In re Miami Conservancy Dist.

2025 Ohio 116
CourtOhio Court of Appeals
DecidedJanuary 17, 2025
Docket30193
StatusPublished
Cited by1 cases

This text of 2025 Ohio 116 (In re Miami Conservancy Dist.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re Miami Conservancy Dist., 2025 Ohio 116 (Ohio Ct. App. 2025).

Opinion

[Cite as In re Miami Conservancy Dist., 2025-Ohio-116.]

IN THE COURT OF APPEALS OF OHIO SECOND APPELLATE DISTRICT MONTGOMERY COUNTY

IN THE MATTER OF: THE MIAMI : CONSERVANCY DISTRICT : : C.A. No. 30193 : : Trial Court Case No. 36847 : : (Civil Appeal from Common Pleas : Court) : :

...........

OPINION

Rendered on January 17, 2025

JASON P. CONTE & EMILY H. DAVIS, Attorneys for Appellant

GREGORY J. DEGULIS & LEE A. SLONE, Attorneys for Appellee

.............

EPLEY, P.J.

{¶ 1} Sunesis Construction Company appeals from the trial court’s judgment

overruling Sunesis’s motion for partial summary judgment and granting summary

judgment to the Miami Conservancy District (MCD) on Sunesis’s claims and on MCD’s

counterclaim. For the following reasons, the trial court’s judgment will be affirmed in part, -2-

reversed in part, and remanded for further proceedings regarding Payment Items 11, 20,

and 26.

I. Facts and Procedural History

{¶ 2} The following facts are undisputed. The MCD, established after the 1913

flood, is a public organization responsible for flood protection in the Great Miami River

watershed. Between 1918 and 1922, MCD constructed five dry dams along major

waterways – the Lockington, Germantown, Englewood, Taylorsville, and Huffman Dams.

{¶ 3} Given the technology at the time, the

concrete used in the dams’ construction was highly

susceptible to deterioration from freezing and

thawing in the presence of moisture. Over time, it

has suffered deterioration in the form of cracking,

spalling, and delamination. Some surface repairs were performed in the 1970s using

shotcrete, but those repairs have delaminated as well and the original concrete has

continued to deteriorate. See O’Connor Dep., Ex. 10. Due to the dams’ aging

infrastructure, MCD had a pilot concrete repair project performed on the southwest

abutment wall (downstream right side, when looking downstream) of the Lockington Dam

in 2017, with a report issued in February 2018. Id.

{¶ 4} In 2019, MCD sought bids for the Lockington Dam Right Wall Drain System

and Concrete Repair Project (“the Project”), Contract No. 2019-021C, which primarily

focused on repairing the right spillway walls. On October 11, 2019, MCD hired Sunesis

for the Project; the original agreed cost was $2,614,347. MCD Motion for Summary -3-

Judgment (MSJ), Ex. K. MCD subsequently agreed to pay an additional $62,896.84 in

two change orders. MCD MSJ, Ex. L.

{¶ 5} The Contract consisted of several complementary documents. General

Condition 35 set forth an order of precedence for the contract documents: (1) Contract,

(2) Change Orders, (3) Addenda, (4) Detailed Specifications, (5) Plans/Drawings, (6)

General Conditions, (7) Proposal, (8) Instructions to Bidders, (9) Other documents

specifically referenced in the Contract, and (10) ODOT Specifications. In the event of a

conflict between the documents, the interpretation of MCD’s Engineer governed. GC-

35.

{¶ 6} Sunesis’s tasks were delineated in 35 Payment Items, which were part of the

Detailed Specifications. For each Payment Item, the Contract provided a general

description of the work to be performed, a description of any required submittals, any

material requirements, any required methods and processes, and instructions on

measurement and payment. Final payment for the contract was based on “actual

quantities realized and unit prices of payment items.” GC-17 (Final Payment); O’Connor

Dep. 46.

{¶ 7} The Contract also contained 36 General Conditions. Of particular relevance

here, GC-8 provided:

GC-8. Direction of Work and Interpretation of Plans and Specifications

It is mutually agreed that the ENGINEER shall have the right to direct the

manner in which all work under this Contract is to be conducted, insofar as

may be necessary to secure the safe and proper progress and quality of the -4-

work. Upon all questions concerning the execution of the work,

interpretation of the Specifications and Plans, determination of all quantities

and amounts of work done, the decision of the ENGINEER shall be final

and binding on both parties, and compliance with its estimates and

decisions shall be a condition precedent to the right of the CONTRACTOR

to receive any payment under the Contract.

(Emphasis added.) The term “Engineer” was defined as MCD’s Chief Engineer or

properly authorized agents. GC-1 (Definitions). It included the terms “owner’s

representative,” “project manager,” and “consultant.” Throughout the contract, Donald

O’Connor served as project manager for MCD.

{¶ 8} Sunesis agreed to begin work within 10 days after the date of the Notice of

Commencement and to complete the Project within 180 days, unless extended by a

written change order. The initial project completion date was April 11, 2020.

{¶ 9} A week after contracting with Sunesis, MCD hired DLZ, its design engineer

consultant, to provide construction administration, concrete and materials testing, and as

needed construction-phase engineering services. MCD MSJ, Ex. B. O’Connor testified

that he and DLZ were the “Engineer” for the Project. O’Connor Dep. 45. For the

majority of the time, Kyle Sparks of DLZ served as an observer engineer, documenting

what happened each day, taking measurements, and performing testing. MCD’s

contract with DLZ expired prior to the completion of the project. At that point, Jim Kittel

of MCD assumed Sparks’s role. O’Connor Dep. 26.

{¶ 10} By a written change order in June 2020, the Project deadline was extended -5-

to July 30, 2020. Sunesis substantially completed its work in the spring of 2021.

{¶ 11} On November 12, 2021, Sunesis filed suit against MCD, raising claims of

breach of contract, unjust enrichment, and promissory estoppel. Sunesis alleged that it

had fulfilled all conditions and obligations under the Contract and that MCD had breached

the agreement by failing to pay Sunesis for work performed under Payment Items 11

(concrete apron), 20 (concrete), 26 (concrete revetment), and 31 (patching concrete

structure). The company further alleged that it had performed additional concrete work

for which MCD had been unjustly enriched.

{¶ 12} In its answer, MCD asserted that Sunesis had been paid in full for the work

it performed and denied that Sunesis was entitled to any additional compensation. MCD

also asserted a counterclaim for expenses incurred due to Sunesis’s failure to complete

the Project on time.

{¶ 13} In December 2021, the parties agreed to Change Order #2, which modified

some aspects of the Project and increased the contract amount, but did not expressly

extend the July 30, 2020 completion deadline. The parties also signed an “Agreement

on Change Order #2” in which they agreed that the change order and the payment made

by MCD to Sunesis “shall not affect or impact, nor shall these actions act as a waiver of

the claims or defenses of Sunesis or MCD in the litigation.” O’Connor Dep., Ex. 12.

{¶ 14} After extensive discovery, Sunesis filed a motion for partial summary

judgment on Payment Item 31. MCD countered with its own motion for summary

judgment on all of Sunesis’s claims, as well as a motion for summary judgment on its

counterclaim. -6-

{¶ 15} On June 4, 2024, the trial court granted MCD’s motions and denied

Sunesis’s motion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

RYS Holdings, L.L.C. v. Virus Gaming Network, L.L.C.
2025 Ohio 2261 (Ohio Court of Appeals, 2025)

Cite This Page — Counsel Stack

Bluebook (online)
2025 Ohio 116, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-miami-conservancy-dist-ohioctapp-2025.