Humphreys v. Texas Power & Light Company

427 S.W.2d 324, 1968 Tex. App. LEXIS 2274
CourtCourt of Appeals of Texas
DecidedMarch 22, 1968
Docket17071
StatusPublished
Cited by34 cases

This text of 427 S.W.2d 324 (Humphreys v. Texas Power & Light Company) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Humphreys v. Texas Power & Light Company, 427 S.W.2d 324, 1968 Tex. App. LEXIS 2274 (Tex. Ct. App. 1968).

Opinion

CLAUDE WILLIAMS, Justice.

This is an appeal by B. L. Humphreys from a take nothing summary judgment in his action against Texas Power & Light Company for personal injuries. Texas Employers Insurance Association, the workmen’s compensation insurance carrier for C. C. Teague & Son Construction Company, Inc., Humphreys’ employer, intervened and sought reimbursement for total and permanent workmen’s compensation benefits which such company had paid to Humph-reys for the serious injuries sustained by him on November 29, 1963 when he came in contact with an energized electrical line while performing his work as a lineman. In his suit against Texas Power & Light Company Humphreys charged that such company, and its employees, were guilty of various acts of negligence which proximately caused him to sustain his injuries. Defendant company filed its motion for summary judgment, supported by various affidavits, depositions, and testimony adduced on a plea of privilege hearing in Nacogdoches County. This motion was opposed by Humphreys who also filed affidavits, depositions, etc. Following hearing, the trial court sustained the summary judgment motion and decreed that Hum-phreys take nothing by his action.

Proper resolution of the questions presented by appellant’s points of error requires a summarization of the material facts which were before the court at the time the summary judgment motion was sustained. Since we are here confronted with a judgment rendered pursuant to Rule 166-A, Vernon’s Texas Rules of Civil Procedure, the sole question is whether material issues of fact were presented to the trial court. If so, it would necessarily follow that the judgment cannot be sustained. Moreover, in such a situation we are enjoined to examine the evidence presented in a light most favorable to appellant.

B. L. Humphreys had, for a number of years prior to his injury, been an electrical lineman. He had first served an apprenticeship and then successfully passed an examination which qualified him to be what is known as a journeyman lineman. He had had several years’ experience as a journeyman lineman and this work involved the handling of energized as well as non-energized electrical lines. He had been train *327 ed to use various types of protective devices to minimize the hazards of injury caused by contact with high-powered electrical lines while performing his duties. He was thoroughly familiar with the dangers involved with and incident to his work around energized lines. About four or six weeks prior to the time he was injured Humphreys went to work for C. C. Teague & Son Construction Co., Inc. (hereinafter referred to as Teague) as a journeyman electrical lineman and was employed by such company in such capacity at the time of his injury. During his period of employment with Teague he ordinarily worked as a member of crews consisting usually of seven men. His foreman was Mr. Henry J. Watkins, who was also his brother-in-law. His work for Teague was the usual work of a lineman and included performing his duties around energized lines from time to time. He received orders concerning his work- from Mr. Watkins. His work necessitated him to climb high poles and perform work in such position.

Teague, a corporation engages in pole line and electrical distribution construction. On May 1, 1962 Teague, as contractor, entered into a written contract with appellee Texas Power & Light Company (hereinafter called Light Company), in which it was agreed that Teague would construct, repair and maintain portions of the utility system owned and operated by Light Company, such work to be designated in detail from time to time by the company. As to the relationship between the two organizations, the contract provided:

“It is understood and agreed that in doing the said work, Company will not exercise any control over the manner hereof, and Contractor will act and be considered as an independent contractor and will assume all liability for damages to persons or property occurring by reason of said work.”

This contract was in full force and effect on November 29, 1963. Between the date of the execution of the contract and November 29, 1963, the light company had, from time to time, designated various work to be done by Teague and the work was performed by Teague as designated by Light Company’s preparation and execution of a work authorization and drawing of the particular work to be performed.. Copies of these instruments were furnished to Teague’s foreman who in turn would direct the work of his men. Generally the compensation paid by the light company to Teague was computed on a unit basis. The schedule of payment varied depending upon whether the work was to be done on energized lines or de-energized lines, the rate being generally higher when the work was to be performed on energized lines.

The testimony reveals that it was the custom and practice of Teague and Light Company, in carrying out the general contract between them, that when Teague needed to de-energize lines being worked upon its employees would request Light Company for permission to de-energize and such permission was given with the understanding that Teague’s employees were to do the actual de-energizing as well as the re-energizing. The time to re-energize was to be left to the Teague employees’ discretion but with the understanding that the lines were not to be left de-energized any longer than was absolutely necessary for Teague and its employees to complete their work.

During the month of November 1963 Light Company prepared a work authorization, pursuant to the written basic contract, and also prepared plans and specifications which called for the stringing of new conductors and the transfer of existing conductors from an old 40-foot pole to a new 45-foot pole within the City of Nacogdoches. Copies of the authorization and drawings were furnished to Watkins who was in charge of the work for Teague. On November 29, 1963 the Teague employees, including the foreman Watkins and the appellant Humphreys were engaged in the work called for in the authorization. According to the testimony of Watkins, at *328 approximately 7:00 A.M. on that date, Mr. Burns, the distribution superintendent of the light company at Nacogdoches, came to the work site and Watkins sought and obtained authorization from him to de-ener-gize certain lines which were attached to the pole which was being worked on by the Teague employees. Burns gave such consent for Teague and its employees to de-energize the lines, it being understood that Teague personnel would notify Light Company’s local office that such work had been done and would also notify the customers who would be affected by such de-energizing. Watkins testified that Burns further requested that the lines would be de-energized no longer than was necessary to permit Teague and its employees to perform the work. There was no direction or understanding as to when the lines would be re-energized but it was consistent with the working arrangements that Teague personnel would re-energize the lines when their work had gotten to the point where same could be re-energized in safety. Watkins, as foreman, had the right to make the decision as to the re-energizing of the lines.

At approximately 8:00 A.M.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Herrell v. NATIONAL BEEF PACKING CO., LLC
259 P.3d 663 (Supreme Court of Kansas, 2011)
Durbin v. Culberson County
132 S.W.3d 650 (Court of Appeals of Texas, 2004)
Pelletier v. Sordoni/Skanska Construction Co.
815 A.2d 82 (Supreme Court of Connecticut, 2003)
Weidner v. Sanchez
14 S.W.3d 353 (Court of Appeals of Texas, 2000)
Thompson v. Jess
1999 UT 22 (Utah Supreme Court, 1999)
Dillard v. Strecker
877 P.2d 371 (Supreme Court of Kansas, 1994)
Hall Dadeland Towers Associates v. Hardeman
736 F. Supp. 1422 (N.D. Texas, 1990)
Barbera v. Brod-Dugan Co.
770 S.W.2d 318 (Missouri Court of Appeals, 1989)
Ray v. Schneider
548 A.2d 461 (Connecticut Appellate Court, 1988)
Moore v. Noble Drilling Co.
637 F. Supp. 97 (E.D. Texas, 1986)
Rowley v. Mayor of Baltimore
505 A.2d 494 (Court of Appeals of Maryland, 1986)
Kemp v. Frozen Food Express, Inc.
618 F. Supp. 431 (E.D. Texas, 1985)
Vertentes v. Barletta Co.
466 N.E.2d 500 (Massachusetts Supreme Judicial Court, 1984)
Vertentes v. Barletta Co.
452 N.E.2d 271 (Massachusetts Appeals Court, 1983)
Johns v. New York Blower Co.
442 N.E.2d 382 (Indiana Court of Appeals, 1982)
John Franks v. Associated Air Center, Inc.
663 F.2d 583 (Fifth Circuit, 1981)
Tauscher v. Puget Sound Power & Light Co.
635 P.2d 426 (Washington Supreme Court, 1981)
Keith Vagle v. Pickands Mather & Company
611 F.2d 1212 (Eighth Circuit, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
427 S.W.2d 324, 1968 Tex. App. LEXIS 2274, Counsel Stack Legal Research, https://law.counselstack.com/opinion/humphreys-v-texas-power-light-company-texapp-1968.