In Re Farmland Industries, Inc.

309 B.R. 14, 2004 Bankr. LEXIS 375, 42 Bankr. Ct. Dec. (CRR) 263, 2004 WL 758942
United States Bankruptcy Court, W.D. Missouri·Decided March 24, 2004·No. 17-30647·Published·Cited by 7 cases

Opinion

MEMORANDUM OPINION

JERRY W. VENTERS, Chief Judge.

The issue presently before the Court in this Chapter 11 case is whether the Court should give effect to pre-petition arbitration agreements and lift the automatic stay to allow the arbitration of certain claims to proceed.

Black & Veatch Prichard, Inc. (“Black & Veatch”) filed a proof of claim for $28,572,482 relating to the alleged breach of three contracts having to do with the engineering and construction of a portion of a refinery and fertilizer plant in Coffey-ville, Kansas. Farmland Industries, Inc., et al., the Debtors in these proceedings, and the Official Committee of Bondholders (collectively, the “Debtor”) joined in an objection to the proof of claim, asserting numerous substantive grounds for disal-lowance. Black & Veatch denied the Debtor’s allegations, argued its claim on the merits, and requested that this Court grant Black & Veatch’s motion for relief from the automatic stay to allow the parties to arbitrate their disputes pursuant to their pre-petition arbitration agreements. The Debtor asks that the Court deny Black & Veatch’s request for arbitration inasmuch as the Debtor’s objection to Black & Veatch’s proof of claim is a core proceeding, the resolution of which concerns the underlying policies and purposes of the Bankruptcy Code.

The Court held a hearing on the Debt- or’s objection to Black & Veatch’s proof of claim on February 9, 2004, in Kansas City, Missouri. At the same time, the Court set a briefing schedule for Black & Veatch’s motion requesting relief from the automatic stay, and took both matters under advisement. 1 After reviewing the arguments of the parties, and after conducting its own research, the Court is prepared to lift the automatic stay to allow the parties’ dispute to be resolved pursuant to their pre-petition arbitration agreements.

I. BACKGROUND

By the end of December 1997, the Debt- or and Black & Veatch had entered into *16 three contracts to engineer, procure, and construct two components of a total petroleum coke-to-fertilizer project in Coffey-ville, Kansas. The parties executed an agreement for engineering services (“Engineering Agreement”), a lump sum agreement for the Coffeyville Gasification Plant (“Gasification Agreement”), and a lump sum agreement for the Coffeyville ammonia synthesis loop project (“Synloop Agreement”). Black & Veatch stated that the value of the three contracts exceeded $180,000,000. According to Black & Veatch, the entire design-build project was based on a process information package (“PIP”) owned by Texaco and licensed to the Debtor. Many of the component parts were being designed by Texaco, while others were being recycled from a plant in Daggett, California.

The Engineering Agreement preceded both the Gasification and Synloop Agreements. The purpose of the Engineering Agreement was to provide a definitive cost estimate for the gasification project, a service that cost the Debtor $935,000.00. The Debtor intended to use the conclusions of the Engineering Agreement as a basis for soliciting bids for the construction of the gasification plant. Ultimately, the Debtor accepted the bid of Black & Veatch, which was based on the design specifications Black & Veatch itself had created. Black & Veatch’s conclusions in the Engineering Agreement were based, in part, on the cost of relocating components of the Daggett, California plant to Coffeyville, Kansas, and on employing Texaco’s proprietary technology under the PIP at the Coffeyville facility. Black & Veatch asserts that the Engineering Agreement was never intended to be a check against Texaco’s engineering or the Debtor’s overall project design and feasibility; those were to be determined by Texaco, the Debtor, and the Debtor’s secured lender.

The Gasification Agreement provided that Black & Veatch was to engineer, procure, and construct the gasification plant within twenty-two months, for the sum of $145,820,500. The Debtor issued a notice to proceed to Black & Veatch on December 12, 1997. Mechanical completion was due no later than October 11,1999.

Black & Veatch argues that the Gasification Agreement was essentially a relocation/modification contract whereby Black & Veatch was responsible for refurbishment of equipment from the Daggett, California facility based on the recommendations of third-party inspectors. Black & Veatch alleges that it was initially the Debtor’s responsibility to designate what parts of the Daggett plant needed to be refurbished and what parts needed replacing, but Black & Veatch asserts that it was forced to take on that responsibility because of the Debtor’s slow performance. Additionally, a major component of the Gasification Agreement was based on the Texaco/Debtor PIP that was specifically developed for use in the Debtor’s coke-to-fertilizer plant. Black & Veatch asserts that it was required to rely on Texaco’s PIP as adequate, and its responsibility was only to install the PIP as designed in the Coffeyville facility.

Timely completion of the Gasification Agreement was designated “of the essence” in the Gasification Agreement, and the time frame allowed for mechanical completion was designated with adequate allowance for inclement weather. Unfortunately, numerous events caused Black & Veatch to postpone the scheduled date for mechanical completion — events that Black & Veatch asserts were attributable to the Debtor. Pursuant to Article 5.1 of the Gasification Agreement, if Black & Veatch’s performance was delayed, then it was required to give prompt written notice *17 and to diligently endeavor to mitigate and remedy the situation. The Gasification Agreement provided that any claim for an extension of the completion deadline had to be made within ten days after the occurrence, or else any request for an extension was waived. The Debtor alleges that on January 17, 2000, three months after the scheduled date for mechanical completion, Black & Veatch submitted the required paperwork for an extension requesting an additional 170 days to complete the project, based on events occurring in 1997 and 1998. Before submitting that paperwork, however, Black & Veatch submitted numerous change orders altering the scope of its work; these change orders were approved by the Debtor.

The Synloop Agreement required Black & Veatch to engineer, procure, and construct an ammonia synthesis loop project for the sum of $32,485,300. Like the Gasi-fication Agreement, the Synloop Agreement required Black & Veatch to attain mechanical completion twenty-two months after December 12, 1997, or no later than October 11, 1999; to notify the Debtor in writing if it believed that the completion schedule would not be met; and to give written notice in the event of a delay within ten days of the occurrence or else a claim for additional time to complete the project was deemed waived. Article 15 of the Synloop Agreement also contemplated an extension of the mechanical completion date based on approved change orders.

Free access — add to your briefcase to read the full text and ask questions with AI

In Re Farmland Industries, Inc., 309 B.R. 14, 2004 Bankr. LEXIS 375, 42 Bankr. Ct. Dec. (CRR) 263, 2004 WL 758942 (Mo. 2004).

309 B.R. 14 (In Re Farmland Industries, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related