OPINION OF THE COURT
ROTH, Circuit Judge:
This appeal requires us to evaluate our jurisdiction to entertain an appeal from the midst of a bankruptcy proceeding. Debt- or/Appellee Market Square Inn (“MSI”) asks us to affirm an order of the United States District Court for the Western District of Pennsylvania, holding that MSI’s principal asset, a lease with its landlord, Appellant Glass Plaza Associates (GPA), was improperly terminated prior to MSI’s voluntary petition for bankruptcy. The bankruptcy court severed the issue of proper termination from MSI’s larger (unresolved) quest to assume the lease in bankruptcy. Thus, the court decided only that the lease survived, not whether it could be assumed. We find nonetheless that the district court’s order regarding the validity of the lease is appealable and that our jurisdiction over the appeal is proper.
I.
MSI is a debtor in possession of certain space in a new office complex, PPG Building Four (“PPG 4”), in Pittsburgh. GPA is a limited partnership in which PPG- Industries, Inc., is the general partner. GPA is also the landlord for PPG 4. GPA and MSI entered into a Lease Agreement (“the Agreement”) on April 5, 1984, whereby MSI would lease space in PPG 4 to construct and run a first-class restaurant. During the negotiations with GPA, MSI emphasized PPG 4’s inadequacies as a restaurant site. Specifically, MSI noted that PPG 4 was designed as office space and this left no room for a restaurant kitchen. The parties nonetheless went forward with the Agreement, and MSI signed a lease with GPA which provided that rent payments would commence at a now-disputed future date. As events have transpired, that date could not now be earlier than December 31, 1984.1 MSI subsequently ne[118]*118gotiated for kitchen space in a Pittsburgh Parking Authority (“the Parking Authority”) parking garage adjacent to PPG 4. MSI leased this space from the Parking Authority on September 25, 1984.2 Borg-Warner Acceptance Corporation (“Borg-Warner”) agreed to provide $2.1 million in financing for the project.
After signing the lease with the Parking Authority in September 1984, MSI commenced designing the restaurant. GPA, acting under its interpretation of the Agreement, began billing MSI for rent in January 1985. When MSI failed to pay in January and early February, GPA sent a letter to Borg-Warner notifying it of MSI’s “default.” In early March 1985, MSI secured a temporary injunction from a Pennsylvania Court of Common Pleas, prohibiting GPA from sending Borg-Warner further such notices. Under protest, MSI then made one payment to GPA representing two months’ rent. No rental payments were made thereafter.
MSI submitted Preliminary Drawings of the restaurant to GPA in April 1985. GPA rejected the drawings on May 2, 1985. Borg-Warner terminated MSI’s funding on June 5, 1985. MSI attempted to negotiate alternative funding with United States Steel Credit Corporation, but GPA terminated the lease with MSI on July 15, 1985, citing inter alia MSI’s failure to pay rent under the Agreement. Ten months later, on May 5, 1986, MSI filed for bankruptcy under Chapter 11 of the Bankruptcy Code.
Before the bankruptcy court, MSI filed a motion to assume the Agreement with GPA under section 365(a) of the Bankruptcy Code. 11 U.S.C.A. § 365(a).3 The bankruptcy judge ordered that the trial on the motion be bifurcated to resolve the issue of the lease’s validity before litigating MSI’s ability to assume the lease. After a 6-day trial in March 1987, the bankruptcy court decided that GPA’s pre-petition termination of the Agreement was wrongful and that the Agreement did exist for MSI to assume.
The bankruptcy court found that MSI’s rental payments were not due to begin on [119]*119January 1, 1985, despite the admittedly unambiguous provision to this effect in the contract. This finding was based upon the fact that the parties intended to defer the rent date by the amount of time it took MSI to negotiate kitchen space with the Parking Authority. This intent was obvious, the court stated, because the parties included in an appendix to the Agreement a clause exonerating MSI from liability for delay in securing kitchen space.4 Since the negotiations with the Parking Authority took nearly six months, payment of rent would not begin until June 1985, rather than in January as stated in the lease. Because in March MSI paid GPA an amount representing two months rent, an amount which the court found not actually to be due until June, that payment satisfied MSI’s nonpayment of rent in June and July of 1985. The court reasoned that this payment rendered GPA's July termination of the Agreement unlawful. As a consequence, the lease existed for MSI to assume after it had filed for bankruptcy.5 On October 8, 1991, the district court affirmed the bankruptcy court’s construction of the Agreement. GPA appeals.
II.
There is some question whether the district court’s determination that the lease remains in existence has value to the parties independent of the resolution of the issue of assumption. For this reason, we must initially determine whether the district court’s order is final and appealable under 28 U.S.C.A. § 158(d). The parties both argue that the district court’s order is appealable under the more liberal rules governing bankruptcy appeals.
Pursuant to 28 U.S.C.A. § 158(a), district courts have jurisdiction to hear appeals from final judgments or orders and, “with leave of the court,” from interlocutory orders of bankruptcy judges. In turn, courts of appeals have jurisdiction over appeals in bankruptcy matters from final decisions of the district courts. See 28 U.S.C.A. § 158(d); Connecticut Nat’l Bank v. Ger-[120]*120main, — U.S. — 112 S.Ct. 1146, 1148, 117 L.Ed.2d 391 (1992).
This court has “consistently recognized that finality must be viewed pragmatically in bankruptcy appeals.” Wheeling-Pittsburgh Steel Corp. v. McCune, 836 F.2d 153, 157 (3d Cir.1987). This is so because “bankruptcy cases ‘frequently involve protracted proceedings with many parties participating. To avoid the waste of time and resources that might result from viewing discrete portions of the action only after a plan of reorganization is approved, courts have permitted appellate review of orders that in other contexts might be considered interlocutory.’ ” Id. at 158, quoting In re Amatex Corp., 755 F.2d 1034, 1039 (3d Cir.1985). In In re Meyertech Corp., 831 F.2d 410, 414 (3d Cir.1987), we set out several factors to be weighed in evaluating the propriety of jurisdiction in a bankruptcy case:
Our jurisdiction is properly invoked by balancing a general reluctance to expand traditional interpretations regarding finality and a desire to effectuate a practical termination of the matter before us. Factors to evaluate in this weighing process are the impact upon the assets of the bankrupt estate, the necessity for further fact-finding on remand, the pre-clusive effects of our decision on the merits on further litigation, and whether the interest of judicial economy would be furthered.
The “most important” of these factors is the impact upon the assets of the bankrupt estate. Id. See Century Glove, Inc. v.
Free access — add to your briefcase to read the full text and ask questions with AI
OPINION OF THE COURT
ROTH, Circuit Judge:
This appeal requires us to evaluate our jurisdiction to entertain an appeal from the midst of a bankruptcy proceeding. Debt- or/Appellee Market Square Inn (“MSI”) asks us to affirm an order of the United States District Court for the Western District of Pennsylvania, holding that MSI’s principal asset, a lease with its landlord, Appellant Glass Plaza Associates (GPA), was improperly terminated prior to MSI’s voluntary petition for bankruptcy. The bankruptcy court severed the issue of proper termination from MSI’s larger (unresolved) quest to assume the lease in bankruptcy. Thus, the court decided only that the lease survived, not whether it could be assumed. We find nonetheless that the district court’s order regarding the validity of the lease is appealable and that our jurisdiction over the appeal is proper.
I.
MSI is a debtor in possession of certain space in a new office complex, PPG Building Four (“PPG 4”), in Pittsburgh. GPA is a limited partnership in which PPG- Industries, Inc., is the general partner. GPA is also the landlord for PPG 4. GPA and MSI entered into a Lease Agreement (“the Agreement”) on April 5, 1984, whereby MSI would lease space in PPG 4 to construct and run a first-class restaurant. During the negotiations with GPA, MSI emphasized PPG 4’s inadequacies as a restaurant site. Specifically, MSI noted that PPG 4 was designed as office space and this left no room for a restaurant kitchen. The parties nonetheless went forward with the Agreement, and MSI signed a lease with GPA which provided that rent payments would commence at a now-disputed future date. As events have transpired, that date could not now be earlier than December 31, 1984.1 MSI subsequently ne[118]*118gotiated for kitchen space in a Pittsburgh Parking Authority (“the Parking Authority”) parking garage adjacent to PPG 4. MSI leased this space from the Parking Authority on September 25, 1984.2 Borg-Warner Acceptance Corporation (“Borg-Warner”) agreed to provide $2.1 million in financing for the project.
After signing the lease with the Parking Authority in September 1984, MSI commenced designing the restaurant. GPA, acting under its interpretation of the Agreement, began billing MSI for rent in January 1985. When MSI failed to pay in January and early February, GPA sent a letter to Borg-Warner notifying it of MSI’s “default.” In early March 1985, MSI secured a temporary injunction from a Pennsylvania Court of Common Pleas, prohibiting GPA from sending Borg-Warner further such notices. Under protest, MSI then made one payment to GPA representing two months’ rent. No rental payments were made thereafter.
MSI submitted Preliminary Drawings of the restaurant to GPA in April 1985. GPA rejected the drawings on May 2, 1985. Borg-Warner terminated MSI’s funding on June 5, 1985. MSI attempted to negotiate alternative funding with United States Steel Credit Corporation, but GPA terminated the lease with MSI on July 15, 1985, citing inter alia MSI’s failure to pay rent under the Agreement. Ten months later, on May 5, 1986, MSI filed for bankruptcy under Chapter 11 of the Bankruptcy Code.
Before the bankruptcy court, MSI filed a motion to assume the Agreement with GPA under section 365(a) of the Bankruptcy Code. 11 U.S.C.A. § 365(a).3 The bankruptcy judge ordered that the trial on the motion be bifurcated to resolve the issue of the lease’s validity before litigating MSI’s ability to assume the lease. After a 6-day trial in March 1987, the bankruptcy court decided that GPA’s pre-petition termination of the Agreement was wrongful and that the Agreement did exist for MSI to assume.
The bankruptcy court found that MSI’s rental payments were not due to begin on [119]*119January 1, 1985, despite the admittedly unambiguous provision to this effect in the contract. This finding was based upon the fact that the parties intended to defer the rent date by the amount of time it took MSI to negotiate kitchen space with the Parking Authority. This intent was obvious, the court stated, because the parties included in an appendix to the Agreement a clause exonerating MSI from liability for delay in securing kitchen space.4 Since the negotiations with the Parking Authority took nearly six months, payment of rent would not begin until June 1985, rather than in January as stated in the lease. Because in March MSI paid GPA an amount representing two months rent, an amount which the court found not actually to be due until June, that payment satisfied MSI’s nonpayment of rent in June and July of 1985. The court reasoned that this payment rendered GPA's July termination of the Agreement unlawful. As a consequence, the lease existed for MSI to assume after it had filed for bankruptcy.5 On October 8, 1991, the district court affirmed the bankruptcy court’s construction of the Agreement. GPA appeals.
II.
There is some question whether the district court’s determination that the lease remains in existence has value to the parties independent of the resolution of the issue of assumption. For this reason, we must initially determine whether the district court’s order is final and appealable under 28 U.S.C.A. § 158(d). The parties both argue that the district court’s order is appealable under the more liberal rules governing bankruptcy appeals.
Pursuant to 28 U.S.C.A. § 158(a), district courts have jurisdiction to hear appeals from final judgments or orders and, “with leave of the court,” from interlocutory orders of bankruptcy judges. In turn, courts of appeals have jurisdiction over appeals in bankruptcy matters from final decisions of the district courts. See 28 U.S.C.A. § 158(d); Connecticut Nat’l Bank v. Ger-[120]*120main, — U.S. — 112 S.Ct. 1146, 1148, 117 L.Ed.2d 391 (1992).
This court has “consistently recognized that finality must be viewed pragmatically in bankruptcy appeals.” Wheeling-Pittsburgh Steel Corp. v. McCune, 836 F.2d 153, 157 (3d Cir.1987). This is so because “bankruptcy cases ‘frequently involve protracted proceedings with many parties participating. To avoid the waste of time and resources that might result from viewing discrete portions of the action only after a plan of reorganization is approved, courts have permitted appellate review of orders that in other contexts might be considered interlocutory.’ ” Id. at 158, quoting In re Amatex Corp., 755 F.2d 1034, 1039 (3d Cir.1985). In In re Meyertech Corp., 831 F.2d 410, 414 (3d Cir.1987), we set out several factors to be weighed in evaluating the propriety of jurisdiction in a bankruptcy case:
Our jurisdiction is properly invoked by balancing a general reluctance to expand traditional interpretations regarding finality and a desire to effectuate a practical termination of the matter before us. Factors to evaluate in this weighing process are the impact upon the assets of the bankrupt estate, the necessity for further fact-finding on remand, the pre-clusive effects of our decision on the merits on further litigation, and whether the interest of judicial economy would be furthered.
The “most important” of these factors is the impact upon the assets of the bankrupt estate. Id. See Century Glove, Inc. v. First American Bank, 860 F.2d 94, 98 (3d Cir.1988). See also Wheeling-Pittsburgh, 836 F.2d at 158 (additionally considering whether delay in the final resolution of the matter would adversely affect .the debtor’s ability to reorganize).
Thus we have found jurisdiction, for example, over an order partially remanding the calculation of an award to the bankruptcy court, Meyertech, 831 F.2d at 412; over an order holding that the debtor was a railroad for purposes of federal bankruptcy law, Wheeling-Pittsburgh, 836 F.2d at 158; over an order denying a motion to dismiss a debtor’s Chapter 7 case, In re Christian, 804 F.2d 46, 47-48 (3d Cir.1986); over an order approving a broker’s application for payment of administrative expenses but which remanded for further proceedings regarding the amount of compensation, F/S Airlease II, Inc. v. Simon, 844 F.2d 99, 104-05 (3d Cir.), cert. denied, 488 U.S. 852, 109 S.Ct. 137, 102 L.Ed.2d 110 (1988); and over an order disqualifying trustee and counsel from employment in a jointly-administered bankruptcy cases but which remanded for further inquiry into allowable compensation, In re BH & P, Inc., 949 F.2d 1300, 1306-07 (3d Cir.1991). We note that our concerns here mirror those we expressed in F/S Airlease:
A resolution of this discrete dispute at this time would further the goal of judicial economy because it could obviate the need for further action by the bankruptcy court. Even more important, the order has a significant impact on the assets of the bankruptcy estate; the amount [sought] represents a substantial portion of the assets of the estate, and an award ... at this point will severely affect the rights of the ... creditors. In fact, a delay in the final resolution of this matter could have an adverse impact on the debtor’s successful reorganization under Chapter 11.
F/S Airlease, 844 F.2d at 104.
The factors set out above, when applied to the district court order in this case, weigh in favor of jurisdiction. First, the question of the lease’s validity greatly impacts the assets of the estate. If we assume jurisdiction over the appeal and were then to determine that the lease had been properly terminated, MSI’s ability to reorganize would effectively be foreclosed because the potential of the lease is the only substantial asset in the debtor-in-possession’s estate. We believe that it would be very difficult under the circumstances for MSI to obtain a commitment from a lender without this Court’s affirmation of the validity of the lease. If, on the other hand, we were to determine that the lease was still in effect, MSI would have a confirmed asset that might permit it to find the financing to go forward with the restaurant.
[121]*121We conclude that, as a matter of practicality, the issues of the validity and the assumability of the lease are not questions that can be decided at the same time by the bankruptcy judge. Although it is not clear from the record, we presume that MSI does not still have a financing commitment from a lender. Without financing, MSI is not in a position to assume the lease. As was mentioned at oral argument, MSI will have to shop the lease in order to attract a new source of financing. When and if MSI does find a lender, the question of assumability of the lease will be ripe to be decided by the bankruptcy judge. The resolution of this issue of assumption or rejection will be a matter of business judgment by the bankruptcy court, see Group of Institutional Investors v. Chicago, Milwaukee, St. Paul & Pacific R. Co., 318 U.S. 523, 550, 63 S.Ct. 727, 742, 87 L.Ed. 959 (1943), depending upon factors such as the terms of the lease, the conditions of any financing available, and the viability of the business.
Since as a practical matter MSI cannot begin to solicit funding to facilitate assumption of the lease until the validity of the lease is determined, this issue is independent of MSI’s ability to assemble a plan of reorganization. Because serious questions about the Agreement exist, the bankruptcy court's separate determination of the termination and assumability issues advances judicial efficiency.6 We acknowledge that concerns about runaway appeals are legitimate, see BH & P, 949 F.2d at 1319-20 (Hutchinson, J., concurring). However, resolving the issue of the status of the lease with GPA is necessary before MSI can have any hope of effectively moving ahead with its reorganization. We find, therefore, that the bankruptcy court’s order is appealable pursuant to 28 U.S.C. § 158.
III.
Unfortunately, although a majority of the panel agrees that the appeal is properly before us, we are equally divided regarding the district court’s determination that the lease was improperly terminated. Of the judges who feel we have jurisdiction to hear the appeal, one would vote to affirm the decision and one would vote to reverse.7 Consequently, the order upholding the validity of the Agreement will be affirmed. See United States v. Zolin, 491 U.S. 554, 561, 109 S.Ct. 2619, 2625, 105 L.Ed.2d 469 (1989); United States v. Bazzano, 712 F.2d 826 (3d Cir.1983) (in banc), cert. denied, sub nom. Mollica v. United States, 465 U.S. 1078, 104 S.Ct. 1439, 79 L.Ed.2d 760 (1984); United States v. Mandel, 609 F.2d 1076, 1076-77 (4th Cir.1979) (Murnaghan, J., statement regarding denial of rehearing) (“It is nearly as important that cases be decided, and the decisions be accorded finality, as it is that they be disposed of absolutely correctly. Courts have, as a consequence, adopted a rule of necessity that an evenly divided appellate court, although it cannot render a decision, affirms the judgment.”), cert. denied, 445 U.S. 961, 100 S.Ct. 1647, 64 L.Ed.2d 236 (1980).
IV.
For the foregoing reasons, we will affirm the order of the district court and remand to the bankruptcy court for further proceedings.