Gehrke, Inc. v. Steeple Chase Farms, LLC and the New Modern Concepts, Inc., Steeple Chase Farms, LLC and the New Modern Concepts, Inc., Counterclaim-Plaintiffs v. Gehrke, Inc., Counterclaim-Defendant.

Court of Appeals of Iowa·Decided January 13, 2016·No. 15-0601·Published

Opinion

IN THE COURT OF APPEALS OF IOWA

No. 15-0601

Filed January 13, 2016

GEHRKE, INC., Plaintiff-Appellee,

vs.

STEEPLE CHASE FARMS, LLC and THE NEW MODERN CONCEPTS, INC., Defendants-Appellants.

STEEPLE CHASE FARMS, LLC and THE NEW MODERN CONCEPTS, INC., Counterclaim-Plaintiffs,

vs.

GEHRKE, INC., Counterclaim-Defendant.

Appeal from the Iowa District Court for Hardin County, Kurt L. Wilke, Judge.

A property owner and a general contractor appeal the district court’s ruling in favor of a subcontractor. AFFIRMED.

Brian Rickert, Michael R. Blaser, and Brant D. Kahler of Brown, Winick, Graves, Gross, Baskerville & Schoenebaum, P.L.C., Des Moines, for appellants/counterclaim appellants.

Stephen E. Doohen of Whitfield & Eddy, P.L.C., Des Moines, for appellee.

Heard by Potterfield, P.J., and Doyle and Tabor, JJ.

TABOR, Judge.

A hog confinement facility under construction in Hardin County incurred damage to its concrete manure pits following heavy rains over Memorial Day weekend in 2013. The facility’s owner and a general contractor1 brought claims against the excavation subcontractor for negligence, breach of contract, breach of express and implied warranties, indemnification and contribution, and unjust enrichment. The district court, recognizing the plaintiffs alleged five counts, found “the sum total” of their claims came “down to a question of negligence.” The court decided if the plaintiffs were unable to establish negligence on the part of the subcontractor “then all of their theories fail.” The court ruled the subcontractor was not negligent and dismissed the other four claims. On appeal, the plaintiffs contend the record lacks substantial evidence to support the court’s determination the subcontractor was not negligent. They also contend the court erred in dismissing the other four claims “for failure to prove negligence” without providing a more detailed analysis.

Because substantial evidence underpins the court’s finding the subcontractor was not negligent and because the same allegations of negligent workmanship form the basis for the plaintiffs’ other claims, we affirm. I. Background Facts and Proceedings Construction. Farmer Steve Liston contacted Iowa Select Farms, a pork production company based in Iowa Falls, about selling a parcel of his land for a

1 Steeple Chase Farms, LLC and New Modern Concepts, Inc. were the defendants in the original mechanic’s lien foreclosure action brought by Gehrke, Inc., but it is their counterclaims at issue on appeal. We will refer to them jointly as the plaintiffs or as New Modern unless a specific designation to Steeple Chase is warranted.

hog confinement facility. In return for the land sale, Liston wanted a manure easement for crop fertilizer. Liston negotiated the deal with William Foley, Iowa Select’s chief financial officer. Foley also manages Steeple Chase Farms, a single member L.L.C. owned by Jeffrey Hanson, Iowa Select’s chief executive officer. Hanson’s wife, Debora, owned New Modern Concepts, Inc., which acted as the general contractor on construction projects undertaken by Steeple Chase.

Steeple Chase bought a rectangular 4.5 acre lot from Liston located near Owasa and bordering the south side of county road D-35. Foley submitted plans for a two-building, 4800-head hog confinement to Hardin County and the Iowa Department of Natural Resources (DNR). Foley testified obtaining a permit was not an “in-depth process.” Foley planned to situate rectangular hog buildings lengthwise, west to east, eighty feet apart. Foley placed the western sides of the buildings one hundred feet from the west lot line and the eastern sides sixty feet from the east lot line. Foley, who did not obtain site elevations before planning the layout, located the driveway on the west side. Liston’s corn bins were west of the hog facility’s lot line.

After Foley submitted his proposal, the county informed him the county intake tile was located in the ditch on the south side of D-35 and north of the proposed north building. The county tile line ran under the center of the proposed confinement buildings before exiting in the southeast corner of the lot. The county required Steeple Chase to reroute the county tile so it did not run under the new buildings. Steeple Chase received the necessary approvals to go forward.

The diagram below illustrates the facility plan Foley created.

The Owasa lot also contained farm tile lines running north/south through the lengths of both buildings. Foley did not know the Owasa site contained tile lines. Foley testified an excavator generally would reroute smaller diameter farm tile as a part of its overall bid, but he expected to pay extra if an excavator had to reroute a county tile line due to its larger diameter. Foley also expected the

excavator to look at the topography in advance and determine how to dig and where to pile the over-dig or spoils.

New Modern, the general contractor, did not perform any of the construction itself; it hired experienced subcontractors. Adjacent landowner Liston recommended Foley use Gehrke, Inc. for the excavation because its owner, Steve Gehrke, had done previous drainage projects for Liston. Foley contacted Gehrke for help in locating the county tile. Thereafter, Foley solicited a bid from Gehrke, who had extensive experience in digging manure pits. In Gehrke’s twenty-eight years as an excavation contractor, he had dug pits for roughly 800 to 1000 confinement buildings, including past work for New Modern.

Gehrke kept a map of the drainage tiles on Liston’s farm because he had completed tile work for Liston. In general, surface water flowed across the Steeple Chase lot from the southwest corner toward the northeast corner. Based on the map showing numerous tiles in a cross-hatch pattern on the acreage sold to Steeple Chase, Gehrke knew the lot was wet ground.

In April 2013, shortly after New Modern told Gehrke the driveway would be located on the west side of the lot, Gehrke submitted a written quote to the general contractor for $34,500 in excavation services (manure pits under each building, including rough and final backfills and rock spreading) and for $5200 to reroute the county tile. On April 25, 2013, New Modern accepted Gehrke’s written offer by issuing a purchase order to Gehrke detailing those items and agreeing to pay the prices Gehrke quoted. The purchase order also asked Gehrke to install a silt fence for $1060 and provide rock for $2878.84. Gehrke

agreed and did so. New Modern contends Gehrke’s April bid and its purchase order constitutes the parties’ contract.

Gehrke ran site elevations on the lot before digging and learned the ground one hundred feet to the east of the southwest corner was slightly more than two feet higher than the ground at the southwest corner. He concluded the “water naturally drains to the west on the south side of the property for the first hundred feet. And then after that, the water goes to the east.” Gehrke also learned the east end of the site was higher; therefore, more water would be running on the west end of the site.

Gehrke started work in late April. A few days into his work, Gehrke asked New Modern’s site manager Darrell Hunt if the driveway could be moved to the east side of the buildings. Hunt knew the east side was higher, did not disagree with Gehrke’s idea, and passed the request on to Foley. Hunt did not ask Liston if moving the driveway to the east was possible. Based on the flow of surface water shown by his elevations, in Gehrke’s opinion the driveway and truck access on the east end of the lot “would have been much better for this site.” Specifically,

[They could] flip flop the distance they bought from Steve Liston, take 100’ off the east end, and move the 60’ . . . to the west end.

They wouldn’t have been buying any more acres total. It would have been a much better way to deal with the water problems.

Free access — add to your briefcase to read the full text and ask questions with AI

Gehrke, Inc. v. Steeple Chase Farms, LLC and the New Modern Concepts, Inc., Steeple Chase Farms, LLC and the New Modern Concepts, Inc., Counterclaim-Plaintiffs v. Gehrke, Inc., Counterclaim-Defendant., (iowactapp 2016).

Gehrke, Inc. v. Steeple Chase Farms, LLC and the New Modern Concepts, Inc., Steeple Chase Farms, LLC and the New Modern Concepts, Inc., Counterclaim-Plaintiffs v. Gehrke, Inc., Counterclaim-Defendant. (Gehrke, Inc. v. Steeple Chase Farms, LLC and the New Modern Concepts, Inc., Steeple Chase Farms, LLC and the New Modern Concepts, Inc., Counterclaim-Plaintiffs v. Gehrke, Inc., Counterclaim-Defendant.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Hilsman v. Phillips
764 N.W.2d 784 (Court of Appeals of Iowa, 2009)
Sun Valley Iowa Lake Ass'n v. Anderson
551 N.W.2d 621 (Supreme Court of Iowa, 1996)
Neimann v. Butterfield
551 N.W.2d 652 (Court of Appeals of Iowa, 1996)
RET Corp. v. Frank Paxton Co., Inc.
329 N.W.2d 416 (Supreme Court of Iowa, 1983)
Royal Indemnity Co. v. Factory Mutual Insurance Co.
786 N.W.2d 839 (Supreme Court of Iowa, 2010)
Meier v. SENECAUT III
641 N.W.2d 532 (Supreme Court of Iowa, 2002)
State v. Mann
602 N.W.2d 785 (Supreme Court of Iowa, 1999)
Pursell Construction, Inc. v. Hawkeye-Security Insurance Co.
596 N.W.2d 67 (Supreme Court of Iowa, 1999)
McPherrin v. Jennings
24 N.W. 242 (Supreme Court of Iowa, 1885)
Ideal Heating Co. v. Kramer
102 N.W. 840 (Supreme Court of Iowa, 1905)