Reilly Construction Co., Inc., plaintiff-appellee/cross-appellant v. Bachelder, Inc., defendant-appellant/cross-appellee.

CourtCourt of Appeals of Iowa
DecidedMarch 25, 2015
Docket14-0817
StatusPublished

This text of Reilly Construction Co., Inc., plaintiff-appellee/cross-appellant v. Bachelder, Inc., defendant-appellant/cross-appellee. (Reilly Construction Co., Inc., plaintiff-appellee/cross-appellant v. Bachelder, Inc., defendant-appellant/cross-appellee.) is published on Counsel Stack Legal Research, covering Court of Appeals of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reilly Construction Co., Inc., plaintiff-appellee/cross-appellant v. Bachelder, Inc., defendant-appellant/cross-appellee., (iowactapp 2015).

Opinion

IN THE COURT OF APPEALS OF IOWA

No. 14-0817 Filed March 25, 2015

REILLY CONSTRUCTION CO., INC., Plaintiff-Appellee/Cross-Appellant,

vs.

BACHELDER, INC., Defendant-Appellant/Cross-Appellee. ________________________________________________________________

Appeal from the Iowa District Court for Winneshiek County, John J.

Bauercamper, Judge.

A property owner appeals the district court’s determination his oral

contract with a construction company to build a pond did not carry express or

implied warranties. The construction company cross-appeals the court’s refusal

to foreclose its mechanic’s lien. REVERSED AND REMANDED ON APPEAL;

AFFIRMED ON CROSS-APPEAL.

Dale L. Putnam of Putnam Law Office, Decorah, for appellant.

Richard D. Zahasky, Decorah, and Douglas A. Boese and John C. Beatty

of Dunlap & Seeger, P.A., Rochester, Minnesota, for appellee.

Heard by Vaitheswaran, P.J., and Tabor and Mullins, JJ. 2

TABOR, J.

This appeal concerns a pond that does not hold water. At issue is how the

landowner and the builder apportioned that risk in their oral contract for the

project. The landowner, Bachelder, Inc., paid for the initial dam construction but

not for remedial digging. The builder, Reilly Construction Co., Inc., filed a

mechanic’s lien. The district court declined to foreclose the mechanic’s lien but

also rejected Bachelder’s counterclaims for breach of either express or implied

warranties. Both sides appeal. Because the district court erred in finding no

breach of an express warranty the pond would hold water or an implied warranty

of workmanlike construction or fitness for a particular purpose, we reverse and

remand for a hearing on Bachelder’s damages. Finding no implied contract to

perform additional work on the pond, we affirm on Reilly’s cross-appeal.

I. Background Facts and Proceedings

Leon and Sherry Bachelder wanted to add a recreational pond to their

Winneshiek County acreage.1 They hoped to use it with family and friends to

“swim, fish, and take the boat out on it.” As part-owner of the Decorah Auto

Center, Leon Bachelder had sold pickup trucks to Christopher Reilly, owner of

Reilly Construction Co., Inc. Because he knew him as a customer, Bachelder

approached Reilly about building the pond, the first time in 2008. When

Bachelder did not hear back, he called Reilly again in 2009.

Reilly sent workers out to survey the area and reported back to Bachelder

that it looked like they could build a pond for him. Then Bachelder, Reilly, and

1 The title holder of the property was Bachelder, Inc.; that entity is the defendant- appellant in this action. 3

Reilly’s employee, Charles Sender, met at the site. Sender had “staked out” the

location where the pond would be. Bachelder recalled Sender telling him the

maximum depth of the pond would be twenty to twenty-one feet. Reilly saw the

location was a natural waterway with a small stream running through it, about

three to four hundred feet across, fairly sloping to the bottom. Reilly agreed to

build a dam across the valley to capture the water.

Reilly started construction of the pond in fall 2009 and finished in spring

2010. His construction company did not have any licensed engineers on staff

and did not consult any before beginning the project. Reilly testified the first step

in his process was to dig a core trench where the center of the dike would be

located. Reilly explained: “You dig down, depending on soil conditions, but until

you find a clay material.” He said, in this case, they ran into a little bit of top soil,

and then “were into clay material” and “dug approximately ten feet, and through

the ravine or waterway, through the bottom, up into the slope,” and then “started

to fill that with on-site material that was available on the property.” During the

construction, Reilly’s crew dug up two natural springs on the property, ostensibly

to make them flow better and keep the pond filled. Reilly understood the

Bachelders wanted the top of the dam to be wide enough to drive across. When

finished the following spring, the dike was about twenty-five feet high, transected

by a twenty-four-inch drainage pipe to allow the water to reach of a maximum

depth of twenty-one feet. 4

Reilly billed Bachelder for his work, and Bachelder wrote Reilly checks in

the amounts of $57,110.63 in December 2009 and $30,000 in April 2010.2 The

pond held water during the summer of 2010—when the precipitation was well

above average. But that autumn the water level dropped dramatically. So

dramatically, the Bachelders could see the tires Reilly’s crew placed at the

bottom of the pond to serve as a habitat for fish. Bachelder called Reilly to tell

him the pond was not holding water.

Reilly went out to investigate and agreed to pump out the remaining

water—free of charge—to look at the bottom of the pond for signs of leakage.

Reilly sent Bachelder an email on October 12, 2010, detailing the next steps:

The guys are going to pump out the pond and see what we can find in the coming days. Also when our guys were out there your wife did not care to [sic] much for the tires as fish habitat so we will remove those. So we are on the same page we will not charge you anything to pump out the pond and come up with a plan but if the solution is to find clay material and line the bottom then we would need to come up with some kind of compensation for that work. Pretty much all the good material from the west was used up for the dam and the clay on the east side was not plentiful so we may need to look at off site material.

Reilly also brought in an engineer at this point to “do some bore testing” to

determine if the structure his company built was leaking. The dam appeared to

be intact and the bottom of the pond was the same clay material Reilly

discovered when he dug the core trench for the dam. But when he started

exploring further up the slopes of the pond, he found “basically a plus or minus

five foot shale layer that was not exposed to the environment but back in under

2 The Bachelders also wrote Reilly a check for $29,851.50 in March 2011. 5

top soil.” The shale layer was porous and water ran through it like it was sand.

To stem the infiltration, Reilly came up with a plan to dig a trench along the sides

of the pond, remove the shale, and replace it with clay from the bottom of the

pond.3 Reilly’s crew started the remedial work in the fall of 2010, but “got froze

out” and did not complete its digging until May 2011.

Reilly sent Bachelder a bill for the second round of work on the pond,

which Bachelder declined to pay. On July 1, 2011, Reilly filed a mechanic’s lien

on the property, alleging Bachelder owed him $93,600 for work performed from

November 2010 through May 2011. Reilly filed a petition to foreclose the

mechanic’s lien on August 9, 2011. Bachelder filed an answer and counterclaim

on September 12, 2011. The counterclaim alleged Reilly was negligent in the

construction of the pond, failed to comply with the oral contract, and failed to

perform in a workmanlike fashion, causing Bachelder damages.

The district court held a trial without a jury on February 26 and 27, 2014.

Both Reilly and Bachelder testified. Bachelder alleged he incurred numerous

expenses related to the pond beyond the cost of construction, including a pump

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Moore v. Vanderloo
386 N.W.2d 108 (Supreme Court of Iowa, 1986)
Semler v. Knowling
325 N.W.2d 395 (Supreme Court of Iowa, 1982)
Flom v. Stahly
569 N.W.2d 135 (Supreme Court of Iowa, 1997)
Carson v. Roediger
513 N.W.2d 713 (Supreme Court of Iowa, 1994)
Busker v. Sokolowski
203 N.W.2d 301 (Supreme Court of Iowa, 1972)
Markman v. Hoefer
106 N.W.2d 59 (Supreme Court of Iowa, 1960)
Speight v. Walters Development Co., Ltd.
744 N.W.2d 108 (Supreme Court of Iowa, 2008)
Roger's Backhoe Service, Inc. v. Nichols
681 N.W.2d 647 (Supreme Court of Iowa, 2004)
Harper v. Cedar Rapids Television Co., Inc.
244 N.W.2d 782 (Supreme Court of Iowa, 1976)
Pike v. Kennedy
730 N.W.2d 209 (Court of Appeals of Iowa, 2007)
Kirk v. Ridgway
373 N.W.2d 491 (Supreme Court of Iowa, 1985)
Flynn Builders, L.C. v. Matthew P. Lande and Chris Lande
814 N.W.2d 542 (Supreme Court of Iowa, 2012)
Smith & Nelson v. Bristol
33 Iowa 24 (Supreme Court of Iowa, 1871)
Ideal Heating Co. v. Kramer
102 N.W. 840 (Supreme Court of Iowa, 1905)

Cite This Page — Counsel Stack

Bluebook (online)
Reilly Construction Co., Inc., plaintiff-appellee/cross-appellant v. Bachelder, Inc., defendant-appellant/cross-appellee., Counsel Stack Legal Research, https://law.counselstack.com/opinion/reilly-construction-co-inc-plaintiff-appelleecross-iowactapp-2015.