Opinion

Weaver, J.

The plaintiff company is engaged in the business of plumbing, pipe fitting, and steam heating. In the year 1901 it entered into contracts by which it undertook to do the plumbing and furnish heating apparatus for a certain block or double building owned by the plaintiff for the aggregate price of $1,250. Thereafter the plaintiff further undertook to install certain radiation for steam heating in the defendant’s dwelling house, which stood near the block or double building above mentioned, and connect said radiation with the boiler by which said block was heated.. The agreed price of this job was $225. The plaintiff claims to have performed all the work aforesaid according to agreement, and that .there is an unpaid balance due him, for which he asks judgment, and the establishment of a lien upon the property. The bill of items attached to the petition indicates that defendant has paid plaintiff $1,250,. the agreed [139]*139price of the work done in the block first mentioned, leaving unpaid the price named in the last contract, $225, and certain small items charged as extras, amounting to $18.47. Defendant admits making the contracts sued -upon, but says he has paid for all the work which has been done according to the agreement. He further alleges that the work done under the last contract for the purpose of heating his dwelling house was executed in such negligent and unworkman-like manner as to prove wholly inadequate and useless, and is without any value, and for injuries resulting from this failure he makes a counterclaim of $300. The district court found the plaintiff entitled to recover nothing, but allowed it to remove the radiators, pipes, and other materials placed by it upon the premises under the last contract, on condition that it repair the injury occasioned by the installment and removal of said materials. The defendant’s counterclaim was dismissed.

1. Heating contract; workmanlike manner; utility. The appellant argues that it did not undertake to accomplish any certain or definite results with the apparatus put in the dwelling house, and that, having in fact installed the radiators and pipes called for by the x x agreement, defendant must be held to pay the ° ' x ° contract price. The contract is embraced in certain written proposals accepted by the defendant. The proposals appear to have been written upon a printed form, some parts of which have no apparent meaning in connection with the work actually, contemplated. It does, however, specify the radiators and piping to be put in, the connection cf the same with the boiler, the quality of the materials to be used, and provides that “ all work is to be done in a good and workmanlike manner.” No detailed plans or specifications for the work are given. It also provides that upon completion of the work it shall be promptly inspected by the defendant, and accepted or rejected, .so that the workmen, while still on the premises, may at once remedy any defects complained of. ' A guaranty is given that, if any part of the [140]*140apparatus sbow any defects in material within eight years, new parts will be furnished upon application. The title to the property, with right to remove the same, is reserved by the plaintiff, if not paid for according to contract.

Without at this time considering whether defendant may rely upon any implied stipulation or agreement, we have to say that, in our judgment, the plaintiff, in agreeing to do the work “ in a good and workmanlike manner,” did undertake to produce definite and certain results. The stipulation means something more than a promise to do a job which shall look well something more than a good example of pipe fitting. A grist-mill which will not grind, a reaper that will not cut grain, a locomotive that will not move when the proper power is applied, can hardly be said to have been constructed in a good and workmanlike manner. Even so a heating apparatus that will heat nothing but the owner’s temper must be said not to fill that condition. If a professional ditcher undertakes to drain a swamp in a good and workmanlike manner, but by a miscalculation makes the outlet of his ditch higher than the surface of the swamp, it will not avail him to say that the trench was evenly dug, and the tile laid with perfect regularity. A good and workmanlike job is one that is done as a skilled workman should do it. Fitzgerald v. La Porte, 64 Ark. 34 (40 S. W. Rep. 261); Smith v. Clark, 58 Mo. 145.

The putting in of a steam heating outfit is a work which' requires experience and skill. When such work is well done, we know, as a matter of common knowledge, it serves its purpose with a fair degree of success. It is made evident in this case that the plan adopted for piping and heating the defendant’s residence did not operate with reasonable success. For one thing, it is practically conceded that the boiler was set too high to permit a return of the condensed steam, with the result that the pipes and radiators would fill with water and prevent the circulation of steam. Plaintiff sought to remedy this by wasting the condensed steam into [141]*141the sewer, but the device did not operate satisfactorily. When, the existence of the defect was demonstrated, plaintiff refused to lower the boiler without extra payment, and the defendant, after vainly trying to heat his house therefrom, abandoned the attempt, and put in a furnace, and notified plaintiff to remove the radiators and pipes. If the boiler was too high, plaintiff, as a skilled workman, must have known the fact, and must further have known that a good and workmanlike job for heating the defendant’s home therefrom was impracticable. It is testified upon part of the plaintiff’s officers that before entering into' the contract they expressed to the defendant their doubt of the success of an attempt to heat the house in the manner proposed, and told him he must take the chances, or words to that effect. If this fact were established, it would, of course, relieve the plaintiff from responsibility, for, under such circumstances, it could only be held to make as good a job as could reasonably be expected in view of the faulty plan adopted. But no such stipulation is contained in the written agreement, and the defendant and his wife deny the alleged conversation, and testify unequivocally that the manager assured them it was perfectly practicable to heat their home successfully by connection with the boiler in the other building. The defendant is a photographer, and has no technical knowledge of steam heating; and, assuming that he is a man of average prudence and sense, it would seem improbable that, in face of a warning that his heating apparatus was likely to prove valueless, he would direct or permit the work to proceed. We are inclined to the view that the defendant’s theory of the conversation preceding the making of the contract is the more reasonable and the more likely to be correct.

But even if we discard all testimony as to prior conversations, there was still the question of fact whether the job -was done in a good and workmanlike manner. In entering into this contract defendant was promising to pay for something more than the installing of so much iron piping [142]*142and radiators, and we must assume that plaintiff supposed it was promising to furnish him something more than the mere materials in place.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pfaudler Company v. American Beef Packing Company
338 F. Supp. 701 (S.D. Iowa, 1972)
Hanson Silo Co. v. Bennett
119 N.W.2d 764 (Supreme Court of Iowa, 1963)
Rasmus v. AO Smith Corporation
158 F. Supp. 70 (N.D. Iowa, 1958)
Drager v. Carlson Hybrid Corn Co.
56 N.W.2d 18 (Supreme Court of Iowa, 1952)
Refrigeration Discount Corp. v. Richards
284 N.W. 343 (Nebraska Supreme Court, 1939)
Lebow & Shell Corp. v. Medella
16 N.E.2d 927 (Appellate Court of Illinois, 1938)
Ford Motor Co. v. Cullum
96 F.2d 1 (Fifth Circuit, 1938)
Rowe Manufacturing Co. v. Curtis-Straub Co.
223 N.W. 895 (Supreme Court of Iowa, 1937)
Hughes v. National Equipment Corp.
250 N.W. 154 (Supreme Court of Iowa, 1933)
Ice Cream MacH. Co., Inc. v. Pig'n Whistle
65 S.W.2d 575 (Court of Appeals of Tennessee, 1933)
Moss v. Best Knitting Mills
130 S.E. 635 (Supreme Court of North Carolina, 1925)
Hercules Powder Co. v. Rich
3 F.2d 12 (Eighth Circuit, 1924)
Morris v. Fox
135 N.E. 663 (Indiana Court of Appeals, 1922)
J. L. Owens Co. v. Leland Farmers Elevator Co.
192 Iowa 771 (Supreme Court of Iowa, 1921)
American Player Piano Co. v. American Pneumatic Action Co.
172 Iowa 139 (Supreme Court of Iowa, 1915)
Penn American Plate Glass Co. v. De La Vergne Machine Co.
106 N.E. 722 (Indiana Court of Appeals, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
102 N.W. 840, 127 Iowa 137, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ideal-heating-co-v-kramer-iowa-1905.