Idaho Transportation Department v. Ascorp, Inc.

357 P.3d 863, 159 Idaho 138, 2015 Ida. LEXIS 249
CourtIdaho Supreme Court
DecidedSeptember 25, 2015
Docket42018
StatusPublished
Cited by30 cases

This text of 357 P.3d 863 (Idaho Transportation Department v. Ascorp, Inc.) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Idaho Transportation Department v. Ascorp, Inc., 357 P.3d 863, 159 Idaho 138, 2015 Ida. LEXIS 249 (Idaho 2015).

Opinion

WALTERS, J. pro term.

This is an appeal from an order of the district court awarding attorney fees to As-corp, Inc. d/b/a Debco Construction (Debco) against the Idaho Transportation Department (ITD) in a declaratory judgment action filed by ITD to determine rights of the parties with respect to a contract for highway construction services on a project in Twin Falls, Idaho. The district court dismissed the action upon Debco’s motion under Idaho Rule of Civil Procedure 12(b)(6) and awarded attorney fees to Debco under Idaho Code section 12-120(3). On appeal ITD argues that the district court erred in determining that the declaratory judgment action qualified as a dispute involving a commercial transaction required for the application of Idaho Code section 12-120(3). We affirm the order of the district court.

I. Factual and Procedural Background

While somewhat convoluted in its background, this appeal stems from a dispute over amounts due and owing under a state highway contract. Debco Construction and ITD entered into a contract whereby Debco agreed to provide construction services on a state highway project in Twin Falls, Idaho, known as the Washington Street Project. The contract included a process (Specifications) for adjustment of the construction price and contained provisions covering alternative dispute resolution, a review process for all claims arising under the contract, and a binding arbitration clause. The interplay of these Specifications was at the core of the dispute underlying this lawsuit. During the course of the construction project at issue, ITD agreed to certain adjustments that increased the amount paid to Debco. In addition to these already-paid increases, Debco asserted that approximately $3,000,000 was due and owing to Debco. This action as originally filed centered on how Debco attempted to collect these additional amounts.

Under the terms of the Specifications, ITD had the opportunity to resolve all claims by way of a claims review process prior to being subjected to binding arbitration. The review process, titled “Administrative Process,” required submission of any claim to ITD’s engineers. Debco filed a claim with ITD seeking payment of an additional $3,120,982.74. 1 This- constituted the start of the claims review process outlined in the Specifications. One day later, however, Debco filed an arbitration demand with the American Arbitration Association (AAA), the entity identified in the Specifications. So as to avoid any waiver in the AAA proceedings, ITD responded to the arbitration demand and also filed a motion with AAA to stay the proceedings pending exhaustion of ITD’s claims review process. Debco opposed ITD’s motion to stay, and AAA denied ITD’s motion by email notice to counsel for both parties. The assigned arbitrator stated, “Absent mutual agreement or court order, [AAA] shall proceed with the administration of this matter.”

In response to Debco’s resort to arbitration, ITD commenced the instant action in district court for declaratory and injunctive relief to enforce the contract’s claims review provision. ITD alleged that Debco had failed to exhaust the claims process outlined in the Specifications prior to demanding arbitration. ITD asserted the provision in the construc *140 tion contract required Debco to submit all claims to ITD’s engineers before invoking the arbitration clause, compelling Debco to exhaust the claims process prior to pursuing a binding arbitration covering the claim. Debco thereafter moved to dismiss the complaint, arguing that questions of procedural arbitrability were matters for arbitrators to decide.

While Debeo’s motion to dismiss was pending before the district court, AAA scheduled a preliminary arbitration hearing and requested initial payment from the parties on or before the scheduled hearing. Based on this pending hearing and AAA’s request for initial payment, ITD filed motions -with the district court seeking a temporary restraining order (TRO) and a preliminary injunction to enjoin the arbitration proceedings. The next day, Debco filed an opposition to ITD’s request for temporary and injunctive relief on grounds that Debco had paid both parties’ initial AAA fees. At a telephonic conference, the district court denied ITD’s motion for a TRO reasoning that Debco’s payment of the AAA fees removed the pending harm to ITD.

AAA held a preliminary arbitration hearing. Based on ITD’s request for more time to administer its claims process, the arbitration panel refused to schedule a full arbitration hearing on the merits of Debeo’s claim. Given the extension granted by AAA, ITD withdrew its motion seeking a preliminary injunction. The district court subsequently held a hearing on Debco’s motion to dismiss ITD’s complaint. At the conclusion of the hearing, the court ruled from the bench, granting the motion and dismissing ITD’s complaint pursuant to Idaho Rule of Civil Procedure 12(b)(6) based on its interpretation of this Court’s decision in Storey Construction, Inc. v. Hanks, 148 Idaho 401, 224 P.3d 468 (2009). The district court issued a written order memorializing its oral ruling and entered a separate judgment in Debco’s favor on all claims asserted against Debco in ITD’s complaint. 2 Debco sought an award for costs and attorney fees. Over ITD’s objection, the court awarded Debco approximately $25,000 in attorney fees and costs.

ITD appealed the district court’s dismissal of its complaint, as well as the award of attorney fees and costs to Debco. After the case was set for argument before this Court, counsel for ITD filed a notice of settlement and memorandum agreement in mediation advising of the “full and final settlement and resolution of all claims of any nature whatsoever arising out of their contractual relationship on the Washington Street Project.” The agreement recited that the settlement “does not affect the pending Supreme Court appeal (Idaho).” Based on this filing, this Court vacated the scheduled argument and conditionally dismissed the appeal. In response, Debco moved for this Court to reinstate the appeal so as to allow argument on the issue of attorney fees, which was encompassed by the appeal. This Court reset the matter for argument on the issue of attorney fees only.

II. Issues on Appeal

1. Whether the district court erred in awarding attorney fees and costs to Deb-co.

2. Whether attorney fees and costs on appeal should be awarded.

III. Standard op Review

The awarding of attorney fees and costs is within the discretion of the trial court and subject to review for an abuse of discretion. Smith v. Mitton, 140 Idaho 893, 897, 104 P.3d 367, 371 (2004). When we consider whether a trial court abused its discretion, the standard is whether the court perceived the issue as discretionary, acted within the boundaries of its discretion and consistently with the legal standards applicable to the specific choices available, and reached its decision by and exercise of reason. Magleby v. Garn, 154 Idaho 194, 196-97, 296 P.3d 400, 402-03 (2013).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vaughan v. Gateway Park, LLC
Idaho Supreme Court, 2025
Petersen v. Millennial Development Partners, LLC
567 P.3d 780 (Idaho Supreme Court, 2025)
Litster v. Litster Frost
Idaho Supreme Court, 2024
Carter Dental v. Carter
551 P.3d 1225 (Idaho Supreme Court, 2024)
Herndon v. City of Sandpoint
531 P.3d 1125 (Idaho Supreme Court, 2023)
Treasure Valley Home Solutions, LLC v. Chason
524 P.3d 1272 (Idaho Supreme Court, 2023)
Cover v. ID Board of Correction
Idaho Supreme Court, 2020
Smith v. Smith
Idaho Supreme Court, 2020
Guenther v. Ryerson
458 P.3d 184 (Idaho Supreme Court, 2020)
Ciccarello v. Davies
456 P.3d 519 (Idaho Supreme Court, 2019)
SilverWing v. Bonner County
Idaho Supreme Court, 2019
Silverwing At Sandpoint, LLC v. Bonner Cnty.
435 P.3d 1106 (Idaho Supreme Court, 2019)
Thurston and T3 v. Safeguard
Idaho Supreme Court, 2019
Thurston Enters., Inc. v. Safeguard Bus. Sys., Inc.
435 P.3d 489 (Idaho Supreme Court, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
357 P.3d 863, 159 Idaho 138, 2015 Ida. LEXIS 249, Counsel Stack Legal Research, https://law.counselstack.com/opinion/idaho-transportation-department-v-ascorp-inc-idaho-2015.