sunesis agreed to begin work within 10 days after the date of the Notice of
Commencement and to complete the Project within 180 days, unless extended by a
written change order. The initial project completion date was April 11, 2020.
{¶ 9} A week after contracting with Sunesis, MCD hired DLZ, its design engineer
consultant, to provide construction administration, concrete and materials testing, and as
needed construction-phase engineering services. MCD MSJ, Ex. B. O’Connor testified
that he and DLZ were the “Engineer” for the Project. O’Connor Dep. 45. For the
majority of the time, Kyle Sparks of DLZ served as an observer engineer, documenting
what happened each day, taking measurements, and performing testing. MCD’s
contract with DLZ expired prior to the completion of the project. At that point, Jim Kittel
of MCD assumed Sparks’s role. O’Connor Dep. 26.
{¶ 10} By a written change order in June 2020, the Project deadline was extended -5-
to July 30, 2020. Sunesis substantially completed its work in the spring of 2021.
{¶ 11} On November 12, 2021, Sunesis filed suit against MCD, raising claims of
breach of contract, unjust enrichment, and promissory estoppel. Sunesis alleged that it
had fulfilled all conditions and obligations under the Contract and that MCD had breached
the agreement by failing to pay Sunesis for work performed under Payment Items 11
(concrete apron), 20 (concrete), 26 (concrete revetment), and 31 (patching concrete
structure). The company further alleged that it had performed additional concrete work
for which MCD had been unjustly enriched.
{¶ 12} In its answer, MCD asserted that Sunesis had been paid in full for the work
it performed and denied that Sunesis was entitled to any additional compensation. MCD
also asserted a counterclaim for expenses incurred due to Sunesis’s failure to complete
the Project on time.
{¶ 13} In December 2021, the parties agreed to Change Order #2, which modified
some aspects of the Project and increased the contract amount, but did not expressly
extend the July 30, 2020 completion deadline. The parties also signed an “Agreement
on Change Order #2” in which they agreed that the change order and the payment made
by MCD to Sunesis “shall not affect or impact, nor shall these actions act as a waiver of
the claims or defenses of Sunesis or MCD in the litigation.” O’Connor Dep., Ex. 12.
{¶ 14} After extensive discovery, Sunesis filed a motion for partial summary
judgment on Payment Item 31. MCD countered with its own motion for summary
judgment on all of Sunesis’s claims, as well as a motion for summary judgment on its
counterclaim. -6-
{¶ 15} On June 4, 2024, the trial court granted MCD’s motions and denied
Sunesis’s motion. The trial court found that the language of the contract was clear and
unambiguous as to the requirements and the manner of determining compensation:
compensation was to be determined by field measurements and the approval of the MCD
Engineer. The court further found that the contract provided that any disputes were to
be resolved by the MCD Engineer, whose decision was final and binding. The court
concluded that, because the Engineer did not approve the after-payment measurements
submitted by Sunesis, Sunesis was paid in conformity with the terms and conditions of
the contract. The trial court further found no dispute that Sunesis had failed to timely
complete the Project, causing MCD to incur additional costs of $110,319.82, plus an
additional amount not to exceed $3,590 for the expense of obtaining as-built drawings.
{¶ 16} Sunesis appeals from the trial court’s judgment, claiming that the trial court
erred in granting summary judgment to MCD and denying Sunesis’s motion for partial
summary judgment.
II. Summary Judgment Standard
{¶ 17} Pursuant to Civ.R. 56(C), summary judgment is proper when (1) there is no
genuine issue as to any material fact, (2) the moving party is entitled to judgment as a
matter of law, and (3) reasonable minds, after construing the evidence most strongly in
favor of the nonmoving party, can only conclude adversely to that party. Zivich v. Mentor
Soccer Club, Inc., 82 Ohio St.3d 367, 369-370 (1998). The moving party carries the
initial burden of affirmatively demonstrating that no genuine issue of material fact remains
to be litigated. Mitseff v. Wheeler, 38 Ohio St.3d 112, 115 (1988). To this end, the -7-
movant must be able to point to evidentiary materials of the type listed in Civ.R. 56(C)
that a court is to consider in rendering summary judgment. Dresher v. Burt, 75 Ohio
St.3d 280, 292-293 (1996).
{¶ 18} Once the moving party satisfies its burden, the nonmoving party may not
rest upon the mere allegations or denials of the party’s pleadings. Dresher at 293; Civ.R.
56(E). Rather, the burden then shifts to the nonmoving party to respond, with affidavits
or as otherwise permitted by Civ.R. 56, setting forth specific facts that show that there is
a genuine issue of material fact for trial. Dresher at 293. Throughout, the evidence
must be construed in favor of the nonmoving party. Id.
{¶ 19} We review the trial court’s ruling on a motion for summary judgment de
novo. Martcheva v. Dayton Bd. of Edn., 2021-Ohio-3524, ¶ 35 (2d Dist.). De novo
review means that this court uses the same standard that the trial court should have used,
and we examine all the Civ.R. 56 evidence, without deference to the trial court, to
determine whether, as a matter of law, no genuine issues exist for trial. Ward v. Bond,
2015-Ohio-4297, ¶ 8 (2d Dist.).
III. Relevant Legal Authority
{¶ 20} To prove a breach of contract claim, a party must establish (1) the existence
of a contract, (2) performance by the plaintiff, (3) breach by the defendant, and (4)
damage or loss to the plaintiff. Lexis Nexis, a Div. of Relx Inc. v. Murrell, 2022-Ohio-550,
¶ 21 (2d Dist.). In this case, it is undisputed that MCD hired Sunesis for the Project and
that Sunesis completed performance of Payment Items 11, 20, 26, and 31. See O’Connor
Dep. 46-48 (acknowledging that MCD accepted Sunesis’s work on Payment Items 11, -8-
20, 26, and 31). Sunesis asserts that MCD failed to pay in full for the work it performed.
{¶ 21} When reviewing a contract, the court’s primary role is to ascertain and give
effect to the intent of the parties. Tera, L.L.C. v. Rice Drilling D, L.L.C., 2024-Ohio-1945,
¶ 11; Hamilton Ins. Serv., Inc. v. Nationwide Ins. Cos., 86 Ohio St.3d 270, 273 (1999).
We presume that the intent of the parties is reflected in the contract’s language. Tera at
¶ 11; DiPasquale v. Costas, 2010-Ohio-832, ¶ 36 (2d Dist.). Courts will give terms their
plain and ordinary meaning unless another meaning is clearly apparent from the contents
of the agreement. Sunoco, Inc. (R&M) v. Toledo Edison Co., 2011-Ohio-2720, ¶ 37.
Technical terms will be given their technical meaning unless a different intention is clearly
expressed. Foster Wheeler Enviresponse, Inc. v. Franklin Cty. Convention Facilities
Auth., 78 Ohio St.3d 353, 361 (1997).
{¶ 22} A contract that is, by its terms, clear and unambiguous requires no real
interpretation or construction and will be given the effect called for by the plain language
of the contract. Aultman Hosp. Assn. v. Community Mut. Ins. Co., 46 Ohio St.3d 51, 55
(1989). On the other hand, “[a] contract is ambiguous where its meaning cannot be
ascertained from its terms or where it is susceptible to multiple reasonable
interpretations.” McGinnis v. Conley, 2024-Ohio-482, ¶ 13 (2d Dist.). Whether a
contract is ambiguous is a question of law. Tera at ¶ 12.
{¶ 23} A plain and unambiguous contract does not become ambiguous simply
because its operation will work a hardship upon one of the parties and a corresponding
advantage to the other. Dugan & Meyers Constr. Co., Inc., 2007-Ohio-1687, ¶ 29; Fifth
Third Bank W. Ohio v. Carroll Bldg. Co., 2009-Ohio-57, ¶ 14 (2d Dist.). It is not the -9-
province of courts to relieve parties of improvident contracts. Id. “[U]nless there is fraud
or other unlawfulness involved, courts are powerless to save a competent person from
the effects of his own voluntary agreement.” Id., citing Ullmann v. May, 147 Ohio St.
468, 476 (1947). These principles apply in cases involving a competitively bid public
construction contract. Dugan & Meyers at ¶ 30.
{¶ 24} Where the question before the court on summary judgment concerns
contract interpretation, “summary judgment may be granted when its words convey a
definite and precise meaning absent any ambiguity.” Bigham v. Deer Run Owners
Assn., 2024-Ohio-5233, ¶ 16 (2d Dist.), quoting Seiden Assocs., Inc. v. ANC Holdings,
Inc., 959 F.2d 425, 428 (2d Cir. 1992). But, where language is susceptible to differing
but reasonable interpretations, the meaning of the words become an issue of fact and
summary judgment is not appropriate. Id.; Wittstein v. Wittstein, 2006-Ohio-6707, ¶ 8
(12th Dist.). “Resolving the meaning of ambiguous terms in a contract is a matter of
factual determination for the fact-finder.” Tera at ¶ 19; Bigham at ¶ 16.
IV. Sunesis’s Claims
{¶ 25} Sunesis’s first and second assignments of error assert that the trial court
erred in granting summary judgment to MCD on Sunesis’s breach of contract claim for
additional payment for Payment Items 11, 20, 26, and 31.
A. Payment Item 31
{¶ 26} In its first assignment of error, Sunesis claims that the trial court erred in
granting summary judgment to MCD and denying Sunesis’s motion for partial summary
judgment on Payment Item 31 (concrete patching) for three reasons. First, it claims that -10-
the trial court erred in concluding that Sunesis failed to provide MCD with written field
measurements to support payment for concrete patching. Second, it argues that the trial
court erred in giving MCD’s Engineer “unbridled discretion” to resolve disputes regarding
whether Sunesis properly documented its work with field measurements. Third, Sunesis
asserts that the trial court improperly accepted MCD’s measurements to conclude that
Sunesis was not entitled to additional payment.
{¶ 27} Payment Item 31 concerned the demolition and patching of deteriorated
concrete on the upstream and downstream right spillway walls, which consisted of rows
of concrete blocks called monoliths. See Rayburn Aff, ¶ 4. It is undisputed that before
the Project began, there was only
one exposed face on the monoliths
to be patched, the channel or flow
face. See Doyle Dep. 63 & Ex. 79
(highlighting Monolith 4A on the
upstream wall). Per the Contract
Plans, prior to patching, Sunesis
removed the stair-stepped
uppermost level of the monoliths, exposing the horizontal side and a vertical side of the
monoliths to be repaired.
{¶ 28} Subpart 31.1 specified that the work included “removing all loose and
disintegrated existing concrete to sound concrete; preparing the surface; erecting and
removing concrete forms; supplying, placing, and finishing concrete; supplying and -11-
placing welded steel wire fabric, reinforcing steel and dowels; constructing the
hydrodemolition test section; and supplying and placing the bonding agent as shown on
the Plans and in accordance with ODOT 519.”
{¶ 29} Subpart 31.4 described the methods and processes for completing the
concrete patching. It explained that “[e]xisting concrete below the horizontal removal
limits or outside of the vertical removal limits, as specified on the Plans, is to be examined
for deteriorated concrete. Remaining concrete at these removal limits is to be sounded
with a hammer to reveal any hollow sounding areas that may be indicative of the onset of
concrete delamination. Any additional delaminated, loose, and deteriorated existing
concrete at the removal limits is to be removed by hydrodemolition to reach sound
concrete and to the approval of the ENGINEER before placement of any concrete
repairs.” Subpart 31.4. It further provided, in part:
During a pilot repair project for the concrete monoliths at the Lockington
Dam, estimates of repair depths were made based on 3D scans of the
concrete face after the removal of deteriorated concrete. The Lockington
Dam Pilot Concrete Repair Project report from February 23, 2018 noted an
average of 0.67 feet of deteriorated concrete removal from the monolith face
for the second monolith from the top of the wall.
Once the limits of sound concrete have been determined, install vertical
dowels as specified in Payment Item 19. Apply bonding agent to the final
concrete surface after removal of deteriorated concrete. Patch concrete
monoliths according to ODOT 519 and to match existing monolith -12-
dimensions and horizontal and vertical construction joints.
{¶ 30} Payment for the concrete patching was to be made at the Contract unit price
per square foot. Subpart 31.5. The agreed unit price was $197.25 per square foot.
See Doyle Dep., Ex. D10; O’Connor Dep., Ex. 2. As for measurement of the patches,
the Contract provided: “Measurement for Patching Concrete Structure shall be based on
the number of square feet of concrete patched on the spillways walls as measured in the
field at locations shown on the Plans. The CONTRACTOR shall provide field
measurements of the patched areas repaired and shall be verified by the ENGINEER
prior to payment.” (Emphasis added.) Subpart 31.5.
{¶ 31} The Contract included Plans which provided more details for completing the
work. Sheet 6 of the Contract Plans included a side-view diagram of a typical concrete
removal section with the monolith to
be completely removed and replaced
above and the monolith to be
patched below it. Sunesis’s Partial
MSJ, Ex. 5 (DLZ Ex. 3). Sheet 11,
entitled Concrete Sections and
Details, included a similar diagram with additional details and instructions. On both
sheets, the cross-hatched section of the lower monolith depicted the areas of “removal of
deteriorated concrete to sound concrete per Item 31 – Patching Concrete Structure.”
{¶ 32} Sheet 5, entitled Excavation and Demolition Plan, includes the limits of
hydrodemolition and concrete repair. Note 3 of the Sheet provides that the contract -13-
should perform hydrodemolition “to the limits shown on Sheet 10 and as shown on Table
1 of this sheet.” Table 1 provided the starting and end points, plus total feet, along the
northwest (upstream) and southwest (downstream) walls.
{¶ 33} Sheet 10, below, showed the horizontal and vertical removal limits for entire
concrete monolith removal and replacement, as well as the limits of concrete removal to
sound concrete and patching for existing monoliths. The diagram also included the
approximate volume of concrete to be removed in existing monoliths, and the lengths and
elevations of the spillway wall. The engineer’s estimate of the area of patching for
Payment Item 31 was consistent with the area of the channel face to be patched, as
shown on Sheet 10. Sheet 10 was later revised after it was found that the vertical
construction joints on the as-built plans were not accurate, and the estimated square
footage for Payment 31 was increased by the square footage of the additional channel
face to be patched.
{¶ 34} The parties disagree regarding what surfaces of the monolith were to be -14-
measured in determining the square footage of the patch for Payment Item 31. Sunesis
asserts that it should be paid for patching three faces of the monoliths – the channel, the
side, and the horizontal top. MCD counters that the patch is measured only on the
channel face.
{¶ 35} When Sunesis submitted its bid, it appears that both parties had the same
understanding of Payment Item 31. William Saxton, senior estimator for Sunesis,
reviewed the bid documents, visited the Lockington Dam, and prepared Sunesis’s bid for
the Project. He did not recall knowing about or seeing the pilot project report. Saxton
Dep. 22-23. Saxton used HeavyBid, a software program, to determine the company’s
total estimated costs by inputting whatever variables were needed for that section of the
job (what crew, how many people, what equipment, forming, etc.). As for Payment Item
31, he understood that 2,262 square feet was the estimated area to be patched at an
average depth of eight inches. When asked during his deposition if that area would be
the “flow face” or would include other potential areas that needed to be patched, Saxton
responded, “I assumed it was the – I guess you’re going to call it the flow face, the face
of the dam.” Saxton Dep. 31. He made that assumption because “it’s in square feet.”
Id. at 32.
{¶ 36} Robert Doyle, Vice President of Operations at Sunesis, soon had a different
view. Doyle attended a preconstruction meeting on October 9, 2019. At that time, he
understood, based on the detail provided in the Plans, that the 2,262 square feet to be
patched included the flow face and the top face. Doyle Dep. 97. Doyle had “no
assumption on the vertical face, but the vertical face was directed in the field by Kyle -15-
Sparks.” Id. at 97-98.
{¶ 37} Jeremy Rayburn, Jr., one of Sunesis’s foremen for the Project, was on site
daily, overseeing Sunesis’s work and working with Kyle Sparks, the field inspector from
DLZ. Rayburn Aff., ¶ 3. According to Rayburn, Sparks would sound the concrete on
the spillway walls to determine what concrete on the channel face, horizontal top face,
and vertical side face was deteriorated and needed to be removed. Rayburn Aff., ¶ 5.
Sounding is the process of striking the concrete surface and interpreting the sounds; solid
concrete produces a ringing sound, while deteriorated concrete produces a flat or hollow
sound. Rayburn Aff., ¶ 6.
{¶ 38} IVS, Sunesis’s hydrodemolition subcontractor, performed the
hydrodemolition on the spillway walls of the Lockington Dam, as directed by Sunesis.
Clark Aff. ¶ 5. According to Rayburn, photographs of the work show that, after the
surrounding monoliths were removed, hydrodemolition occurred on the channel face,
horizonal top, and vertical side of the monolith. See Rayburn Aff. ¶ 9 & Ex. A; Doyle
Dep. 63-67 & Ex. D79.
{¶ 39} IVS recorded contemporaneous
field measurements of all areas where it
performed hydrodemolition on the spillway
walls. Clark Aff., ¶ 4. It submitted seven
invoices to Sunesis for the work. Clark Aff.,
Ex. A. The first three invoices provided the total square footage of the hydrodemolition
it performed on the respective dates. The fourth invoice provided a total square footage -16-
with the notation “tops and sides.” The last three invoices provided the areas of
hydrodemolition for the front and top, as well as the sum of the two. IVS measured that
it had completed 4,605.11 square feet of hydrodemolition on the Project. Clark Aff., ¶ 6
& Ex. A.
{¶ 40} According to Rayburn, once the hydrodemolition was completed, his team
of Sunesis employees formed up and patched the areas of the spillway walls on all three
faces where the hydrodemolition had removed deteriorated concrete. Rayburn Aff.,
¶ 10. Rayburn stated that, throughout the project, he “measured the forms and ordered
an amount of concrete consistent with the measurements I had taken.” Rayburn Aff.,
¶ 11. Doyle indicated the same during his deposition, but he acknowledged that Sunesis
did not have the written field measurements and drawings for the patches. Sunesis
prepared a spreadsheet to calculate the square footage of concrete patches using “in-
place measurements . . . based off the plan sheets that were provided,” not field
measurements. Doyle Dep. 87-88 & Ex. D72. This calculation equaled 4,727.84
square feet. Doyle Dep., Ex. D72. McAfee equated the area of the patches to the
amount that was “hydrodemoed.” He testified that if he were measuring the patches, he
would look at the total area that was hydrodemoed, including the two vertical aspects and
the top. McAfee Dep. 61.
{¶ 41} In support of Sunesis’s claim for Payment Item 31, John Denniston, former
transportation manager for ODOT and a one-time employee of Sunesis, provided an
affidavit about concrete patching on ODOT projects. He stated that ODOT always paid
for concrete patching based on the square footage patched. Denniston Aff., ¶ 5. If -17-
multiple faces of a concrete structure were patched pursuant to ODOT 519, ODOT paid
the contract amount for the square footage of each face patched. Denniston Aff., ¶ 6-8.
However, while Payment Item 31 refers to ODOT 519 in terms of the method of
completing the work, the Contract does not adopt ODOT 519’s method of calculating
payment.
{¶ 42} In contrast to Sunesis’s interpretation, MCD and DLZ viewed the patch as
solely on the channel face. Steven Riedy of DLZ was the engineer of record on the
Project design and was heavily involved in engineering support during the construction
phase. He indicated that the engineer’s estimate for Payment Item 31 was based on the
square footage of the channel face only. When asked why it did not include the
horizontal face, he answered, “We didn’t envision patching or all of the elements that are
included in that patching payment item being necessary for the tops.” Riedy Dep. 51.
Riedy did not believe that patching actually occurred on the horizontal face: “Patching in
this instance for Item 31 involves several things, including bonding agent, doweling, wire
mesh, and concrete. And those things only occurred on the channel side face. And
hydrodemolition was a portion of that payment item as well.” Id. Riedy indicated that
Sheet 6 showed patching on the channel face of spillway wall and the patch extending
across the entire top horizontal face of the spillway wall below the monolith cap. Riedy
Dep. 62.
{¶ 43} O’Connor of MCD also interpreted the Plans as requiring one patch, to be
measured from the channel face only. He emphasized that it only took one patch to
replace the deteriorated concrete; “There was not a second patch and a third patch. It -18-
was one removal process and one patch.” O’Connor Dep. 59. Although deteriorated
concrete was removed from the top and side, “[a]ll the hydrodemolotion was achieved by
performing the work on the east [channel] face of the wall.” O’Connor Dep. 63. He
stated that there was no patching on the top and vertical side of the monoliths. Id. at 62.
{¶ 44} O’Connor’s interpretation was informed by ODOT 519, which addresses
payment for concrete patching on ODOT projects. O’Connor stated that, “[a]ccording to
ODOT 519[,] the measurement is based on exposed face of the wall. And that’s the
exposed – there’s only one exposed face of the wall and that’s that eastern face.”
O’Connor Dep. 57. MCD understood the exposed face to mean the face that was
exposed before or after construction, not during construction. Id.
{¶ 45} Kyle Sparks, DLZ’s observer engineer, was on-site and completed daily
inspection logs of the work performed. After the formwork was up for the concrete
patching but before the concrete was poured, he measured the width and height of the
formwork on channel side of spillway wall. Sparks Dep. 17-18. Sparks understood that
only one patch was performed on a monolith; he was told to measure the surface, and he
thought everything was included in that measurement. Id. at 78. Sparks explained: “It
was one pour, it’s surrounded on – there’s bulkheads on two sides, and there's form work
on the front side. It's one monolith patch in my mind.” Id. at 78. Sparks’s
measurements of the channel face patches totaled 2,204 square feet. Sparks testified
in his deposition that Sunesis did not do anything to confirm any of his measurements,
and he did not recall seeing Sunesis performing its own measurements. Id. at 72.
{¶ 46} In an email exchange in late March and early April 2021, O’Connor asked -19-
Sparks through Riedy about the hydrodemolition that IVS performed on the top and side
of the monoliths. Sparks indicated that IVS would spend approximately 5 to 15 minutes
“roughing up” the vertical joints and top surface of the monolith, depending on the length
and height of the monolith, not accounting for the corners of the face and side where there
was unsound concrete. DLZ Ex. 20; see also Sparks Dep. 40-41. Sparks further
indicated that concrete was poured across the entire top when the original horizontal
joints did not match up between adjacent monoliths; it was not due to hydrodemolition.
Id. O’Connor had indicated, and Sparks understood, that this concrete would be
accounted for with the monolith replacement. Id.
{¶ 47} The parties’ experts also had different interpretations of the Plans.
Sunesis’s expert, Eric Kohls, stated that “Drawings 6, 10, and 11 of 19 and the written
scope for Pay Item 31 clearly calls for the concrete removal and repairs on the vertical
and horizontal surface of the monoliths.” Kohls Expert Report, p. 5. He faulted MCD
for “ignor[ing] the sections of the work shown on drawing 6 & 11 that clearly show the
work on the horizontal surface and the direction in the field from DLZ for the work on the
other face.” Id., p. 6. Kohls also points out the MCD later altered its drawings in its
documents for its subsequent project concerning the left spillway walls. Id.
{¶ 48} In contrast, MCD’s expert, Joseph Troxell, disagreed that Sheet 6 showed
patching on the top surface. He testified, “I see it extends along the horizontal
construction joint, but I would interpret this to indicate that – and, again, based on the
reading of the description of Pay Item 31 in the specifications, that that needs to go as
deep as required in the field.” Troxell Dep. 38-39. Troxell’s understanding of Pay Item -20-
31 was that patching was all measured off of the channel face. Troxell Dep. 39. He
noted that all the reinforcing was on the channel face. Id. at 41, 45.
{¶ 49} Troxell further expressed that IVS’s field measurements were not a useful
measure of Pay Item 31, because it appeared that hydrodemolition was completed as
part of both Pay Item 31 and Pay Item 14. Troxell Apr. 7, 2023 Report, p. 6. He stated
that “[r]emoving unsound concrete on the face of the monolith is a part of work for Pay
Item 31. DLZ reports describe IVS using hydro demolition to ‘rough up’ the surfaces
against which new concrete would be cast. Demolition of those surfaces is paid for
under Pay Item 14 – Portions of Structure Removed, regardless of the means of
demolition.” Troxell Apr. 7, 2023 Report, p. 6.
{¶ 50} MCD completed 3D scans of the spillway walls, both after demolition was
completed and after repairs were done. The scans were provided to Sunesis, who
retained Berding Surveying to calculate the fill area for Payment Item 31. The Berding
report indicated 917.8 square feet of patching on the upstream wall and 1596.9 square
feet of patching on the downstream wall, totaling 2,514 square feet. Troxell believed the
scans were a useful measurement tool for Payment Item 31, although small areas of the
wall were not scanned. Kohls testified, however, that he believed Berding’s results were
inaccurate. Kohls Dep. 98-109.
{¶ 51} Both Sunesis and MCD assert that the Contract is clear and unambiguous
as to the scope of Payment Item 31. However, the record reflects that MCD and Sunesis
had reasonable but differing interpretations of Sheets 6, 10, and 11 of the Plans and,
consequently, of the scope of the hydrodemolition work that was required under Payment -21-
Item 31 and how the patching would be paid. While the documents, when construed in
Sunesis’s favor, supported Sunesis’s interpretation that the Specifications and Plans
showed patching on three faces, General Condition 8 squarely placed in the hands of the
Engineer the authority to resolve questions regarding interpretation of the Specifications
and Plans. Moreover, where the Contract documents conflicted, the Engineer’s
resolution of the inconsistency governed. GC-35.
{¶ 52} Sunesis argues that General Condition 8 related only to directing the
manner of work and not payment. However, the two issues are not easily separated, as
both parties rely heavily on the Specifications and Plans to support their positions. The
trial court did not err in concluding as a matter of law that, under the terms of the Contract,
the Engineer had the authority to resolve the dispute about what constituted a patch under
Payment Item 31 and, consequently, what face(s) were appropriately measured for
{¶ 53} The Engineer interpreted the Specifications and Plans as illustrating a
single patch to be measured from the channel face of the spillway walls. MCD paid
Sunesis based on the field measurements taken primarily by Sparks of the patching on
the channel face. Sunesis did not dispute the accuracy of those measurements.
Accordingly, the trial court did not err in determining that Sunesis was not entitled to
additional payment under Payment Item 31.
{¶ 54} Even if Sunesis were entitled to payment for the areas on top and side of
the monoliths where hydrodemolition occurred, there is no evidence that Sunesis
provided “field measurements” for Payment Item 31 to the Engineer prior to its requests -22-
for payment, as required by Subsection 31.5. Although Sunesis employees indicated
that they took measurements – length, height, and depth – to order concrete, Sunesis did
not provide its own field measurements for the patching to MCD. E.g., Doyle Dep. 68;
Riedy Dep. 134. Sunesis relies instead on IVS’s hydrodemolition invoices, arguing that
they were sufficient to constitute “field measurements of the patched areas repaired.”
However, the invoices contained the square footage calculated from IVS’s apparent
measurements, but not the measurements themselves. Most of the invoices did not
distinguish between square footage of the front, side, and top of the monoliths, and none
identified the monoliths that were hydro-demolished. Under the plain language of
Subsection 31.5, Sunesis did not demonstrate that it provided field measurements to
MCD.
{¶ 55} Finally, we note that genuine issues of material fact would have precluded
summary judgment in Sunesis’s favor even accepting Sunesis’s interpretation of the
Plans and assuming that the invoices were sufficient to establish the field measurements.
Although the IVS invoices provided the square footage of the hydrodemolition that
occurred, MCD presented evidence that the invoices included hydrodemolition that was
not associated with Payment Item 31.
{¶ 56} The trial court properly denied Sunesis’s motion for partial summary
judgment on Payment Item 31 and granted summary judgment to MCD on Payment Item
31. Accordingly, the first assignment of error is overruled.
B. Payment Items 11, 20, and 26
{¶ 57} In its second assignment of error, Sunesis claims that the trial court erred -23-
in granting summary judgment to MCD on Sunesis’s claims regarding Payment Items 11,
20, and 26. Those Payment Items concerned different aspects of the Project, but they
contained similar measurement and payment provisions.
{¶ 58} Payment Item 11 covered the construction of a concrete apron behind the
spillway walls. It included “erecting and removing concrete forms; supplying, placing,
and finishing concrete; and supplying and placing reinforced steel as shown on the
Plans.” Payment Item 11.1. The measurement and payment provision stated,
“Measurement for Concrete Apron shall be based on the number of cubic yards of
concrete in the concrete aprons behind the spillway walls based on the locations shown
on the Plans.” Payment Item 11.5.
{¶ 59} Payment Item 20, entitled Concrete, concerned the construction of
reinforced concrete monoliths at the tops of the spillway walls to replace the existing
concrete structures that were being removed. Measurement for Concrete was to be
based on “the number of cubic yards of concrete in the entire monoliths that are replaced
at the tops of the spillway walls based on the locations shown on the Plans.” Payment
Item. 20.5.
{¶ 60} Payment Item 26 concerned the construction of a concrete revetment
behind the spillway walls. Subpart 26.5 provided that “[m]easurement for Concrete
Revetment shall be based on the number of cubic yards of concrete placed as measured
by the computed volume based on the location shown on the Plans.”
{¶ 61} For each of these Payment Items, payment was to be made at the Contract
unit price per cubic yard for the Payment Item. Payment Items 11.5, 20.5, and 26.5. -24-
{¶ 62} On appeal, Sunesis contends that nothing in the Contract specified that the
payments for Payment Items 11, 20, and 26 must be based on field measurements. It
argues that it could rely on concrete delivery tickets and invoices provided by its supplier,
Spring Creek, for each Payment Item. Sunesis asserts that MCD itself proposed the use
of concrete delivery tickets to calculate the amount of concrete that was placed. Sunesis
thus claims that genuine issues of material fact exist as to the total cubic yards placed for
Payment Items 11, 20, and 26.
{¶ 63} Beginning with the contract language, we agree with Sunesis that the
language in Subsections 11.5, 20.5, and 26.5 did not specify that the payment for the
volume of concrete had to be based on field measurements. Unlike Subsections 9.5
(concrete headwall), 19.5 (dowel holes), and 31.5 (concrete patching), all of which linked
payment to measurements in the field, the measurement and payment provisions for the
apron, concrete, and revetment did not specifically require field measurements. And
while the disputed subsections did not specifically authorize payment based on concrete
tickets and/or invoices, neither did they indicate a specific method by which Sunesis was
to substantiate the amount of concrete it used to perform those tasks.
{¶ 64} MCD further emphasized in the trial court that Sunesis submitted 16 pay
applications but did not provide any of the concrete tickets and invoices during that
process. It argued that Sunesis was asserting an “alternative payment process” which,
if successful, would render the Contract Documents and related payment process
worthless. We disagree here, too.
{¶ 65} Nothing in the Contract required Sunesis to submit supporting -25-
documentation for Payment Items 11, 20, and 26 as part of its payment applications.
See GC-16 (partial payments). Rather, General Condition 16 instructed Sunesis to
provide the payment item number, description, contract unit price, quantity of work
completed for that time period, dollar amount of work completed, and dollar amount of all
payment items included. The pay application also had to include the project name, MCD
contract number, application number, application date, and period of work to date
completed. Unlike Payment Item 31, which required Sunesis to provide field
measurements for verification prior to payment, no similar language was included in
Subsections 11.5, 20.5, and 26.5.
{¶ 66} In addition, General Condition 16 stated that monthly payments were
approximates only, and all partial estimates and payments were subject to correction in
the final estimate and payment. Under General Condition 17, final submittals were due
60 days after MCD accepted the Project by a “Report of Final Inspection.” It is unclear
whether that has occurred.
{¶ 67} We therefore turn to whether genuine issues of material fact exist as to the
amount that Sunesis was entitled to receive for Payment Items 11, 20, and 26.
{¶ 68} In support of its motion for summary judgment, MCD presented evidence
that it paid Sunesis in full for Payment Items 11, 20, and 26 based on field measurements
and the agreed upon amounts in the change orders. MCD and DLZ interpreted the
payment items as providing for payment based on concrete actually placed, and Sparks
of DLZ took measurements in the field regarding each of the payment items. See
generally Sparks Dep.; Riedy Dep. 131-133. For the concrete apron, Sparks used a -26-
construction wheel to measure the surface area and calculated the volume using the
depth shown on the Plans. Sparks Dep. 21-22.
{¶ 69} Regarding Payment Item 20, Sparks testified that he measured the new
monoliths by getting inside the form work and measuring “at all of the corners at the
bottom side, both sides, and the top corners, and anywhere where it wasn’t a straight line,
where it would deviate, to try to break it up, monoliths into two different sections if I had
to.” Sparks Dep. 17,
{¶ 70} Steven Riedy, DLZ’s project manager for the Project, communicated with
O’Connor on April 30, 2020, about the quantity of concrete that was used for Payment
Item 20. Riedy explained that two things were constructed differently than the Plans with
authorization from MCD: Monolith 1 was replaced with a thicker section than shown on
the Plans, and Monolith 22A was replaced rather than patched. As a result, the concrete
volume for Payment Item 20 was revised to 704 cubic yards. Later, additional work was
performed because two other monoliths were found to be broken and field locations of
joints were found to be different from the Plans. Payment for the additional work on the
monolith replacement was included in Change Orders #1 and #2.
{¶ 71} With the revetment, Sparks stated that he used a measuring wheel and
measured the surface area, then multiplied the surface area by the agreed depth, and
separately accounted for the area with a greater depth. Sparks Dep. 18. O’Connor
recalled two discussions about concrete overages related to the revetments. He testified
during his deposition that the design for the upstream revetment had been changed, at
Sunesis’s request, so that it could be built more easily. O’Connor Dep. 53-54. As a -27-
result, there was a larger area for that portion of the revetment on the upstream end, but
it reduced the thickness of the concrete and the amount of reinforcement steel on the
concrete. Id. at 54.
{¶ 72} Robert Doyle, Vice President of Operations for Sunesis, agreed that the
Contract required “in place” quantities for payment. E.g., Doyle Dep. 30. He testified
that the Sunesis foreman took field measurements for Payment Items 11, 20, and 26, but
those measurements were not retained, and no written drawings or measurements could
be provided to MCD. Doyle Dep. 32-34, 40-41; see also McAfee Dep. 59-60. Neither
Riedy nor Sparks was aware of any measurements provided by Sunesis. Riedy Dep.
131-133; Sparks Dep. 72-75. Doyle further noted that field measurements for the
monoliths (Payment Item 20) would be difficult to obtain. Doyle Dep. 37.
{¶ 73} According to Sunesis’s expert, Kohls, however, one method of measuring
material used is calculating how much material was ordered and put into place. Kohls
Dep. 32. Doyle similarly testified that in-place concrete quantities could be demonstrated
with the amount that was delivered per the concrete tickets. Doyle Dep. at 31.
Rayburn, a foreman for Sunesis, substantiated that he and his team “measured the area
after the form work was placed for each area of the Project, including width, height, and
depth, if necessary, and ordered an amount of concrete consistent with the
measurements we had taken, in cubic yards.” Rayburn Aff., ¶ 5; see also Doyle Dep.
32-33. Doyle indicated that the order also included a five percent waste “because we
don’t want a cold joint. We don’t want to take a chance of losing the pure.” Doyle Dep.
58. Kohls indicated that five percent was a reasonable waste factor for the type of work -28-
that Sunesis was performing. Kohls Dep. 30.
{¶ 74} Sunesis received field tickets from its concrete supplier, Spring Creek,
detailing the amount of concrete Spring Creek delivered in each truck, in cubic yards.
Rayburn Aff., ¶ 7. The field tickets were also included in weekly invoices that Sunesis
received from Spring Creek. Id. at ¶ 8. Copies of the tickets and invoices were attached
to Rayburn’s affidavit.
{¶ 75} Sunesis’s requests for payment for Payment Items 11, 20, and 26 were
based on the concrete tickets, minus five percent for waste. Doyle Dep. 55-56. Using
that method, Sunesis originally calculated that it was owed for 15.25 cubic yards of
concrete for Payment Item 11, 62.29 cubic yards for Payment Item 20, and 85.53 cubic
yards for Payment Item 26. Doyle Dep. 122. Under Change Order #2, MCD
compensated Sunesis for an additional 4 cubic yards for Payment Item 11 and 24 cubic
yards for Payment Item 20. Sunesis has thus presented evidence that it is now owed for
(1) 11.25 cubic yards for Payment Item 11 at a unit cost of $546, for a total of $6,142.50,
(2) 38.29 cubic yards for Payment Item 20 at a unit cost of $1,058.75, for a total of
$40,539.54, and (3) 85.53 cubic yards for Payment Item 26 at a unit cost of $706, for a
total of $60,384.18. See Kohls Ex. Report, Summary of Damages.
{¶ 76} The record contains evidence from which a factfinder could conclude that
the concrete tickets, minus a five percent waste factor, were not an accurate
measurement of the concrete actually placed for Payment Items 11, 20, and 26.
O’Connor explained that concrete tickets “are created by the concrete company at their
plant and us, as project owners, don’t have control over how much concrete is put into -29-
the truck, how much concrete leaves the site in the truck, so there’s too much uncertainty
with tickets to use them as a reliable source of figuring quantities.” O’Connor Dep. 139-
140.
{¶ 77} Sparks also testified in his deposition that there was an unusual amount of
concrete waste on the Project. Sparks Dep. 27. He recalled a conversation with Dave
Koontz, the foreman for the upstream wall portion, in which Koontz indicated that he would
order a minimum of three cubic yards, even if less were needed, because Sunesis only
got paid for what was placed and there were fees for having less than three cubic yards
of concrete. Id. at 27-28.
{¶ 78} In a March 2021 email to McAfee, O’Connor challenged Sunesis’s use of a
five percent waste factor. O’Connor indicated that he had taken a “random sampling of
concrete items poured and checked the concrete truck tickets and field measurements
for each pour.” O’Connor Dep. 141-142 & Ex. 29. After sampling ten total pours from
concrete monoliths, concrete aprons, and concrete revetment, he found that the average
concrete waste was 18.6 percent, the lowest waste of those ten was 2.6 percent, and the
highest was 28.2 percent.” Id. He surmised that “[t]his could be a combination of
ordering too much and/or placing too much depth on things like aprons and revetment,”
but reiterated that the “concrete tickets are not sufficient evidence for me to pay for more
quantity than was designed or measured in the field.”
{¶ 79} MCD’s evidence raises questions about the validity of Sunesis’s use of the
volume reflected on Spring Creek’s concrete tickets and invoices and of a five percent
waste factor. However, it is the role of a factfinder to determine the credibility of the -30-
parties’ evidence on the compensable amount of concrete, not the role of the court upon
a motion for summary judgment. (We note that the parties have agreed to the trial judge’s
serving as the trier of fact in this case. See Agreed Entry Transferring Case, June 13,
2022.). We thus conclude that the trial court erred in granting summary judgment to
MCD on Sunesis’s claims on Payment Items 11, 20, and 26, and that the matter must be
remanded for further proceedings on these payment items.
{¶ 80} Sunesis’s second assignment of error is sustained.
V. MCD Counterclaim
{¶ 81} In its third assignment of error, Sunesis claims that the trial court erred in
granting summary judgment to MCD on MCD’s counterclaim for construction delay
damages. It argues that MCD delayed the Project’s completion by substantially
changing the plans and specifications and that, under United States v. Spearin, 248 U.S.
132 (1918), it should not be liable for the delays.
{¶ 82} According to the Contract, Sunesis was required to complete the Project
within 180 calendar days, unless the period for completion was changed by written
Change Order. General Condition-11 gave MCD the right to withhold amounts if the
Project were not completed timely. It read, in part:
It is mutually agreed by and between the parties hereto that time is an
essential part of this Contract, and if the CONTRACTOR shall fail to carry
on the work with such force and in such manner and order, and at such
points, within the time set out in its Proposal, . . . MCD may retain from the
monies that are due, or which may become due said CONTRACTOR, -31-
MCD's estimated daily cost of the completed work, for each and every
calendar day the completion of the work be delayed beyond the time
specified herein for such completion; or such extensions thereto as may be
approved in writing by MCD upon written request from the CONTRACTOR.
The CONTRACTOR shall not be entitled to a bonus for early completion.
CONTRACTOR acknowledges that time is of the essence. By this it is
meant that the maintenance of construction schedules is critical to the
success of the Project. Accordingly, CONTRACTOR hereby agrees that if
its performance hereunder is not completed within the time provided for
completion, it shall reimburse and indemnify MCD for and against any and
all loss and expense of any and every kind, whether direct or consequential,
including reasonable attorney fees.
GC-11.
{¶ 83} General Condition-15 expressly addressed extensions of time. It provided:
Delays due to causes beyond the control of the CONTRACTOR, other than
such as reasonably would be expected to occur, may entitle the
CONTRACTOR to an extension of time; however, the CONTRACTOR
declares that it has familiarized itself with weather and local conditions and
other circumstances which may, or are likely to, affect the performance and
completion of the work, and agrees that it will prosecute the work in such
manner that it will be completed without undue delay, even though the most
adverse conditions which reasonably could be expected to occur do prevail -32-
during the performance of the work.
...
No extension of time shall be granted for any cause, unless the
CONTRACTOR shall within 15 days from the initiation of the delay, notify
the ENGINEER in writing of such delay, and of its cause and time of
beginning, and the CONTRACTOR’s assessment of the extent of the delay,
and the ENGINEER will make an independent assessment. If the
ENGINEER agrees to grant a time extension, MCD will issue a Change
Order amending the Contract completion date.
The CONTRACTOR shall pay or, to have deducted from the Contract price,
the actual amount of the inspection and Contract administration costs for
each day past the final completion date in the Contract, plus additional days
agreed to for approved Change Orders. The cost for the inspection and
Contract administration services will be based on invoices paid by MCD for
such services.
{¶ 84} The parties agree that the initial completion date was April 11, 2020. The
parties further agree that the construction delays occurred, although they differ as to the
causes of the delays and their effect on the completion date.
{¶ 85} O’Connor of MCD stated in his deposition that Sunesis did not get started
right away and it had issues determining how to start the Project, such as how to access
the wall. O’Connor Dep. 34. O’Connor also attributed Sunesis’s delays to a lack of
crew and equipment. He explained, “It seemed like there were times when they could -33-
have had more people and more equipment on site to finish things quicker. And then
toward the end of the project especially there [were] long periods where they were not on
site at all and they would come back periodically. They didn’t work consistently through
to completion.” O’Connor Dep. 36.
{¶ 86} Riedy of DLZ agreed that the project took longer than anticipated. Riedy
Dep. 36. He also testified that Sunesis “didn’t appear to show up with a plan to execute
the work” and “[i]t appeared they were trying to figure out how to best approach the work
once they got on-site.” Riedy Dep. at 36.
{¶ 87} Throughout the Project, the parties communicated by email. In addition,
regular progress meetings were held with representatives from MCD, Sunesis, DLZ, and
the Ohio Department of Natural Resources (ODNR). See O’Connor Dep., Ex. 16. Early
in the Project, it became clear that the location of the major vertical joints in the wall
deviated from those depicted on the construction documents. On November 13, 2019,
demolition was delayed due to this discrepancy, and McAfee, project manager for
Sunesis, provided written notice to MCD that it was tracking the loss of productivity due
to this issue. McAfee Dep., Ex. D93; Sparks Dep. 37. On November 14, 2019, Riedy
of DLZ provided O’Connor a Revised Sheet 10 depicting concrete monolith removal limits.
He also informed O’Connor of the consequent increased quantities for Payment Items 14,
20, and 31. Riedy Dep., Ex. 5 & 6. Design Sheet 11 also needed to be revised. In
January 2020, Sunesis reported some delays due to high water; the access road was
under water and water had to be pumped out.
{¶ 88} O’Connor’s notes from the February 5, 2020 progress meeting indicated -34-
that, at that point, the parties anticipated a July completion date. At the meeting, Sunesis
shared its reasons for the delays, including (1) an early learning curve related to the
means and methods because of the unique nature of this project; (2) Sunesis was not
comfortable with the bridge bracket approach to access the front of the spillway wall; (3)
the upstream section of the wall needed more concrete depth removed by
hydrodemolition than expected; (4) high water events affected lift access and access to
the lower sections of the wall; (5) additional monolith removal and replacement at the
bottom of the wall required continuous pumping, more excavation, and was affected by
even minor rises in the creek level; (6) the sheet 10 redesign delayed the start of concrete
work; (7) multiple reinforcing steel redesigns; (8) temperatures were too cold for
hydrodemolition at times; (9) a change in hydrodemolition methods (to using a wand),
which takes longer; (10) some rain days led to mud and access issues; and (11) the
hydrodemolition sounding process. O’Connor Dep., Ex. 20. MCD asked Sunesis to
attempt to assign days of delay for the reasons they provided. Id.
{¶ 89} On February 24, 2020, McAfee sent a letter to O’Connor itemizing the
delays and calculating 79 days of delay due to those factors. O’Connor Dep. Ex. 22.
Sunesis’ estimated completion date was July 30, 2020. Id. O’Connor and Riedy agreed
that some of Sunesis’s reasons for delay were valid, but they did not agree with all of
them. O’Connor Dep. 120; Riedy Dep. 93-97.
{¶ 90} On June 16, 2020, the parties approved Change Order #1, dated June 10,
2020. See Sunesis’s Opposition to MSJ on MCD’s Counterclaim, Ex. 1; Kohls Dep., Ex.
2. Under this change order, Plan Sheets 10 and 11 were replaced with Plan Sheets 10R -35-
and 11R, the contract completion date was extended by 110 days, and Sunesis was
compensated for additional concrete sawing and for changes to the cofferdam and
continuous dewatering for Monoliths 1B and 1C. Change Order #1 explained that the
contract date was extended by 110 days “due to low winter temperatures, high water
events, and changes to the work.” The completion date for all work was revised to July
30, 2020. Change Order #1 granted an extension of time for whatever the excusable
delays were at that time. O’Connor Dep. 122.
{¶ 91} Sunesis states that it performed additional work at MCD’s request after
Change Order #1. According to Sparks’s daily inspection log, on August 26, 2020,
Sunesis graded the flat area above the creek slopes at and upstream of the northwest
concrete revetment per MCD’s request from MCD’s last on-site visit. Sunesis’s
Opposition to MSJ on MCD’s Counterclaim, Ex. 2. On August 28, 2020, Sunesis
installed an additional keyway on Monolith 48. Id., Ex. 3. The daily inspection log for
August 28 reflects that this work took approximately 120 minutes to complete. Id.
{¶ 92} In December 2021, after Sunesis had substantially completed its work and
after litigation had begun, the parties agreed to a second change order. See, e.g., Doyle
Dep., Ex. D-76; Kohls Dep., Ex. 3. Change Order #2 approved additional payment for
the concrete apron, rocket channel protection, concrete, and fencing. It also included
payment for removal of draft at the upstream end of the dam conduits, installation of some
reinforcing steel, installation of dowels on some small monoliths, installation of a concrete
walk, and fabrication and installation of an aluminum staff board on the upstream right
wall. The Contract price increased by $54,162. Nothing was written in the area where -36-
the parties would indicate how much the Contract Time would change. Change Order
#2 again indicated that the date of completion for all work would be July 30, 2020.
Sunesis’s corporate secretary signed Change Order #2 on March 5, 2022; O’Connor
signed Change Order #2 for MCD on March 8, 2022, and MCD’s general manager signed
it the next day.
{¶ 93} In his deposition, Doyle admitted that Change Order #2 did not include a
revised completion date. He nevertheless testified, “It is to be assumed that if you do
additional quantities of work, it should be implied that there’s additional time to complete
those additional quantities.” Doyle Dep. 52. O’Connor stated that MCD intentionally
kept the July 30, 2020 completion date as part of Change Order #2 even when the
completion date had already passed. O’Connor Aff., ¶ 25.
{¶ 94} Sunesis’s expert, Eric Kohls, also opined in his report and testified in his
deposition that MCD did not substantiate its counterclaim for delay. Kohls Ex. 1. He
expressed that MCD had agreed to a time extension of 110 days in Change Order #1,
and the “remaining 93 days in its claim should be an excused delay to Sunesis for the
Project due to the issues, including but not limited to the following:
1. Additional work agreed to in CO #2.
2. Additional work for the disputed quantities increases in Sunesis’s Claim . . .
3. Unforeseen conditions associated with the monolith 1B and 1C due to cracking
below grade. To correct this issue, our cofferdam had to be modified and
additional dewatering was required.
4. The vertical joints between the monoliths were not in accordance with the plan -37-
documents. MCD ordered Sunesis to stop hydro-demolition activities until the
joints could be mapped and a revised plan be developed.”
Kohls Ex. 1, p. 7. Kohls believed that Change Order #2 was irrelevant in terms of the
delay issue. Kohls Dep. 52.
{¶ 95} When construing the evidence in the light most favorable to Sunesis, no
genuine issue of material fact exists that Sunesis failed to complete the Project by the
July 30, 2020 deadline. Sunesis’s own evidence unequivocally demonstrated that
Sunesis had not completed the Project by July 30, 2020. Exhibit 2 to Sunesis’s
memorandum in opposition to MCD’s motion for summary judgment on the counterclaim
showed not only the additional work that MCD asked it to do, but also that Sunesis
performed work due to damage that it had caused to piezometer main trunkline conduit
and other work required by the Contract. Sunesis’s Exhibit 3 to its opposition
memorandum similarly showed that Sunesis was continuing to perform tasks required by
the Contract. Moreover, other daily inspection logs from July 30, 2020, and later
substantiated that a significant amount of work remained to be done on the Project after
July 30, 2020. O’Connor Dep., Ex. 15.
{¶ 96} Sunesis argues on appeal, as it did in the trial court, that MCD delayed the
Project’s completion by substantially changing the plans and specifications and that the
Spearin Doctrine thus applies. Sunesis also asserts that much of the additional scope
of work for the Project was caused by the inaccurate bid quantities provided by MCD,
which could not have been discovered through any pre-bid inspection.
{¶ 97} In Spearin, the United State Supreme Court recognized that when a -38-
contractor is “bound to build according to plans and specifications prepared by the owner,
the contractor will not be responsible for the consequences of defects in the plans and
specifications.” Spearin, 248 U.S. at 136. However, the Ohio Supreme Court has
declined to extend the Spearin doctrine to disputes about construction delays. See
Dugan & Meyers Constr. Co., 2007-Ohio-1687. Moreover, it has held that the Spearin
Doctrine does not invalidate an express contractual provision. S & M Constructors, Inc.
v. Columbus, 70 Ohio St.2d 69, 75 (1982).
{¶ 98} The Ohio Supreme Court addressed the Spearin Doctrine in Dugan &
Meyers. Dugan & Meyers involved claims arising from a contractor’s failure to complete
construction of three buildings on the Ohio State University campus within the 660 days
required by the contract. The State removed the lead contractor due to the delays and
had the completion overseen by another contractor. When the original contractor sought
payment under the contract, the State deducted the amount paid to the second lead
contractor and also assessed liquidated damages for the delay, as permitted by the
contract. The original lead contractor sued for breach of contract and unjust enrichment,
claiming that the delay was due to deficiencies in the plans provided by the State, delays
caused by the State, and additional work outside the contract that it had been required to
complete. The State counterclaimed for delay damages.
{¶ 99} The Ohio Supreme Court distinguished Spearin, stating that Spearin
involved the existence of a site condition that precluded completion of the construction
project whereas the case before it concerned the allocation of damages flowing from
delay in completion of a construction project due to plan changes. The Court declined -39-
to extend the Spearin Doctrine from job-site-conditions cases to cases involving delay
due to plan changes. (Citations omitted.) Dugan & Meyers at ¶ 27-28. The supreme
court emphasized that the OSU construction contract had included terms that addressed
the contractor’s remedy when changes were made to the plans.
{¶ 100} The Spearin Doctrine does not apply here. Completion of the Project was
not precluded by conditions at the Lockington Dam, and MCD’s Plans and Specifications
were not so defective that Sunesis could not successfully complete the Project. Rather,
as with Dugan & Meyers, this matter concerns delays resulting, in part, from changes to
the Plans and Specifications.
{¶ 101} In its responses to MCD’s first set of interrogatories (Ex. D-59), Sunesis
identified several reasons for why it did not complete the Project by April 11, 2020, and
again by July 30, 2020. See Answers to Interrogatories 6 & 7. Sunesis’s expert, Eric
Kohls, also cited four reasons why Sunesis’s failure to complete the Project by the
completion date was excused. Many of the circumstances that Kohls and Sunesis
pointed to occurred prior to Change Order #1. These included unforeseen conditions
associated with Monolith 1B and 1C, inaccuracies in the Plan documents regarding the
vertical joints, abnormally cold winter temperatures, flood events, and additional
quantities performed on contract items. Through Change Order #1, the parties agreed
to extend the completion date from April 2020 to July 30, 2020. It expressly stated that
the extension was due to “low winter temperatures, high water events, and changes to
the work.” As a matter of law, Sunesis cannot rely on events prior to Change Order #1
to support an equitable extension of the July 30, 2020 completion date. -40-
{¶ 102} It is undisputed that, after July 30, 2020, MCD asked Sunesis to perform
tasks that were not included in the Contract. Sunesis stated in its interrogatory
responses that the additional work included drift removal, additional reinforcement and
design changes in the poured revetment, additional vertical dowels on the monoliths, the
addition of a 4” concrete walk, and the addition of an aluminum staff board. Rayburn
also detailed additional work concerning Monolith 51A, the concrete apron, and other
specific projects. Rayburn Aff., ¶ 10-15 and Exs. B & C. Sunesis has not detailed how
much delay was associated with these additional items. Sunesis also attached two daily
inspection logs to its memorandum in opposition to summary judgment on MCD’s
counterclaim, which showed that the two items were performed in August 2020; the logs
show that those items took minimal time to complete.
{¶ 103} MCD cites to Foster Wheeler Enviresponse, 78 Ohio St.3d 353 (1997), to
support its assertion that Sunesis was required to obtain a written change order to alter
the completion date of the Project. In that case, a hazardous waste remediation
contractor agreed to excavate and transport 140 cubic yards of contaminated material
from the construction site of the Greater Columbus Convention Center. After more
contaminated material was found, the contractor sought compensation for its removal of
the additional material. Summary judgment was granted to the public agency and its
environmental consulting firm, and the contractor appealed. The Tenth District reversed
as to the public agency, concluding that written authorization was required only for a
change in the scope of work.
{¶ 104} On review, the Ohio Supreme Court reinstated the grant of summary -41-
judgment to the public agency. Initially, it noted that “[i]t is universally recognized that
where a building or construction contract, public or private, stipulates that additional,
altered, or extra work must be ordered in writing, the stipulation is valid and binding upon
the parties, and no recovery can be had for such work without a written directive therefor
in compliance with the terms of the contract, unless waived by the owner or employer.”
Id. at 360. It further stated that “in the absence of express authority, an engineer,
architect, superintendent or inspector in charge of or assigned to public building or
construction work has no power to waive or modify a stipulation requiring a written order
for alterations, even where that person may authorize alterations in writing.” Id. at 364.
{¶ 105} After applying well established canons for the interpretation of contracts,
the supreme court concluded that the contract required a change order for the change in
quantity. It commented that the “primary purpose of requiring written authorization for
alterations in a building or construction contract is to protect the owner against unjust and
exorbitant claims for compensation for extra work. It is generally regarded as one of the
most effective methods of protection because such clauses limit the source and means
of introducing additional work into the project at hand. It allows the owner to investigate
the validity of a claim when evidence is still available and to consider early on alternative
methods of construction that may prove to be more economically viable. It protects
against runaway projects and is, in the final analysis, a necessary adjunct to fiscal
planning.” Id. at 363-64.
{¶ 106} We agree with MCD that Sunesis was bound by the contractual provisions
regarding change orders, delays, and extensions of time. For Sunesis to be -42-
compensated for the additional work that it was asked to perform, the parties needed to
agree to a change order encompassing that work. And, to the extent that the additional
work would affect the existing completion date, the parties should have negotiated a
modified completion date as part of the change order.
{¶ 107} As to other reasons for delay, the Contract required Sunesis to provide
written notice of delays. Specifically, General Condition 15 required Sunesis to notify the
Engineer in writing within 14 days from the initiation of a delay of (1) the cause of the
delay, (2) when it began, and (3) the contractor’s assessment of the extent of the delay.
Sunesis did not provide MCD written notice of any delay occurring after July 30, 2020,
nor did it seek an extension of time in writing. Accordingly, as a matter of law, Sunesis
was not entitled to an extension of time beyond July 30, 2020.
{¶ 108} The third assignment of error is overruled.
VI. Conclusion
{¶ 109} The trial court’s judgment will be affirmed in part, reversed in part, and
remanded for further proceedings on Payment Items 11, 20, and 26.
WELBAUM, J. and LEWIS, J., concur.
Related
Cite This Page — Counsel Stack
2025 Ohio 116, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-miami-conservancy-dist-ohioctapp-2025.