Roger's Backhoe Service, Inc. v. Nichols

681 N.W.2d 647, 2004 Iowa Sup. LEXIS 198, 2004 WL 1336257
CourtSupreme Court of Iowa
DecidedJune 16, 2004
Docket02-2014
StatusPublished
Cited by14 cases

This text of 681 N.W.2d 647 (Roger's Backhoe Service, Inc. v. Nichols) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Roger's Backhoe Service, Inc. v. Nichols, 681 N.W.2d 647, 2004 Iowa Sup. LEXIS 198, 2004 WL 1336257 (iowa 2004).

Opinion

CARTER, Justice.

Defendant, Jeffrey S. Nichols, is a funeral director in Muscatine. This action arises from a construction project that he undertook in 1998 involving the building of a crematorium and an enlargement and resurfacing of the parking lot at his funeral home. A dispute arose between Nichols and Roger’s Backhoe Service, Inc. (Roger’s) concerning invoices presented by Roger’s for excavation work performed during the construction. The district court awarded Roger’s the full amount claimed in the action.

The court of appeals reversed the district court’s award and concluded that no enforceable contract had been established between the parties. After reviewing the record and considering the arguments presented, we conclude that the district court’s judgment was supported by the evidence and was not the product of legal error. Consequently, we vacate the decision of the court of appeals and affirm the judgment of the district court.

In early 1998 Nichols decided to build a crematorium on the tract of land on which his funeral home was located. In working with the Small Business Administration, he was required to provide drawings and specifications and obtain estimates for the project. Nichols hired an architect who prepared plans and submitted them to the City of Muscatine for approval. These plans provided that the surface water from the parking lot would drain onto the adjacent street and alley and ultimately enter city storm sewers. These plans were approved by the city.

Nichols contracted with Roger’s for the demolition of the foundation of a building that had been razed to provide room for the crematorium and removal of the concrete driveway and sidewalk adjacent to that foundation. Roger’s completed that work and was paid in full. Scott Price d/b/a Price-Built Constructions (Price) was hired by Nichols as the contractor for building the crematorium and an enlarged concrete parking lot. Price contracted with Roger’s to assist in a curb cut that was required by his contract. Roger’s has been paid for that work, and it is not in issue in the present case.

After construction began, city officials came to the jobsite and informed Price and Roger’s that the proposed drainage of surface water onto the street and alley was unsatisfactory. The city required that an effort be made to drain the surface water into a subterranean creek, which served as part of the city’s storm sewer system. City officials indicated that this subterranean sewer system was about fourteen feet below the surface of the ground. Price *649 and Roger’s conveyed the city’s mandate to Nichols when he visited the jobsite- that same day.

It was Nichols’ testimony at trial that, upon receiving this information, he advised Price and Roger’s that he was refusing permission to engage in the exploratory excavation that the city required. Nevertheless, it appears without dispute that for the next three days Roger’s did engage in digging down to the subterranean sewer system, which was located approximately twenty feet below the surface. When the underground creek was located, city officials examined the brick walls in which it was encased and determined that it- was not feasible to penetrate those walls in order to connect the surface water drainage with the underground creek. As a result of that conclusion, the city reversed its position and once again gave permission to drain the surface water onto the adjacent street and alley.

Two of the four invoices at issue in this litigation relate to charges that Roger’s submitted to Nichols for the three days of excavation necessary to locate the underground sewer system and the cost for labor and materials necessary to refill the excavation with compactable materials and attain compaction by means of a tamping process. The other two invoices for which Roger’s made claim against Nichols involved grading necessary to enable Price to perform the work called for in its contract with Nichols. The district court found that the amount of. the charges submitted on the four invoices were fair and reasonable and that they -had been performed for Nichols’ benefit and with his tacit approval.

I.Scope of Review.

This contract action was tried by ordinary proceedings and consequently is reviewed for errors at law. Iowa Const. art. V, § 4; Iowa Code § 611.6 (2001). Trial court findings of fact are binding on us if supported by substantial evidence, but we are not precluded from inquiry into whether erroneous rules of law materially affected the. decision. In re Estate of Northup, 230 N.W.2d 918, 921 (Iowa 1975); Farmers Ins. Group v. Merryweather, 214 N.W.2d 184, 186-87 (Iowa 1974).

II. The Court of Appeals Opinion.

The court of appeals premised its reversal of the district court’s decision on three separate and distinct conclusions. First, it concluded that an action based on an open account is a discrete cause of action with fixed legal elements that were not established in the matter before the court. Second, the court of appeals concluded that Roger’s should not be able to establish an implied contract because it did not allege any oral or written contract in its petition as required by Iowa Rule of Civil Procedure 1.418. Finally, the court of appeals concluded that a necessary element in establishing an implied-in-fact contract is that the services performed be beneficial to the alleged obligor. It concluded .that Roger’s had failed to show that its services benefited Nichols.

III. Whether Suit on an Open Account is a Discrete Cause of Action With Fixed Elements.

In concluding that suit on an open account is a discrete cause of action with fixed elements, the court of appeals relied on two lines of authority neither of which provide a satisfactory resolution of the issue. First, the court of appeals relied on the statements in Griffith v. Portlock, 233 Iowa 492, 7 N.W.2d 199 (1942), and Tucker v. Quimby, 37 Iowa 17 (1873), indicating that

[a] “continuous, open, current account” is one “which is not interrupted or bro *650 ken, not closed by settlement or otherwise, and is a running, connected series of transactions.”

Griffith, 233 Iowa at 498, 7 N.W.2d at 202 (quoting Tucker, 37 Iowa at 19). The Griffith and Tucker cases were not concerned with establishing the elements for recovery in an action on an open account. Rather, these cases dealt with the requirements to show that an open account existed for purposes of establishing the statute of limitations set forth in Iowa Code section 614.5 and its statutory predecessors. Consequently, we find these cases to be inappo-site.

The court of appeals further described an open account as involving

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ZT Enterprises, Inc. v. Alan Pedersen
Court of Appeals of Iowa, 2020
Danaher v. Harrington
838 F. Supp. 2d 867 (S.D. Iowa, 2012)
Capital One Bank (USA), N.A. v. Denboer
791 N.W.2d 264 (Court of Appeals of Iowa, 2010)
Western Reserve Life Assur. Co. of Ohio v. Bratton
464 F. Supp. 2d 814 (N.D. Iowa, 2006)
Iowa Network Services, Inc. v. Qwest Corp.
385 F. Supp. 2d 850 (S.D. Iowa, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
681 N.W.2d 647, 2004 Iowa Sup. LEXIS 198, 2004 WL 1336257, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rogers-backhoe-service-inc-v-nichols-iowa-2004.