Dimambro-Northend Associates v. United Construction, Inc

397 N.W.2d 547, 154 Mich. App. 306
CourtMichigan Court of Appeals
DecidedSeptember 8, 1986
DocketDocket 83545
StatusPublished
Cited by13 cases

This text of 397 N.W.2d 547 (Dimambro-Northend Associates v. United Construction, Inc) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dimambro-Northend Associates v. United Construction, Inc, 397 N.W.2d 547, 154 Mich. App. 306 (Mich. Ct. App. 1986).

Opinion

Danhof, C.J.

Defendants United Construction, Inc., and Mancini Construction, Inc., a joint venture (United/Mancini), appeal as of right from the November 5, 1985, opinion and order of the Wayne Circuit Court in this construction contract case.

We agree with United/Mancini that the circuit court erroneously interpreted the comprehensive general liability insurance policy between United/ Mancini and its insurer, Admiral Insurance Company, third-party defendant. We reverse the opinion and order with respect to the circuit court’s decision on the issue of insurance coverage provided by Admiral and remand for further proceedings consistent with this opinion.

*309 This case enjoys a lengthy procedural history, a description of which is necessary to an informed understanding of the legal issues.

This appeal arises out of the consolidation of two lawsuits filed in the circuit court as a result of construction contracts which the Southgate-Wyandotte Relief Drain’s Drainage District (drainage board) awarded to two contractors for the construction of part of a sewer system. This construction involved some tunnel work. The drainage board awarded contract No. 3 to United/Mancini, and awarded contracts No. 5 and No. 7 to DiMambro-Northend Associates, the principal plaintiff in both lawsuits. The work of each contractor was to be independent and separate from that of the other contractors until such time as "activation” occurred, at which time the system would be completed.

On July 18, 1977, a fire occurred in the tunnel worked on by United/Mancini under contract No. 3. The circuit court ultimately found that the fire was a result of United/Mancini’s negligence. The fire caused physical damage to the tunnel and to property of United/Mancini only. However, the fire caused a delay in the completion of work by DiMambro, the contractor responsible for the tunnel portion adjacent to that of United/Mancini.

After the fire, United/Mancini petitioned the drainage board for an extension of time within which to complete their work. On May 17, 1978, the drainage board agreed to an extension until June 23, 1979, subject to an agreement by United/ Mancini to indemnify the drainage board against any damage claim or any claim for additional compensation by other contractors due to the delay caused by the fire and the extension of time.

On July 9, 1980, the first of two lawsuits (Case i) was filed by DiMambro against United/Mancini. *310 The complaint alleged that DiMambro had completed its work under the contract with the drainage board in November of 1977 but that DiMambro could not "connect up” and end the project because of the fire and resultant delay. The complaint sought "delay damages” including lost profits, increased labor costs, overhead costs and the like. The complaint alleged liability under the theories of negligence, tortious interference with DiMambro’s contractual relationship with the drainage board, and a theory that DiMambro was a third-party beneficiary to the contract between the drainage board and United/Mancini, which contract United/Mancini breached.

United/Mancini had obtained insurance from several carriers to cover its risk of liability for a policy period beginning July 1, 1976, to August 1, 1977. The Hartford Insurance Company was the primary insurer. The Hartford insurance policy provided two types of coverage: comprehensive general liability coverage up to $100,000 and comprehensive contractual liability coverage with a different dollar limit. Canadian Universal Insurance Company wrote insurance in "following form” above the Hartford limits to a limit of $500,000. Admiral, providing the third layer of insurance coverage, also wrote insurance in "following form” for the excess of the Canadian coverage. These insurance carriers, through their agent, certified to the drainage board that they had written the general liability and contractual liability insurance coverages in accordance with the tunnel contract bidding documents.

Shortly after Case i was filed, United/Mancini impleaded Admiral as third-party defendant. In turn, Admiral impleaded Hartford and Canadian as fourth-party defendants. United/Mancini believed that Admiral should defend and indemnify *311 it in Case i. Admiral claimed that the policy limits of the other carriers had not yet been exhausted and that they should be held liable first in the event of a judgment. At the time Case i was filed, the general liability limits of both the Hartford and Canadian policies had been exhausted. The contractual liability limits of Hartford’s policy were untouched, as were the limits of Admiral’s policy.

On November 20, 1980, DiMambro filed Case n in the Wayne Circuit Court. The complaint alleged breach of contract against the drainage board. Thereafter the drainage board filed a third-party complaint against United/Mancini on an indemnity theory, relying upon the earlier agreement of United/Mancini to indemnify the drainage board in return for an extension of time.

United/Mancini then impleaded all three insurance carriers into Case n, claiming that one or all of them should defend and indemnify United/Mancini in Case ii. DiMambro’s complaint in Case n essentially sought extra compensation. It is undisputed that the failure of DiMambro to complete performance was not the fault of DiMambro, but was the direct result of the fire and the extension of time granted to United/Mancini by the drainage board.

On June 1, 1982, the circuit court consolidated the two lawsuits for trial. It divided the consolidated lawsuits into phases for purposes of trial. In phase one, the circuit court was to determine liability, i.e., whether DiMambro was entitled to delay damages and additional compensation. In phase two, the court was to decide the amount of damages sustained by the parties, and in phase three, the court was to decide the issue of insurance coverage, i.e., the duties of the three insurers. *312 Each phase was conducted as a bench trial before the Honorable Circuit Judge Richard C. Kaufman.

In phase one, the circuit court determined that the fire was the result of United/Mancini’s negligence. Further, the circuit court determined that recovery was warranted on the negligence theory, on the third-party beneficiary theory, and on the theory that the drainage board breached its contract.

In phase two, the circuit court awarded money damages of $38,836.87 to DiMambro. The damage award reflected a ten percent increase in labor costs, increased costs for demobilization and remobilization of DiMambro’s work force, overhead, profit, interest, labor costs and lost profits. The circuit court declined to award damages for the loss of the use of DiMambro’s trucks during the delay. The circuit court’s decision concerning liability and damages was reduced to judgment and entered on June 1, 1984.

United/Mancini subsequently filed a motion supplementary to judgment asking the circuit court to decide which insurance carrier was responsible for paying the judgment awarded to DiMambro.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nucor Corp. v. Employers Insurance
296 P.3d 74 (Court of Appeals of Arizona, 2012)
Edward E. Gillen Co. v. Insurance Co. of Pennsylvania
874 F. Supp. 2d 755 (E.D. Wisconsin, 2012)
Dow Chemical Co. v. Fireman's Fund Insurance
217 F. Supp. 2d 816 (E.D. Michigan, 2002)
Mattiola Construction Corp. v. Commercial Union Insurance
60 Pa. D. & C.4th 412 (Philadelphia County Court of Common Pleas, 2002)
Arco Industries Corp. v. American Motorists Insurance
531 N.W.2d 168 (Michigan Supreme Court, 1995)
Fragner v. American Community Mutual Insurance
502 N.W.2d 350 (Michigan Court of Appeals, 1993)
Whitaker v. Citizens Insurance Co. of America
476 N.W.2d 161 (Michigan Court of Appeals, 1991)
Allstate Insurance v. Freeman
443 N.W.2d 734 (Michigan Supreme Court, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
397 N.W.2d 547, 154 Mich. App. 306, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dimambro-northend-associates-v-united-construction-inc-michctapp-1986.