Hymas v. UAP Distribution, Inc.

272 P.3d 889, 167 Wash. App. 136
CourtCourt of Appeals of Washington
DecidedMarch 8, 2012
Docket29906-6-III
StatusPublished
Cited by14 cases

This text of 272 P.3d 889 (Hymas v. UAP Distribution, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hymas v. UAP Distribution, Inc., 272 P.3d 889, 167 Wash. App. 136 (Wash. Ct. App. 2012).

Opinion

*140 Siddoway, J.

¶1 We are called upon to decide whether UAP Distribution Inc., the owner of a jobsite at which John Hymas was seriously injured while working construction, was entitled to summary judgment that it had no statutory or common law duty that could give rise to liability for Mr. Hymas’s fall into an unguarded trench. Mr. Hymas, whose employer was UAP’s cement contractor, argues that UAP owed him a duty of care under WISHA, 1 as a jobsite owner, because it retained control over his employer’s work. He argues that UAP owed him a duty under common law, as a landowner, because it should have anticipated that Mr. Hymas could be injured despite his knowledge of the open trench. We find no issues requiring trial and agree with the trial court that on the evidence presented UAP owed no duty as a matter of law. We affirm the dismissal of Mr. Hymas’s claims.

FACTS AND PROCEDURAL BACKGROUND

¶2 UAP Distribution Inc. 2 is a chemical and fertilizer manufacturer that does a nationwide business. In 2006, it contracted with Raneo Fertiservice Inc., a manufacturer of fertilizer-handling equipment, to develop plans for constructing a fertilizer mixing plant on land that UAP owned *141 in Plymouth, Washington. UAP did not hire a general contractor to manage the construction work. Instead, armed with Ranco’s plans, it contracted directly with an engineering firm and specialty contractors. UAP had opted to forgo the services of a general contractor on earlier construction projects.

¶3 Ranco’s plans called for the excavation of a 5-foot-deep, 240-foot-long, 10-foot-wide trench framed with concrete within one of three buildings proposed for the plant, in which a below-grade conveyor belt would eventually be installed. UAP hired Narum Concrete Construction Inc. to perform the excavation and concrete work.

¶4 UAP and Narum entered into a written contract prepared using an American Institute of Architects (ALA) standard form agreement. 3 Subsection 8.2.1 of the contract (under article 8, “CONTRACTOR,” and section 8.2, “SUPERVISION AND CONSTRUCTION PROCEDURES”) provides:

The Contractor [Narum] shall cooperate fully with the Owner [UAP] and Architect and supervise and direct the Work, using the Contractor’s best skill and attention. The Contractor shall be solely responsible for and have control over construction means, methods, techniques, sequences and procedures, and for coordinating all portions of the Work under the Contract, unless the Contract Documents give other specific instructions concerning these matters.

Clerk’s Papers (CP) at 96 (redlining 4 omitted). Sections 15.1 and 15.3 of the contract, under article 15, “PROTECTION OF PERSONS AND PROPERTY,” provide in part:

15.1 SAFETY PRECAUTIONS AND PROGRAMS
The Contractor shall be responsible for initiating, maintaining and supervising all safety precautions and programs in connec *142 tion with the performance of the Contract. The Contractor shall take reasonable precautions for safety of, and shall provide reasonable protection to prevent damage, injury or loss to:
.1 employees on the Work and other persons who may be affected thereby;
.2 the Work and materials and equipment to be incorporated therein; and
.3 other property at the site or adjacent thereto.
The Contractor shall give notices and comply with applicable laws, ordinances, rules, regulations and lawful orders of public authorities bearing on safety of persons and property and their protection from damage, injury or loss. . . .
15.3 The Contractor shall comply with all applicable safety laws and regulations. Notwithstanding any language to the contrary, the Owner and the Architect shall not have any responsibility for job site inspections or safety accommodations. Any inspections or observations by the Owner or the Architect are solely for the benefit of the Owner and shall not create any duties or obligations to anyone else.

CP at 104 (redlining omitted). The contract gave UAP the right to terminate the contract for any reason, approve subtier contractors, perform the construction work with its own forces, inspect the work, stop or delay the work, order changes to the work, and reject the work.

¶5 On February 9, 2007, Narum employees were at the jobsite performing concrete work. Mr. Hymas, a concrete pump operator, was operating the pumper truck remotely. His work required that he follow along as a co-worker, who was holding a discharge hose supported by a crane, poured concrete into forms at an elevation 15 feet above them. While watching the pour, Mr. Hymas regulated the pressure and flow of the concrete using a wireless remote box that he wore as a backpack, the controls resting on his chest. At the time of the accident resulting in this action, Mr. Hymas was following his co-worker alongside the trench, which had by *143 then been framed with concrete. While operating the pump, Mr. Hymas stepped over the edge, which was unguarded by safety rails, and fell into the trench. He seriously injured his leg.

¶6 Mr. Hymas brought this action against UAP, asserting that UAP failed to maintain the trench in compliance with WISHA regulations and negligently failed to protect or warn him of a hazardous condition. His complaint implicated issues of whether and to what extent UAP had retained or exercised control over Narum’s work. The parties engaged in deposition and other discovery into their representatives’ understandings of the contract and UAP’s actual working relationship with Narum and other specialty contractors.

¶7 Evidence as to the parties’ background, beliefs, and actions was essentially undisputed. It established that before building the Plymouth plant, UAP had entered into contracts with specialty contractors on 24 occasions. In connection with construction of the Plymouth plant it contracted not only with Raneo, but with an engineering firm, an electrical contractor, a construction company engaged to pipe water to the site, a shed manufacturer engaged to erect a control room, and a material testing and inspection firm to perform site inspections and quality control. UAP exercised its contractual right to perform a portion of Ranco’s work, painting pieces of the steel frame for the building that had been scratched in transit and having two idle employees from its Moses Lake facility assist Raneo employees with other painting and welding. In the second phase of the plant, it terminated a pipefitting contractor whose pace was slowing the project and took over the work with its own employees. UAP paid the specialty contractors directly, for a total project cost of over $4 million.

¶8 UAP area manager Brian Jones visited the work site frequently at first and “every couple weeks” as the project progressed. CP at 251. While Narum was on-site, Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City Of Sedro Woolley, V. Philip A. Murray
Court of Appeals of Washington, 2025
State of Washington v. Shawndrae Don-L Huff
Court of Appeals of Washington, 2024
Jody Aucoin, V. C4digs, Inc
555 P.3d 884 (Court of Appeals of Washington, 2024)
Marriage Of Ann Weaver, V. Geoffrey Norman Weaver
Court of Appeals of Washington, 2023
Exxonmobil Oil Corp, V. Wayne Wright
Court of Appeals of Washington, 2021
Golik v. CBS Corp.
472 P.3d 778 (Court of Appeals of Oregon, 2020)
Roy D. Cheesman v. John Graf
Court of Appeals of Washington, 2020
State of Washington v. Amel William Dalluge
Court of Appeals of Washington, 2015
Garrison v. SagePoint Financial, Inc.
185 Wash. App. 461 (Court of Appeals of Washington, 2015)
Miguel Gaona v. Glen Acres Golf & Country Club
Court of Appeals of Washington, 2014
Garrison Family v. Mark And Michelle Garrison
Court of Appeals of Washington, 2014
Kevin Grudzinski v. Randy Grudzinski, et ux
Court of Appeals of Washington, 2013

Cite This Page — Counsel Stack

Bluebook (online)
272 P.3d 889, 167 Wash. App. 136, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hymas-v-uap-distribution-inc-washctapp-2012.