Wiley v. Hartzler (In Re Wiley)

288 B.R. 818, 2003 Bankr. LEXIS 104, 40 Bankr. Ct. Dec. (CRR) 241, 2003 WL 355283
CourtUnited States Bankruptcy Appellate Panel for the Eighth Circuit
DecidedFebruary 19, 2003
Docket02-6057WM
StatusPublished
Cited by12 cases

This text of 288 B.R. 818 (Wiley v. Hartzler (In Re Wiley)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Appellate Panel for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wiley v. Hartzler (In Re Wiley), 288 B.R. 818, 2003 Bankr. LEXIS 104, 40 Bankr. Ct. Dec. (CRR) 241, 2003 WL 355283 (bap8 2003).

Opinion

KRESSEL, Chief Judge.

William Carl Wiley appeals from the order of the bankruptcy court 1 which granted Geoffrey and Dorothy Hartzler relief from the automatic stay. Because we believe the bankruptcy court did not abuse its discretion, we affirm.

BACKGROUND

In 1998, the Hartzlers, residents of Johnson County, Kansas, wanted to build a home in Camden County, Missouri. The *820 Hartzlers contacted William C. Wiley Construction, Inc. 2 The Hartzlers allege that the parties orally agreed that Wiley Construction would be paid a 12% mark-up, above and beyond time and materials. On October 2, 1998, the Hartzlers and Wiley Construction entered into a construction agreement.

On October 6, 1998, the Hartzlers, Wiley Construction, and Legend Title Co., Inc. entered into an escrow agreement. Pursuant to the agreement, the Hartzlers es-crowed certain funds and Wiley Construction was authorized to draw on the funds to make payment upon any construction agreement addenda. The Hartzlers argue that the debtor and Wiley Construction represented that each draw applied for and received would be consistent with the agreed-upon 12% mark-up. The debtor argues he did not agree to the 12% mark up, and that under the construction agreement, the contract price was subject to additions and deductions by Change Order, and that the Hartzlers were not charged a fixed fee because of the uniqueness, unknowns, and size of the project. Pursuant to the construction agreement, the work on the property progressed and Wiley Construction submitted bids for each job to be undertaken at the property. The Hartzlers approved the job bids submitted by Wiley Construction.

The Hartzlers allege that Wiley Construction was not properly performing its duties as provided in the construction agreement because there were significant delays and an insufficient work force on the job site. The Hartzlers also suspected that Wiley Construction was exceeding the 12% mark-up. The Hartzlers argue that Wiley Construction had in fact exceeded the mark-up, with an average mark-up of 27.79%. The Hartzlers have alleged that the debtor, in serving in his individual capacity, as well as an agent for Wiley Construction, engaged in a series of wrongful acts with respect to their property and in dealings with them. 3

On or around February 26, 2001, the Hartzlers told the debtor that Wiley Construction would no longer be involved in the project and requested him to sign a settlement agreement “parting ways and avoiding lawsuits.” The Hartzlers and Wiley Construction entered into the Settlement Agreement. That agreement required Wiley Construction to: (1) submit a final lien waiver and affidavit to the Hartzlers; (2) make no claims, commitments or representations concerning the project and/or the debtor’s involvement in the project to any media source, and not cause Wiley Construction to be associated with the project in any advertising or visual presentation; and (3) take no action to impede, obstruct, affect, alter or influence the Hartzlers’ ability to retain general contractors and subcontractors, materials, supplies or services to complete the project. The Hartzlers maintain that the debtor breached this agreement by failing to submit a final lien waiver and affidavit, utilizing photos of the Hartzler home on *821 the debtor’s website, and by disparaging the Hartzlers in the local construction community. As a result, the Hartzlers filed suit in the U.S. District Court for the District of Kansas on October 24, 2001. 4

Since October 24, 2001, the Hartzlers maintain that the parties have exchanged Rule 26 disclosures, creditors have served written discovery, debtor has responded to creditors’ written discovery, William Wiley appeared on behalf of Wiley construction in a Fed.R.Civ.P. 30(b)(6) deposition, depositions of fact witnesses have commenced. Trial of the Hartzler suit had been set for a two week jury trial in December 2002.

The debtor filed for bankruptcy protection under Chapter 13 on July 9, 2002. The debtor listed the Hartzler claim as contingent, unliquidated and disputed for a unknown amount, in addition to $3,300 for reimbursement for materials used. 5 The Hartzlers filed two proofs of claim in the case, totaling $693,000.

On July 24, 2002, in an effort to complete the litigation which began in the district court, the Hartzlers filed a Motion to Dismiss the case 6 or in the alternative, relief from the automatic stay. At the hearing, the bankruptcy court heard testimony from the debtor. After reviewing the evidence, the court granted the Hartzlers relief from the automatic stay on October 2, 2002. The debtor filed a notice of appeal on October 14, 2002. On October 28, 2002, the debtor filed an emergency motion with the bankruptcy court for a stay pending appeal. This motion was denied by the bankruptcy court on November 26, 2002. The debtor subsequently filed a Motion for Stay Pending Appeal with this Court, which we denied on December 17, 2002.

DISCUSSION

STANDARD OF REVIEW

We review the bankruptcy court’s factual findings for clear error and its conclusions of law de novo. Blackwell v. Lurie (In re Popkin & Stern), 223 F.3d 764, 765 (8th Cir.2000); Wendover Fin. Servs. v. Hervey (In re Hervey), 252 B.R. 763, 765 (8th Cir. BAP 2000). A decision to grant or deny a motion for relief from the automatic stay is within the discretion of the bankruptcy court and as such, is reviewed for an abuse of discretion. Blan v. Nachogdoches County Hosp. (In re Blan), 237 B.R. 737, 739 (8th Cir. BAP 1999). An abuse of discretion will only be found if the bankruptcy court’s judgment was based on clearly erroneous factual findings or erroneous legal conclusions. Id. A finding is clearly erroneous when although there is evidence to support it, the reviewing court, on the entire evidence is left with the definite and firm conviction that a mistake has been committed. Anderson v. City of Bessemer City, 470 U.S. 564, 573, 105 S.Ct. 1504, 84 L.Ed.2d 518 (1985).

*822 THE MERITS

The mere filing of a petition in bankruptcy cannot, in and of itself, erase a plaintiffs claim, its opportunity to litigate, or the fact that the debtor may be liable to the plaintiff in some amount. In re Bock Laundry Mach. Co., 37 B.R. 564, 567 (Bankr.N.D.Ohio 1984). Bankruptcy Code section 362(d)(1) provides that the bankruptcy court may grant relief from the automatic stay for cause. In re Blan, 237 B.R. at 739.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
288 B.R. 818, 2003 Bankr. LEXIS 104, 40 Bankr. Ct. Dec. (CRR) 241, 2003 WL 355283, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wiley-v-hartzler-in-re-wiley-bap8-2003.