Brunobuilt, Inc. v. Briggs Engineering, Inc.

CourtIdaho Supreme Court
DecidedMarch 7, 2023
Docket49176
StatusPublished

This text of Brunobuilt, Inc. v. Briggs Engineering, Inc. (Brunobuilt, Inc. v. Briggs Engineering, Inc.) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brunobuilt, Inc. v. Briggs Engineering, Inc., (Idaho 2023).

Opinion

IN THE SUPREME COURT OF THE STATE OF IDAHO

Docket No. 49176

BRUNOBUILT, INC., an Idaho corporation, ) ) Plaintiff-Appellant, ) Boise, January 2023 Term ) v. ) Opinion filed: March 7, 2023 ) BRIGGS ENGINEERING, INC., an Idaho ) Melanie Gagnepain, Clerk corporation; DEAN W. BRIGGS, ) ) Defendants-Respondents, ) ) and ) ) MATERIALS TESTING & INSPECTION, ) LLC, an Idaho limited liability company; ) KEVIN L. SCHROEDER, CHARLES E. ) KAISER, ELIZABETH BROWN, DAVID O. ) CRAM, ERSTAD ARCHITECTS, PA, an ) Idaho professional service corporation; ) ANDREW C. ERSTAD, CHERYL PEARSE, ) TREASURE VALLEY ENGINEERS, INC., ) an Idaho corporation; MATRIX ) ENGINEERING, INC., an Idaho corporation; ) DOUGLAS L. UNGER, KLEINFELDER, ) INC., a California corporation; and G. ) ALEXANDER RUSH, ) ) Defendants. )

Appeal from the District Court of the Fourth Judicial District of the State of Idaho, Ada County. Steven J. Hippler, District Judge.

The judgment of the district court is affirmed.

McConnell Wagner Sykes & Stacey, PLLC, Boise, for Appellant. Richard Lee Stacey, Jr. argued.

Cummings Law Offices, Boise, for Respondents. Richard Cummings argued. _______________________________________________

MOELLER, Justice.

1 This appeal stems from a professional malpractice lawsuit following a landslide in the Boise foothills. BrunoBuilt, Inc., was constructing a custom home on a vacant lot in 2016 when a landslide occurred beneath the Terra Nativa subdivision. Following damage to the lot, BrunoBuilt filed a professional negligence suit against numerous engineers and engineering firms involved in the construction of the subdivision, arguing that they failed to identify preexisting landslide conditions and other geological circumstances that made residential development unsafe at this site. Over two years later, in the fall of 2018, BrunoBuilt discovered additional damage to the finished custom home itself. It then brought suit against additional defendants, including Briggs Engineering, Inc., and Erstad Architects. 1 Briggs Engineering filed a motion for summary judgment, which the district court granted. The court concluded that BrunoBuilt’s action was time barred by the two-year statute of limitations under Idaho Code section 5-219(4). BrunoBuilt appealed this decision. It argued that the malpractice claim did not begin to accrue until there was damage to the custom home, rather than just the land. We disagree with BrunoBuilt’s analysis and affirm the district court that BrunoBuilt’s claim is time barred. I. FACTUAL AND PROCEDURAL BACKGROUND This case concerns damage to a residential construction project in the Terra Nativa subdivision caused by a landslide in the foothills northeast of Boise, Idaho. Work on this subdivision began back in 1998, with multiple engineering firms employed over the years to complete the various phases of development amidst market fluctuations and delays. One engineering firm, Strata, Inc., completed a geotechnical engineering report of the area in 2003. This report was independently reviewed by Kleinfelder, Inc., an engineering firm hired by the City of Boise, to evaluate Strata’s compliance with the City of Boise Hillside Development Manual and its engineering requirements to ensure safe residential development. Boise approved the plats and, in 2004, the Terra Nativa property was annexed into the City of Boise. In 2014, Amy and William Dempsey purchased a vacant property lot (“Lot 16”) in Terra Nativa. At the time the Dempseys acquired the property, it was bare land with no structures on it. The Dempseys first hired Erstad Architects, PA, 2 to design their home. As part of the property’s

1 BrunoBuilt’s lawsuit against the Erstad Architects is the subject of a companion appeal. 2 At all relevant times to this appeal, Erstad Architects was organized as Erstad Architects, PA. However, Erstad Architects, PA, filed a statement of conversion and converted to a general business corporation (Erstad Architects, 2 development, Erstad entered into a contract with Dean Briggs, of Briggs Engineering, Inc., (collectively “Briggs Engineering”) to perform civil engineering services, including the preparation of a site grading and drainage plan as well as an erosion control plan for Lot 16. “The scope of work involved surface soils and water,” but it did not involve geotechnical services. In July 2015, the Dempseys separately contracted with BrunoBuilt, Inc., to build a custom home designed by Erstad. Pursuant to a construction agreement, the Dempseys transferred ownership of Lot 16 to BrunoBuilt, via a quitclaim deed, as security for their construction contract with the agreement to pay for the home upon its completion. Construction on the home commenced in 2015 and continued into 2016. In February 2016, the lands beneath the Terra Nativa subdivision began to slide. Several homes within the subdivision were damaged by earth movement. At this time, the Dempseys’ home was practically complete. In an affidavit that Mr. Bruno later submitted in connection with this litigation, he stated that “[i]n anticipation of securing a certificate of occupancy, [the] final heating, final plumbing, final electrical, and final building inspections were conducted in and around February and March of 2016.” Although the Dempseys’ home had passed all final building inspections, cracks in the soil began appearing in the yard. By April, a landslide scarp 3 became visible and certain utilities had to be relocated. Robert Bruno’s affidavit detailed the damages from the landslide: 9. As a result of the landslide, utility, highway district, and fire department services were all terminated, and the City of Boise withheld their certificate of occupancy. Portions of the utility lines were physically damaged and/or severed by the landslide. 10. BrunoBuilt immediately began working with the utility entities on solutions to resume services to the Dempsey Lot. The utility lines have to be rerouted to the Dempsey Home before the utilities can be turned back on. To restore the utilities, BrunoBuilt will be required to perform or pay for the majority of work for rerouting the utility lines and services, including buying a transformer, installing the conduit, installing 500 feet of water line, and 500 feet of sewer line, as well as all the trenching, backfilling and concrete replacement. Based on requirements from the Fire Department, BrunoBuilt will also be required to widen the driveway to 20 feet

Inc.) on November 30, 2021. Throughout this appeal, “Erstad Architects, PA” or “Erstad Architects” is used to refer to the general corporation that is now organized as Erstad Architects, Inc. 3 A scarp is “a steep (nearly vertical) region of exposed soil and rock at the head of the landslide” where the movement of adjacent land exposes part of the subsurface. Landslide Features, Kansas Geological Survey: Public Outreach https://www.kgs.ku.edu/Publications/pic13/pic13_2.html (last visited February 6, 2023). 3 wide to accommodate a fire truck. The City of Boise has also required a retaining wall be installed in order to retain topsoil. 11. To this date, BrunoBuilt still has not been able to secure a certificate of occupancy for the Dempsey Home, and has had to incur increased costs based on the demands of the City for the certification of occupancy. BrunoBuilt had to build a retaining wall, grade the land, remedy the surface cracking in the yard, buy a transformer, reroute utilities, install sewer and water lines, and complete “all the trenching, backfilling and concrete replacement” required to restore service to the Dempsey home. 4 BrunoBuilt also hired a surveyor at this time to determine whether the finished home had been affected by the landslide, who confirmed that he did not detect movement of the home at that time.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brian & Christie, Inc. v. Leishman Electric, Inc.
244 P.3d 166 (Idaho Supreme Court, 2010)
Bagley v. Thomason
241 P.3d 972 (Idaho Supreme Court, 2010)
Aardema v. U.S. Dairy Systems, Inc.
215 P.3d 505 (Idaho Supreme Court, 2009)
McCabe v. Craven
188 P.3d 896 (Idaho Supreme Court, 2008)
Ramerth v. Hart
983 P.2d 848 (Idaho Supreme Court, 1999)
Clark v. International Harvester Co.
581 P.2d 784 (Idaho Supreme Court, 1978)
Salmon Rivers Sportsman Camps, Inc. v. Cessna Aircraft Co.
544 P.2d 306 (Idaho Supreme Court, 1975)
Brower v. EI DuPont De Nemours and Co.
792 P.2d 345 (Idaho Supreme Court, 1990)
Tusch Enterprises v. Coffin
740 P.2d 1022 (Idaho Supreme Court, 1987)
Great Plains Equipment, Inc. v. Northwest Pipeline Corp.
36 P.3d 218 (Idaho Supreme Court, 2001)
Blahd v. Richard B. Smith, Inc.
108 P.3d 996 (Idaho Supreme Court, 2005)
City of Kellogg v. Mission Mountain Interests Ltd., Co.
16 P.3d 915 (Idaho Supreme Court, 2000)
City of McCall v. Buxton
201 P.3d 629 (Idaho Supreme Court, 2009)
Idaho Transportation Department v. Ascorp, Inc.
357 P.3d 863 (Idaho Supreme Court, 2015)
Krinitt v. Idaho Department of Fish & Game
398 P.3d 158 (Idaho Supreme Court, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
Brunobuilt, Inc. v. Briggs Engineering, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/brunobuilt-inc-v-briggs-engineering-inc-idaho-2023.