Hutton Construction, Inc. v. Continental Western Insurance Company

2022 DNH 076
CourtDistrict Court, D. New Hampshire
DecidedJuly 5, 2022
Docket21-cv-706-PB
StatusPublished
Cited by1 cases

This text of 2022 DNH 076 (Hutton Construction, Inc. v. Continental Western Insurance Company) is published on Counsel Stack Legal Research, covering District Court, D. New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hutton Construction, Inc. v. Continental Western Insurance Company, 2022 DNH 076 (D.N.H. 2022).

Opinion

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW HAMPSHIRE

Hutton Construction, Inc.

v. Case No. 21-cv-706-PB Opinion No. 2022 DNH 076 Continental Western Insurance Company

MEMORANDUM AND ORDER

This insurance coverage case stems from a subcontractor’s defective

masonry work. The principal issue presented by the insurer’s motion for

partial summary judgment is whether the subcontractor’s comprehensive

general liability policy covers stipulated delay damages that the general

contractor incurred when the subcontractor’s faulty work caused a building

inspector to issue a stop-work order for the entire project.

I. BACKGROUND

In 2018, Hutton Construction Inc. entered into a build-to-suit lease

with O’Reilly’s Auto Enterprises, LLC to construct an auto parts store on

property Hutton owned in Ossipee, New Hampshire. The lease required

construction be completed within 125 days and imposed stipulated damages

of $1,000 for each additional day that the project remained unfinished. Hutton served as the general contractor for the project and

subcontracted with Frederick A. Meyer III & Sons, Inc. to construct the

building’s exterior masonry walls. The subcontract obligated Meyer to

complete the masonry work per the stipulated schedule and indemnify

Hutton against any claims, damages, or losses caused in whole or in part by

Meyer’s negligence. Construction began in July and was scheduled to be

finished in November. After Meyer completed a sufficient portion of the

exterior masonry work, Hutton began work on the roof and the interior of the

building.

While the work was ongoing, the Ossipee building inspector identified

defects in Meyer’s masonry work, including a lack of proper grouting of the

concrete blocks that formed the walls. After Meyer failed to address the

inspector’s concerns, he issued a “stop-work order” in October that required

all work on the project to cease immediately. In support of his order, the

inspector cited Meyer’s failures to properly grout concrete blocks and

correctly install steel anchors that connected the roof framing to the walls.

Both defects potentially threatened the building’s structural integrity.

The stop-work order remained in place for about thirteen months.

During that time, water seeped into the building through the defective

masonry walls and the unfinished roof, damaging Hutton’s work on the

interior. The water damage included moldy sheetrock, rusty metal studs, and

2 water-filled insulation. After the stop-work order was lifted, Hutton needed

two additional months to fix the water damage and complete the project.

Meanwhile, Meyer fixed the defective masonry at its own expense.

The construction delay left Hutton responsible to O’Reilly’s for

stipulated damages of close to half a million dollars. Hutton subsequently

demanded that Meyer reimburse it for both the stipulated damages and the

costs it incurred to repair the water damage. Meyer submitted a claim for

coverage under a commercial general liability (“CGL”) insurance policy it had

purchased from Continental Western Insurance Company. After Continental

denied coverage, Meyer assigned Hutton its rights under the policy. Hutton

then filed this declaratory judgment action in state court, and Continental

later removed the case to federal court. Continental now moves for partial

summary judgment, limited to Hutton’s claim for the stipulated delay

damages. Hutton objects.

II. STANDARD OF REVIEW

Summary judgment is appropriate when the record reveals “no genuine

dispute as to any material fact and the movant is entitled to judgment as a

matter of law.” Fed. R. Civ. P. 56(a). In this context, a “material fact” is one

that has the “potential to affect the outcome of the suit.” Cherkaoui v. City of

Quincy, 877 F.3d 14, 23 (1st Cir. 2017) (cleaned up). A “genuine dispute”

3 exists if a factfinder could resolve the disputed fact in the nonmovant’s favor.

Ellis v. Fid. Mgmt. Tr. Co., 883 F.3d 1, 7 (1st Cir. 2018).

The movant bears the initial burden of presenting evidence that “it

believes demonstrates the absence of a genuine issue of material fact.”

Celotex Corp. v. Catrett, 477 U.S. 317, 323 (1986); accord Irobe v. U.S. Dep’t

of Agric., 890 F.3d 371, 377 (1st Cir. 2018). Once the movant has properly

presented such evidence, the burden shifts to the nonmovant to designate

“specific facts showing that there is a genuine issue for trial,” Celotex, 477

U.S. at 324, and to “demonstrate that a trier of fact could reasonably resolve

that issue in [its] favor.” Irobe, 890 F.3d at 377 (cleaned up). If the

nonmovant fails to adduce such evidence on which a reasonable factfinder

could base a favorable verdict, the motion must be granted. Celotex, 477 U.S.

at 324. In considering the evidence, the court must draw all reasonable

inferences in the nonmoving party’s favor. Theriault v. Genesis HealthCare

LLC, 890 F.3d 342, 348 (1st Cir. 2018).

Under New Hampshire law, the interpretation of an insurance policy is

a question of law. Town of Londonderry v. N.H. Mun. Ass’n Prop. Liab. Ins.

Tr., Inc., 140 N.H. 440, 441 (1995). “Where disputed terms are not defined in

a policy or by State judicial precedent, [courts] apply an objective standard,

construing the terms in context and as would a reasonable person in the

position of the insured, based upon more than a casual reading of the policy

4 as a whole.” Cath. Med. Ctr. v. Exec. Risk Indem., Inc., 151 N.H. 699, 701

(2005) (quoting Panciocco v. Lawyers Title Ins. Corp., 147 N.H. 610, 613

(2002)). Ambiguities in a policy must be resolved in favor of coverage.

Philbrick v. Liberty Mut. Fire Ins. Co., 156 N.H. 389, 391 (2007). The insurer

has the burden to prove that coverage is unavailable. Maville v. Peerless Ins.

Co., 141 N.H. 317, 320 (1996).

III. ANALYSIS

Continental cites three different policy provisions to support its refusal

to cover Hutton’s claims against Meyer. First, it argues that any property

damage Hutton suffered was not caused by an “occurrence.” Second, it argues

that the stipulated delay damages Hutton paid to O’Reilly’s are not a covered

form of “property damage.” Finally, it argues that Meyer’s right to coverage is

barred by the policy’s “your work” exclusion.

A. Occurrence

The Continental policy is a standard-form CGL policy. The insuring

agreement provides that Continental will “pay those sums that the insured

becomes legally obligated to pay as damages because of . . . ‘property damage’

to which this insurance applies.” Doc. No. 11–3 at 164. Coverage is available

under the policy, however, only if “‘property damage’ is caused by an

‘occurrence.’” Id. An “occurrence” is defined as “an accident, including

5 continuous or repeated exposure to substantially the same general harmful

conditions.” Id. at 178. The term “accident” is not defined in the policy.

Continental argues that the stipulated delay damages Hutton incurred,

both while the stop-work order was in effect and while Hutton was repairing

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2022 DNH 076, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hutton-construction-inc-v-continental-western-insurance-company-nhd-2022.