In Re MDL-1824 Tri-State Water Rights Litigation

644 F.3d 1160, 2011 WL 2536507
CourtCourt of Appeals for the Eleventh Circuit
DecidedJune 28, 2011
Docket09-14657
StatusPublished
Cited by18 cases

This text of 644 F.3d 1160 (In Re MDL-1824 Tri-State Water Rights Litigation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re MDL-1824 Tri-State Water Rights Litigation, 644 F.3d 1160, 2011 WL 2536507 (11th Cir. 2011).

Opinion

644 F.3d 1160 (2011)

In Re MDL-1824 TRI-STATE WATER RIGHTS LITIGATION.
State of Alabama, Alabama Power Company, State of Florida, Plaintiffs-Appellees,
v.
United States Army Corps of Engineers, John M. McHugh, Secretary of the Army, et al., Defendants-Appellees Cross-Appellants.
State of Georgia, Gwinnett County, Georgia, et al., Plaintiffs-Appellants Cross-Appellees,
v.
United States Army Corps of Engineers, John M. McHugh, in his official capacity as Secretary of the United States Army, et al., Defendants-Appellees Cross-Appellants.
City of Apalachicola, Florida, Plaintiff-Appellee,
v.
United States Army Corps of Engineers, John M. McHugh, Secretary of the Army, et al., Defendants-Appellees Cross-Appellants. *1161
Southeast Federal Power Customers, Inc., City of Apalachicola, Florida, Plaintiffs-Appellees,
v.
United States Army Corps of Engineers, John M. McHugh, Secretary of the Army, et al., Defendants-Appellees Cross-Appellants.

No. 09-14657.

United States Court of Appeals, Eleventh Circuit.

June 28, 2011.

*1164 Seth Paul Waxman, Christopher E. Babbit, Joshua M. Salzman, Washington, DC, Allen M. Brabender, U.S.Dept. of Justice, ENRD, Paul R.Q. Wolfson, Wilmer Cutler Pickering Hale and Dorr, Washington, DC, Patricia T. Barmeyer, Lewis B. Jones, King & Spalding, William Middleton Droze, Natalie Diamond Sacha, Troutman Sanders, R. Todd Silliman, Bruce Perrin Brown, John Curtis Allen, McKenna, Long & Aldridge LLP, Angela Jean Levin, Atlanta, GA, Clyde Y. Morris, Jr., Gainesville, GA, for Appellant.

Michael T. Gray, U.S.Dept. of Justice, ENR, App. Sect., Karen A. Sealy, Clinton A. Vince, Orlando E. Vidal, SNR Denton US LLP, James T. Banks, Hogan & Hartson, L.L.P., Washington, DC, Matthew H. Lembke, Bradley, Arant, Rose & White, LLP, Joel M. Kuebnert, Jess R. Nix, Bradley, Arant, Boult, Cummings, LLP, W. Larkin Radney, IV, William S. Cox, III, Lightfoot, Franklin & White, L.L.C., Thomas Lee Casey, III, Specer M. Taylor, Balch & Bingham, LLP, Birmingham, AL, Parker D. Thomson, Hogan & Hartson, LLP, Natalie N. Barefoot, Hogan Lovells US, Miami, FL, James A. Byram, Jr., Balch & Bingham, LLP, Montgomery, AL, Christopher M. Kise, Foley & Lardner, Tallahassee, FL, Donald G. Blankenau, Thomas R. Wilmoth, Blankenau Wilmoth LLP, Lincoln, NE, J. Patrick Floyd, Port St. Joe, FL, for Appellee.

*1165 C.B. Rogers, Thomas J. Mew, IV, Robert B. Remar, Richard H. Sinkfield, Rogers & Hardin, LLP, Atlanta, GA, Mary Ann Ralls, NRECA, Arlington, VA, Susan Noel Kelly, American Public Power, Washington, DC, for Amici Curiae.

Before MARCUS and ANDERSON, Circuit Judges, and MILLS,[*] District Judge.

PER CURIAM:

The Georgia Parties,[1] Gwinnett County, Georgia, and the United States Army Corps of Engineers ("the Corps") appeal from the Middle District of Florida's grant of summary judgment in this consolidated suit. The appeal arises from more than 20 years of litigation involving the above parties as well as the States of Alabama and Florida, Alabama Power Company, the City of Apalachicola, Florida, and Southeastern Federal Power Customers, Inc. ("SeFPC"), a consortium of companies that purchase power from the federal government. All of the underlying cases[2] relate to the Corps' authority to operate the Buford Dam and Lake Lanier, the reservoir it created, for local water supply. In its order, the district court found that the Corps' current operation of the Buford Project—Buford Dam and Lake Lanier collectively—had allocated more than 21% of Lake Lanier's storage space to water supply. The court determined that such an allocation exceeded the Corps' statutory authority and ordered the Corps to drastically reduce the quantity of water that it made available for water supply. The court's summary judgment order also affirmed the Corps' rejection of Georgia's 2000 request for additional water supply allocations to meet the needs of the localities through 2030. The court stayed its order for three years to give the parties time to reach a settlement or to approach Congress for additional water supply authority.

On appeal, the parties argue several jurisdictional matters. Alabama and Florida[3] contend that this Court does not have appellate jurisdiction to hear the appeal of three of the four underlying cases because there is no final judgment in the cases and *1166 pendent jurisdiction is inappropriate. The Georgia Parties and the Corps argue that the district court lacked jurisdiction over these three matters because there was no final agency action, and, therefore, the Administrative Procedures Act ("APA") did not provide for judicial intervention at this juncture.

The parties also assert a number of substantive claims. The Georgia Parties argue that the district court erred by concluding that the Corps lacked authority to allocate substantial quantities of storage in Lake Lanier to water supply on the basis of the legislation that authorized the creation of the Buford Project, the 1946 Rivers and Harbors Act ("RHA"), Pub.L. No. 79-525, 60 Stat. 634 (1946). Although not in agreement with the Georgia Parties that water supply for the Atlanta area is an authorized project purpose under the RHA, the Corps does argue that the district court underestimated its authority to accommodate the water supply needs of the Atlanta area. The Georgia Parties and the Corps both assert that the district court erred by misinterpreting the scope of the Corps' authority under the 1958 Water Supply Act. The Georgia Parties and the Corps urge this Court to remand the case to the agency to make, in the first instance, a final determination of its water supply authority. Gwinnett County also individually asserts statutory, constitutional, and contractual claims relating to authority granted to it for its current withdrawals from Lake Lanier.

For the reasons explained below, we hold: First, the district court erred in finding that it had jurisdiction to hear Alabama, SeFPC, and Apalachicola because the Corps has not taken final agency action. The three cases therefore must be remanded to the Corps in order to take a final agency action. Second, the district court and the Corps erred in concluding that water supply was not an authorized purpose of the Buford Project under the RHA. The Corps' denial of Georgia's 2000 water-supply request is therefore not entitled to Chevron deference, and the request must be remanded to the Corps for reconsideration. Third, the district court erred in finding that the 1956 Act, which authorized the Corps to contract with Gwinnett County to withdraw 10 million gallons of water per day, expired after 50 years. Gwinnett County's contractual and just-compensation claims are without merit. Fourth, we also provide certain instructions to the Corps on remand. And finally, the Corps shall have one year to make a final determination of its authority to operate the Buford Project under the RHA and WSA. Our opinion is organized as follows.

    FACTS AND PROCEDURAL HISTORY
    DISCUSSION
         Part I. Jurisdictional Matters
                  A. Appellate Jurisdiction over Alabama, SeFPC, and
                        Apalachicola
                  B. Final Agency Action in Alabama, SeFPC and
                        Apalachicola
         Part II. Georgia's 2000 Request: The Corps' Water Supply Authority
                        Under the RHA
         Part III. Georgia's 2000 Request Must Be Remanded to the Corps
         Part IV. 

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Curtis Hamrick v. Partsfleet, LLC
1 F.4th 1337 (Eleventh Circuit, 2021)
Tresa Brown v. Chris Nocco
Eleventh Circuit, 2019
Omar Paez v. Claudia Mulvey
915 F.3d 1276 (Eleventh Circuit, 2019)
Florida v. Georgia
585 U.S. 803 (Supreme Court, 2018)
State v. U.S. Army Corps of Eng'rs
304 F. Supp. 3d 56 (D.C. Circuit, 2018)
Commodores Entertainment Corporation v. Thomas McClary
879 F.3d 1114 (Eleventh Circuit, 2018)
Jacqueline Lewis v. City of Union City, Georgia
877 F.3d 1000 (Eleventh Circuit, 2017)
Fishing Rights Alliance, Inc. v. Pritzker
247 F. Supp. 3d 1268 (M.D. Florida, 2017)
Valenzuela v. Union Pacific Railroad
194 F. Supp. 3d 918 (D. Arizona, 2016)
Christina Bazemore v. Jefferson Capital Systems, LLC
827 F.3d 1325 (Eleventh Circuit, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
644 F.3d 1160, 2011 WL 2536507, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-mdl-1824-tri-state-water-rights-litigation-ca11-2011.