Joseph Finegan & Co. v. L'engle & Son

8 Fla. 413
CourtSupreme Court of Florida
DecidedJuly 1, 1859
StatusPublished
Cited by7 cases

This text of 8 Fla. 413 (Joseph Finegan & Co. v. L'engle & Son) is published on Counsel Stack Legal Research, covering Supreme Court of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Joseph Finegan & Co. v. L'engle & Son, 8 Fla. 413 (Fla. 1859).

Opinion

BALTZELL, C. J.,

delivered the opinion of the Court.

L’Engle & Son, plaintiffs in the Court below, contracted with the defendants Einegan & Co. to “execute all the gradation on that part of the Florida Railroad included between sections 1,240 and 1,268, comprising ten miles, more or less, and to furnish all the sills and cross-ties required for the same, together with all hewed timber necessary for the construction of drains or trestles on said portion of said road.” After providing for the mode of execution of the work by special articles, not necessary to be particularly noticed here, it was further agreed that “ the work should be justly estimated, received and paid for, by the terms of the contract, after the completion of each consecutive section of five miles, and at the end of thirty days from the commencement of the work, the parties of the second part should cause a proper estimate of the work done to be made, and pay to the parties of the first part seventy-five per cent, of the amount due for said work in cash, reserving twenty-five per cent, of said amount until the completion of the section of five miles, which reserved twenty-five per cent, should be then paid,” &c.

Plaintiffs complain, alleging “performance of the first five miles to the satisfaction of the Engineer and of defendants, and of the failure to pay agreeably to the contract made; of the not making further estimates nor pay for extra work, by reason of which they were unable to go on with their work and were compelled to abandon it.”

Defendants take issue on these allegations and insist, [415]*415that “the plaintiffs did not perform the work on the first section of five miles to the satisfaction of the Engineer of the road and of defendants “ that they abandoned the contract and wholly refused to perform a large part of the work stipulated in said contract;” “that they were not compelled, from non-performance of said agreement by defendants, to abandon their work;” “that defendants had fully performed all things stipulated to be performed by them when plaintiffs abandoned their work;” “that plaintiffs wholly failed and refused to perform said work according to the direction of the Chief Engineer, as by the contract it was stipulated it should be performed.”

These issues were submitted to the jury, with instructions. Upon them the jury found a verdict for the plaintiffs. Upon which defendants moved for a new trial, which the Court refusing to grant, they excepted, so as to present the facts and bring this question before this Court for its consideration.

Whether this motion should have been granted can alone be determined by the testimony — by an ascertainment of the facts bearing upon the contract between the parties. It is satisfactorily shown that estimates were made, at the expiration of thirty days, by the Engineers, for work performed for the months of September, October, November, December, January, February, March, April and May, up to the time of abandonment, and that payments were made in full compliance therewith to the amount of $12,821 62.

Mr. Butler, the Engineer in charge of the road, deposes, “ that a final estimate was demanded of the five miles and refused by the Engineer, for objections stated to plaintiffs, that the work was not right. He supposed that L’Engle Gould see it as well as witness could, who said he would go [416]*416and do it. He does not think plaintiffs ever notified him that it had been done. The road was not trimmed according to the road pegs; the embankment was not up to grade in some places, it was over grade in other places. There were stumps that should have been taken out, and in some places there were ditches to be opened,” &c. The entire statement of witness need not here be repeated, as. this will give an idea of its contents.

This testimony of the Engineer in charge of the work disproves the allegations in the declaration as to the “ performance on the first section of five miles to the satisfaction of the Engineer of the road and defendants ” and the other allegations as to the making of estimates, and should be regarded as conclusive on the point, uncontradicted as it is by other testimony, and, more than all, having the weight due to it by the official position of the witness, especially accredited by the written agreement of the parties.

That we are not mistaken as to the other testimony in the case, we extract such portion of it as is applicable. Mr. Gregg, a Civil Engineer, engaged on an adjoining road, a witness jor the plaintiff, says: “ He went over all the road, except at station 1,304 and a quarter of a mile towards that station and speaks favorably of it.” The work, as far as he saw, was done as well as the work on his road. There was nothing wrong that witness could detect. He said, at the time, he wished the work on his own road was as good. He yet states that he went over the work without any instrument. It was entirely out of his power to form any opinion by the examination he made as to how the grubbing and clearing was done. When an embankment is once built, no man can tell how the grubbing was done and before the embankment was put upon it. The Engineer who superintended the construction of a, [417]*417road-bed is the best evidence of how it was grubbed. "Witness would rely upon his testimony in preference to his own examination after the embankment was made. Witness cannot say whether all the ditches for draining the road-bed on the first five miles were built; he could see no omission. The turn-out and the T track at Baldwin were not complete. The ditches are not such as the road requires at that place. Witness thinks they were staked, but not finished. Baldwin is on the first five miles. He did not measure the clearing, but thinks it was sixty feet wide. Witness cannot tell from his own examination whether all the logs, brush-wood and other perishable matter had been removed beyond the place occupied by the embankment, nor can he tell whether, under an embankment ten feet high or less, all the trees and stumps were grubbed, nor whether they were cut to the surface of the earth under an embankment over ten feet high.” This is not the entire testimony of this witness, but will give a correct idea of its character and bearing.

Alfred A. Sears, another Engineer, examined for plaintiffs, says he was charged with laying the superstructure of the road, and saw no difference between the work done by plaintiffs and the balance of the road; noticed nothing peculiar in the road-bed. It was fit to receive the track as much as any part of the road. There was some trifling amount of grading to be done at the Northern end. There was a gap in the road there. Could not have been over two or three hundred cubic yards of work altogether that was necessary to put on. It made no difference, except the two or three hundred yards of extra work.

This is substantially the testimony of these witnesses, and sustains the Engineer in his testimony as to the nonperformance of the work and the omission to complete it agreeably to the contract of the parties. In argument, it [418]*418was urged that the work left unperformed was of little value, only a slight jog of a few hundred feet — a few stumps, extricable at an expense of a few dollars, to be disregarded as worthy of no consideration. We do not think so. Completion is the word, as near as may be, in works of this kind, without defects and with everything done to perform the contract, so that there may be a substantial Iona fide compliance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Townsend v. First Federal Savings & Loan Ass'n
15 So. 2d 199 (Supreme Court of Florida, 1943)
Duval County v. Charleston Engineering & Contracting Co.
134 So. 509 (Supreme Court of Florida, 1931)
Moss v. Best Knitting Mills
130 S.E. 635 (Supreme Court of North Carolina, 1925)
Charlotte Harbor & Northern Railway Co. v. Burwell
56 Fla. 217 (Supreme Court of Florida, 1908)
Wilcox v. Stephenson
30 Fla. 377 (Supreme Court of Florida, 1892)
St. Paul & Northern Pacific Railway Co. v. Bradbury
44 N.W. 1 (Supreme Court of Minnesota, 1889)
Howard v. Pensacola & Atlantic Railroad
24 Fla. 560 (Supreme Court of Florida, 1888)

Cite This Page — Counsel Stack

Bluebook (online)
8 Fla. 413, Counsel Stack Legal Research, https://law.counselstack.com/opinion/joseph-finegan-co-v-lengle-son-fla-1859.