Howard v. Pensacola & Atlantic Railroad

24 Fla. 560
CourtSupreme Court of Florida
DecidedJune 15, 1888
StatusPublished
Cited by16 cases

This text of 24 Fla. 560 (Howard v. Pensacola & Atlantic Railroad) is published on Counsel Stack Legal Research, covering Supreme Court of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Howard v. Pensacola & Atlantic Railroad, 24 Fla. 560 (Fla. 1888).

Opinion

Mr. Justice Raney

delivered the opinion of the court:

I. The complainants, having amended their bill in the manner shown by the record, after the ruling of the Chan•eeller holding the plea to be sufficient, and the defendant 'having pleaded to the bill as amended and filed an answer in support thereof, it is not necessary for us to pass upon .such ruling, nor would it serve any beneficial purpose in so far as this litigation . is concerned. The case as made by the bill and plea prior to the amendment was abandoned by making the amendment. By amending the complainants have waived the right to insist upon our reviewing [579]*579the ruling in question, and can only claim that we shall dispose of the case made by the bill as amended and the pleadings filed subsequent to such, amendment, and the testimony. The effect of the amendment is also to remove from the ease, as a practical issue, the question of the propriety of the previous order setting aside the decree pro confesso entered on the original bill. 1st Daniell’s Chan. P. & P., 425, 524; Weightman vs. Powell, 2 DeG. & S., 570; 12 Jurist, 958; Jopling vs. Stewart, 4 Vesey, 619; Trust and F. I. Co. vs. Jenkins, 8 Paige, 593; Circuit Court Chancery Rule 52, 59.

The agreement of counsel for a “ fiual hearing,” and that a “final decree” should be entered, is entirely consistent with the above views.

II. Under the agreement of counsel just referred to, we are to consider and dispose of the ease made by the bill as amended, the subsequent pleadings and the evidence, and pass upon the correctness of the decree appealed from.

By referring to the original contract of July 24th, 1881, in the statement of the case, it will be seen that upon the complete performance óf the work to the entire satisfaction of the engineer in charge, the same to be evidenced by his certificate, the railroad company was to pay the contractors as follows; Upon the execution of portions of the work to the satisfaction of said engineer in charge for the time being, eighty per cent, of his monthly estimates of the relative value of the work performed, including materials furnished at the site of the structure, to the first day of each month, was to be paid on or before the 15th day of the month ; and the balance shown by the engineer’s certificate to be due on the contract was to be paid on the completion of the entire work, and upon the production of the engineer’s certificate showing such balance.

[580]*580Howard, in his testimony, puts in evidence monthly certificates or monthly estimates for work done in December, 1881, February, March, April, May and June, 1882. These, he says, are the estimates of Chief Engineer A. W. Gloster. There are also in the record monthly estimates for the months of August, 1881, and September, 1882, and for each of the intervening months; those for August and September being signed by Colin A. Davies as “Assistant Engineer,” and the others by Gloster as Chief Engineer.These were put in by the defendant. Davies disclaims having made the calculations on which those signed by himself are based.

Howard, in his bill as amended, alleges that in April, 1883, he had fully and completely performed the work undertaken, in accordance with the contract, and to the entire-satisfaction of the defendant’s Chief Engineer, who prepared and furnished him a final statement or estimate of the work, bearing date the 5th of said month, and of which a copy is made a part of the bill.

This final estimate is assailed by Howard. His first charge against it is that the Chief Engineer has, through mistake or fraud, allowed him for total excavation and haul the sum of only $113,164.29, when he should have allowed him $123,277.85, a difference of $10,118.56.

Howard, in his testimony, gives the quantity of earth excavation which he claims was done on each section, and the figures given by him (excluding those relating to his claim for extra work) aggregate 379,961 cubic yards, excluding 995 yards of ditching, and 380,956 yards including the ditching. lie says these figures are given from monthly estimates made by Gloster prior to July, 1882. He produces the estimates as a part of his testimony, they being those for December, 1881, February, March, April, May and June, 1882. As we understand the “monthly esti[581]*581mates,” they show the whole quantity of work doue under the contract on a section up to the end of the month for which the estimate or report is made, and not merely the quantity done during such month. Comparing the figures as given by him in his testimony with those given in the monthly statements annexed by him thereto, we find, in the case of sections 1, 4, 5 and 10, that they are reduced by the estimate for June from the figures given by Howard .and to be found in some former one or more of such estimates, as follows: 9,200 cubic yards on section 1, and 296 yards on section 4, and 1,139 on section 5, and 2,542 yards on section 10, making an aggregate reduction of 13,177 cubic yards.

It is true also, however, that Howard has adopted the figures given as to section 8 in the April and June estimates, although they are 1,854 cubic yards less than those in the estimate for December ; and in the case of section 14 he has adopted the April estimate, which is 755 yards less than that for March, and in the case of section 19 he has adopted that for May, which is 999 yards less than that for December and February, and in the case of sections 23 and 21 he has adopted those of June, which are respectively 1,696 and 127 yards less than the figures given by the May report; these differences making an aggregate of 5,432 yards more than the reports adopted by him in the case of the five sections mentioned in this paragraph, show.

As we understand Howard, his contention is that the railroad company should pay him for the quantities of ■earth excavations stated in his testimony, and as shown by those monthly estimates adduced by him, in which the .same quantities are to be found.

The defence of the railroad company is, in short, that disputes had arisen between it and Howard both as to [582]*582whether the work bad been done in accordance with the contract of July, 1881, and as to the amount due to Howard, survivor, and that the agreement of April 24, 1888, appearing in the statement of the case, was a settlement of those disputes, and that Howard is bound by it and the action taken under it; that it covers the matter of earth excavation, as well as other matters not excepted by its terms, and adopts the estimate of the quantity of earth excavation shown by Davies’ final estimate of April 5th, referred to above.

This agreement of April 24th, 1883, is, upon its face,, unmistakably one for payment to Howard, as the survivor of Howard & Walker, of the balance due as shown upon the “final” given Howard by Engineer Davies April 5th,. 1888; and the sums payable thereunder, including the amounts to be withheld for special purposes mentioned in the agreement, are made expressly a “ full and complete satisfaction for all claims of Howard & Walker, and Howard, survivor, under said contract of July 25th, 1881,” except the account for the iron and timber at the Apalachicola river, which were to be measured and weighed before being paid for. The language of the preamble of this agreement also shows that the parties to it understood the contract of July 25th, 1881, to be that set forth “ in said-contract and specifications thereto annexed.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Olfati v. City of Sacramento
E.D. California, 2024
State Farm Fire and Cas. Co. v. Ray
556 So. 2d 811 (District Court of Appeal of Florida, 1990)
Westinghouse Electric Corp. v. Carol Florida Corp.
122 So. 2d 795 (District Court of Appeal of Florida, 1960)
Broderick v. Overhead Door Co. of Fort Lauderdale, Inc.
117 So. 2d 240 (District Court of Appeal of Florida, 1959)
Iowa Electric Light & Power Co. v. Hopp
866 N.W. 512 (Supreme Court of Iowa, 1936)
Duss v. Duss
160 So. 488 (Supreme Court of Florida, 1935)
Hotel Halcyon Corp. v. Miami Real Estate Co.
103 So. 403 (Supreme Court of Florida, 1925)
Charlotte Harbor & Northern Railway Co. v. Burwell
56 Fla. 217 (Supreme Court of Florida, 1908)
McClinton v. Chapin
54 Fla. 510 (Supreme Court of Florida, 1907)
Chicago Lumber & Coal Co. v. Garmer
109 N.W. 780 (Supreme Court of Iowa, 1906)
Pinney v. Pinney
46 Fla. 559 (Supreme Court of Florida, 1903)
Summerlin v. Thompson & Co.
31 Fla. 369 (Supreme Court of Florida, 1893)
Wilcox v. Stephenson
30 Fla. 377 (Supreme Court of Florida, 1892)
Hanover Fire Insurance v. B. C. Lewis & Sons
28 Fla. 209 (Supreme Court of Florida, 1891)
Deans v. Wilcoxon
25 Fla. 980 (Supreme Court of Florida, 1889)

Cite This Page — Counsel Stack

Bluebook (online)
24 Fla. 560, Counsel Stack Legal Research, https://law.counselstack.com/opinion/howard-v-pensacola-atlantic-railroad-fla-1888.