In re Makwa Builders, LLC

545 B.R. 311, 2016 Bankr. LEXIS 355, 2016 WL 451699
CourtUnited States Bankruptcy Court, D. New Mexico
DecidedFebruary 4, 2016
DocketCase No. 12-13664
StatusPublished

This text of 545 B.R. 311 (In re Makwa Builders, LLC) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, D. New Mexico primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re Makwa Builders, LLC, 545 B.R. 311, 2016 Bankr. LEXIS 355, 2016 WL 451699 (N.M. 2016).

Opinion

MEMORANDUM OPINION ON OBJECTION TO CLAIM

ROBERT H. JACOBVITZ, United States Bankruptcy Judge

THIS MATTER is before the Court on the Debtor’s Objection to Claim Nos. 7-1 and 27-1 of Everguard Roofing, LLC (the “Objection”) filed by Debtor, Makwa Builders, LLC (“Makwa”). ' (Docket No. 256). The Court held a final hearing on the Objection on September 10,11, and 22, 2015 and October 22, 2015, and took the matter under advisement. Claimant, Ev-erguard Roofing, LLC (“Everguard”) was represented by Wayne Bingham. Makwa was represented by Adam Melton. After considering the evidence and arguments of counsel, the Court finds that Everguard is entitled to an allowed contingent claim under 11 U.S.C. § 502(b) in the full amount assei'ted in Claim No. 27-1, that Ever-guard failed to establish a right to interest or attorneys’ fees, and that no amount is due at this time. Consequently, the Court will sustain, in part, and overrule, in part, the Objection.

PROCEDURAL HISTORY

Makwa commenced this voluntary Chapter 11 case on October 3,2012. See Voluntary Petition, Docket No. 1. On November 16, 2012, Everguard filed a proof of claim in the amount of $66,710.63. See Proof of Claim 7-1. Everguard specified “breach of contract” as the basis for its claim. On March 12, 2013, prior to the deadline to file claims, Everguard filed an amendment to its proof of claim (the proof of claim, as so amended, hereafter is called “Everguard’s Claim” or the “Claim.”). See Proof of Claim 27-1. In the amendment, Everguard increased its unsecured nonpri-ority claim to $76,357.90, states that the basis of the claim is “construction work at NMHU Student Union,” and asserts an entitlement to a fixed rate of 18% per annum interest. Everguard attached invoices and ledgers to the amended Claim as well as a three-page statement of the basis for the Claim (the “Statement”). Id. In the Statement, Everguard asserts it is entitled to interest because of Makwa’s alleged violation of New Mexico’s Prompt Pay Act (N.M. Stat. § 57-28-5) and because Makwa overbilled NMHU for work Everguard performed. See id. Makwa timely objected to Everguard’s Claim. See Docket No. 256. In support of its objection, Makwa asserts that it has yet to receive payment from New Mexico Highlands University (“NMHU”) on account of the work that forms the basis for Ever-guard’s Claim and that, pursuant to a pay-if-paid provision in its subcontract agreement with Everguard, nothing is due to. Everguard unless and until NMHU pays Makwa on account of such work. See id. Further, Makwa asserts it is currently in litigation with NHMU in New Mexico state court wherein NMHU claims an offset against payment due to Makwa partially based on allegedly substandard work performed by Everguard. See id. Finally, Makwa asserts it is, in turn, entitled to an off-set against any payment due by Makwa to Everguard equal to any amount by which NMHU is allowed to off-set its [314]*314payment to Makwa on account of Ever-guard’s substandard work.1

The Plan

On April 5, 2013, Makwa filed, its first plan of reorganization. See Chapter 11 Plan of Reorganization, Docket No. 191. About four months later, Makwa filed its first amended plan of reorganization (the “Plan”). See Debtor’s First Amended Plan of Reorganization Dated August 5, 2013, Docket No. 246. Everguard timely filed an objection to confirmation - of the Plan. See Objection, Docket No. 307. On January 8, 2014, the Court entered its Order Confirming Debtor’s First Amended Plan of Reorganization, As Modified (the “Confirmation Order”). See Docket No. 310. In the Confirmation Order, the Court ruled that “[c]onfirmation of Debt- or’s Amended Plan, as modified, does not constitute [a] determination of whether Everguard Roofing is properly included in Class 6A or Class 6B under the Plan.” Id.

The Plan, as confirmed, divides claims into- seven classes. Class 6 includes all unsecured claims not entitled to priority under 11 U.S.C. § 507 and is further divided into five sub-classes: Class 6A includes claims by Makwa’s subcontractors whose subcontract conditioned payment on Mak-wa having received payment from the project owner and for which Makwa has not received payment from the project owner; Class 6B includes claims by Makwa’s subcontractors whose subcontract conditioned payment on Makwa having received payment from the project owner claim and for which Makwa has received payment from the project owner; Class 6D .includes, all other unsecured claims not entitled to priority; and Classes 6C and 6E include only claims of specifically identified claimants, none of which are Everguard.

The Plan provides that Class 6A claims are unimpaired and that each Class 6A claimant will be treated “identically to the provisions contained in the Subcontracts between Debtor and the [claimant].” The Plan further provides that allowed Class 6A claims are “entitled to payment from Debtor only if and when the Debtor is paid and only to the extent that the Debtor is paid from a Project owner.” Makwa must pay allowed Class 6B claims within thirty days of the effective date of the Plan. Under the Plan, a claim may be divided between Class 6A and Class 6B where the portion of the claim for which Makwa previously received payment is a Class 6B claim and the remainder of the claim is a Class 6A claim. Class 6D is a catch-all class for all unsecured' claims not entitled to priority which do not fall into either Classes 6A, 6B, 6C, or 6E. Makwa must pay allowed Class 6D claims in full within three years of the effective date of the Plan.

FINDINGS OF FACT

The General Contract

Makwa is a construction company which at all relevant times primarily acted as a general contractor on public works projects. In April 2010, NMHU issued an invitation to bid on a contract to construct a new student center building on its campus in Las Vegas, New Mexico (the “Student Center Project”). NMHU awarded Makwa the general construction contract for the Student Center Project. On June 15, 2010, NMHU and Makwa executed the Document A101-2007, Standard Form of Agreement Between Owner and Contrac[315]*315tor (the “General Contract”). See Exhibit B. The original contract price for the General Contract was $16,006,000.00. See id.

The Subcontract

Everguard is a construction company primarily engaged in roofing and siding installation. On August 5, 2010, Makwa and Everguard entered into the Makwa Builders LLC Subcontract Agreement (the “Subcontract”) whereby Everguard agreed to perform roofing and Corten panel installation for the Student Center Project. See Exhibit A. The original contract price for the Subcontract was $632,880.00. See id.

Article V of the Subcontract includes provisions regarding how and when Mak-wa must make payments to Everguard under the Subcontract. Pursuant to Section 5.2 of the Subcontract, Everguard must create a schedule of values, with the approval of Makwa, allocating portions of the Subcontract price to categories of the work to be performed under the Subcontract (e.g., $35,000.00 for Mobilization, $118,231.00 for Insulation Labor TPO Roofs, etc.).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Continental Potash, Inc. v. Freeport-McMoran, Inc.
858 P.2d 66 (New Mexico Supreme Court, 1993)
Davies v. Boyd
385 P.2d 950 (New Mexico Supreme Court, 1963)
Mark V, Inc. v. Mellekas
845 P.2d 1232 (New Mexico Supreme Court, 1993)
Western Commerce Bank v. Gillespie
775 P.2d 737 (New Mexico Supreme Court, 1989)
Hasse Contracting Co. v. KBK Financial, Inc.
1999 NMSC 023 (New Mexico Supreme Court, 1999)
Hasse Contracting Co. v. KBK Financial, Inc.
1998 NMCA 038 (New Mexico Court of Appeals, 1998)
In Re All Media Properties, Inc.
5 B.R. 126 (S.D. Texas, 1980)
Fort Knox Self Storage v. Western
142 P.3d 1 (New Mexico Court of Appeals, 2006)
Lehrer McGovern Bovis, Inc. v. Bullock Insulation, Inc.
197 P.3d 1032 (Nevada Supreme Court, 2008)
Wm. R. Clarke Corp. v. Safeco Insurance of America
938 P.2d 372 (California Supreme Court, 1997)
Fort Knox Self Storage, Inc. v. Western Technologies, Inc.
2006 NMCA 096 (New Mexico Court of Appeals, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
545 B.R. 311, 2016 Bankr. LEXIS 355, 2016 WL 451699, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-makwa-builders-llc-nmb-2016.