Pelletier v. Sordoni/Skanska Construction Co.

815 A.2d 82, 262 Conn. 372, 2003 Conn. LEXIS 47
CourtSupreme Court of Connecticut
DecidedFebruary 11, 2003
DocketSC 16743; SC 16747
StatusPublished
Cited by5 cases

This text of 815 A.2d 82 (Pelletier v. Sordoni/Skanska Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pelletier v. Sordoni/Skanska Construction Co., 815 A.2d 82, 262 Conn. 372, 2003 Conn. LEXIS 47 (Colo. 2003).

Opinion

Opinion

BORDEN, J.

In these two consolidated appeals, the plaintiff, Norman Pelletier, and his wife, Reine Pelletier,1 appeal from the summary judgment of the trial court,2 rendered in favor of the defendants, Sordoni/ Skanska Construction Company (Sordoni) and Professional Services Industries, Inc. (Professional Services).3 [374]*374The plaintiff claims that the trial court improperly determined that neither Sordoni nor Professional Services could be held hable to the plaintiff for alleged negligence. We affirm the judgment of the trial court.

The following procedural history is relevant to our resolution of these appeals. In his complaint, the plaintiff alleged negligence as to both Sordoni and Professional Services, and breach of contract as to Sordoni alone. Both defendants moved for summary judgment. Sordoni argued that, pursuant to the rule set forth by the Appellate Court in Ray v. Schneider, 16 Conn. App. 660, 548 A.2d 461, cert. denied, 209 Conn. 822, 551 A.2d 756 (1988), it could not be held hable in neghgence to the employee of its independent subcontractor. Sordoni also argued that the contract that was alleged in count two of the plaintiffs complaint did not exist. Professional Services argued that it did not owe a duty to the plaintiff under its subcontract with Sordoni. The trial court granted both motions for summary judgment and rendered judgment for the defendants accordingly. These appeals fohowed.

The parties presented the following undisputed facts to the trial court on the motions for summary judgment. At the time of the incident giving rise to this action, Sordoni was the general contractor for the “Pitney Bowes Project,” a building under construction for a large shipping company, Pitney Bowes, Inc. (Pitney Bowes). The plaintiff was an employee of Berlin Steel Construction Company (Berlin Steel), the structural steel fabrication and erection subcontractor for the project. Sordoni hired Professional Services to inspect the work performed by Berlin Steel.

Under its subcontract with Sordoni, Berlin Steel had the responsibility to provide all of the structural steel for the Pitney Bowes project, and to ensure its integrity. This included the duty to weld connections in the struc[375]*375tural steel that would allow for the interconnection of steel members as a load-bearing, structural frame for the building. Furthermore, Berlin Steel had the duty to inspect those welds, ensuring their ability to bear weight. Under its contract with Berlin Steel, Sordoni reserved the right to inspect the structural steel, “solely for [its own] benefit.” The contractual documents emphasized that Sordoni’s “[inspection and acceptance, or failure to inspect, shall in no way relieve [Berlin Steel] from [its] responsibility to furnish satisfactory material strictly in accordance with the [c]ontract [documents.”

On June 20,1994, the plaintiff suffered serious physical injuries in an accident at the Pitney Bowes construction site. At the time of the accident, he was working beneath the building’s large steel frame, which his employer, Berlin Steel, had been hired to build. The plaintiff was in the process of installing metal sheet flooring between two steel columns when several of his coworkers interrupted his work to install a two ton crossbeam between the columns. The plaintiff stepped away while his coworkers bolted the crossbeam to seat connections, which are steel flanges that enable the interconnection of large structural members, located on each of the columns. One of the seat connections, on column 313, had been only tack welded to the column. A tack weld is a weak, provisional weld, which is intended only to hold a piece in place pending a full, load-bearing weld. The tack weld on column 313 did not immediately give way under the one ton load of the crossbeam. After his coworkers secured the crossbeam to the seat connections on the columns, the plaintiff returned to work beneath the crossbeam. Within minutes, the seat connection broke and the corresponding end of the crossbeam fell, striking him. The plaintiff suffered severe injuries and is currently recovering workers’ compensation benefits from Berlin Steel for his injuries. [376]*376Further facts and procedural history will be set forth where necessary.

We first set forth the standards of review applicable to both of these appeals. Each appeal arises from a judgment of the trial court granting a motion for summary judgment. “[T]he standard of review of a trial court’s decision to grant a motion for summary judgment is well established. Practice Book [§ 17-49] provides that summary judgment shall be rendered forthwith if the pleadings, affidavits and any other proof submitted show that there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law. In deciding a motion for summary judgment, the trial court must view the evidence in the light most favorable to the nonmoving party.” (Internal quotation marks omitted.) Elliott v. Waterbury, 245 Conn. 385, 391, 715 A.2d 27 (1998). With this standard of review in mind, we turn to the plaintiffs claims on appeal.

I

THE PLAINTIFF’S CLAIMS AGAINST SORDONI

In his appeal against Sordoni, the plaintiff claims that the trial court improperly determined that: (1) the general contractor nonliability rule set forth in Ray v. Schneider, supra, 16 Conn. App. 663-65, barred recovery under count one of his complaint, which sounded in negligence; and (2) neither Sordoni’s contract with Pitney Bowes nor an orientation and procedures manual that Sordoni had distributed to the plaintiff created a duty to the plaintiff.4 We disagree.

[377]*377The plaintiffs complaint against Sordoni was based on allegations of both negligence and breach of contract. The plaintiffs allegations of negligence were based on a range of legal duties, with statutory and public policy sources. More specifically, the plaintiff alleged that Sordoni “knew or in the exercise of reasonable care . . . should have known” that the job site was unsafe, and failed to abate the danger of the defective weld. The plaintiff alleged further that Sordoni had a duty to inspect the structural steel, including “all main stress carrying elements, welding material and bolting material ... all steel welds . . . [and] the steel frame of the column upon which the seat angle connection collapsed,” yet Sordoni failed to do so in violation of the state building code. Regs., Conn. State Agencies § 29-252-la. In the breach of contract count, the plaintiff alleged that Sordoni had entered into a contract with the plaintiff, as evidenced by the orientation and procedures manual that Sordoni had required the plaintiff to sign prior to commencing work for Berlin Steel on the project.

In its motion for summary judgment, Sordoni argued that, as a matter of law, with respect to the negligence count, Sordoni, as a general contractor, could not be [378]*378held hable to the plaintiff, an employee of Sordom’s subcontractor, and that this issue was controlled by Ray v. Schneider, supra, 16 Conn. App. 660. With respect to the breach of contract claim, Sordoni argued that the orientation and procedures manual did not create any contractual obligations to the plaintiff, but served only as an “acknowledgement that . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pelletier v. Sordoni
825 A.2d 72 (Supreme Court of Connecticut, 2003)
Mozeleski v. Thomas
818 A.2d 893 (Connecticut Appellate Court, 2003)
United Services Automobile v. Kaschel, No. Cv 02-0190241 S (Mar. 25, 2003)
2003 Conn. Super. Ct. 3716 (Connecticut Superior Court, 2003)
Zielinsky v. Kotsoris, No. Cv 01 0185802 (Mar. 24, 2003)
2003 Conn. Super. Ct. 3944 (Connecticut Superior Court, 2003)
Lewis v. Clinton Pzc, No. X06-Cv-96-0154803s (Feb. 13, 2003)
2003 Conn. Super. Ct. 2265 (Connecticut Superior Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
815 A.2d 82, 262 Conn. 372, 2003 Conn. LEXIS 47, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pelletier-v-sordoniskanska-construction-co-conn-2003.