Howard Jamison, Administrator of the Estate of Albert Tucker, Deceased v. A. M. Byers Company

330 F.2d 657
CourtCourt of Appeals for the Third Circuit
DecidedMay 20, 1964
Docket14262
StatusPublished
Cited by33 cases

This text of 330 F.2d 657 (Howard Jamison, Administrator of the Estate of Albert Tucker, Deceased v. A. M. Byers Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Howard Jamison, Administrator of the Estate of Albert Tucker, Deceased v. A. M. Byers Company, 330 F.2d 657 (3d Cir. 1964).

Opinion

KALODNER, Circuit Judge.

Defendant A. M. Byers Company has appealed from a judgment entered pursuant to a jury’s verdict 1 in a diversity Action brought by the plaintiff, administrator of the estate of Albert Tucker, deceased, for recovery of damages under the Pennsylvania Wrongful Death 2 and Survival Acts, 3 following the District Court’s denial of its motions for judgment N.O.V., or in the alternative, for a mew trial.

Tucker, a 23-year old carpenter’s helper, employed by Allegheny Contracting Industries, Inc. (“Allegheny”), was killed on February 3, 1959 when a trench caved in while he was assisting one May, carpenter in charge, in shoring a part of .it. The trench was being excavated by .Allegheny at the South Side plant of .A. M. Byers Company in Pittsburgh, Pennsylvania, as part of a sewer construction project pursuant to a written -contract awarded to Allegheny. As the -contract, in Section 2.04 described A. M. Byers Company as “Engineer” it may hereinafter be referred to in that man:ner.

Since jurisdiction is based on diversity, Pennsylvania law governs.

The facts as to the accident itself are detailed in the District Court’s opinion reported at 222 F.Supp. 475 (W.D.Pa. 1962). They may be summarized as follows:

The trench was to be 20 feet deep and 5 feet wide. (The record does not disclose its length). At the time of the accident about 25 feet of the trench had been shored; 8 to 10 feet remained unshored. Tucker assisted May in constructing “forms” for the shoring; each form was about 10 feet long and 5 feet wide; the “forms” were lowered into the trench one on top of the other to form a supporting frame work for the shoring planks or sheeting which were then secured along the sides of the excavation. The cave-in was due to the fact that the shoring planks were too short and the bracing was too small, 4 and as a consequence the shoring twisted or shifted throwing the “braces out of square and they collapsed.” 5 Tucker “had but little experience in the type of work in which he was engaged”, and “His classification was that of a semi-skilled laborer.” 6 The issue of his contributory negligence was left to the jury with the instruction that the plaintiff could not recover if the jury found Tucker to have been guilty of contributory negligence.

It must immediately be noted that on this appeal it is undisputed that the shoring operation was negligently performed, as the jury found it to be.

It should be added that the case was tried under the theory advanced by plaintiff’s counsel that the applicable law was *659 that found in Section 414 of the Restatement of Torts, which provides in sum that one who entrusts work to an independent contractor but retains control of any part of the work is subject to liability for the contractor’s negligent performance which causes bodily harm to others.

The District Court charged the jury in accordance with this theory. It also instructed the jury that it might find the retention of control under the terms of the contract.

On this appeal the defendant urges (1) that under Pennsylvania law right of control is insufficient to establish liability in the absence of the actual exercise of control and that here there was no exercise of control; (2) that the contract did not establish right of control but the contrary; (3) that the District Court erred in not construing the contract and leaving it to the jury to do so; (4) that the issue of contributory negligence was improperly submitted to the jury, and (5) that the District Court erred in permitting the contract to go to the jury without deletion of its provisions with respect to liability insurance.

First, as to the contention that right of control is insufficient to establish liability, and that exercise of control is essential to establish liability on the part of the employer of an independent contractor :

In Spinozzi, Pennsylvania Threshermen & Farmers’ Mut. Cas. Ins. Co., Intervenor v. E. J. Lavino and Company, 243 F.2d 80 at page 82-83 (1957) we said:

“The Pennsylvania courts have recognized that the employer should be liable where he has retained control of some part of the work, or so interfered with the performance of the job as to have assumed control, and his failure to exercise that control with reasonable care causes harm to others.” (emphasis added)

In essence the defendant contends that the italicized language is not a correct statement of Pennsylvania law, although he does not attack the holding in Spinozzi on its facts. He asserts that in Spinozzi and the cases cited therein, McGrath v. Pennsylvania Sugar Co., 282 Pa. 265, 127 A. 780 (1925), Stork v. Philadelphia, 199 Pa. 462, 49 A. 236 (1901), Pender v. Raggs, 178 Pa. 337, 35 A. 1135 (1896) liability was premised solely on the fact that the employer (of the independent contractor) had actually interfered with and controlled the work being performed.

In Spinozzi there was evidence of both actual control over the contractor’s activity and of retention of control. The holding of the court is consistent with the conclusion that the jury was justified in basing liability on either ground or both. This is in line with the Restatement which was relied on by the District Court.

The Pennsylvania cases which antedate the Restatement (1934) provide no greater solace for the defendant’s view than did Spinozzi. In Stork v. Philadelphia, supra, the City of Philadelphia had engaged an independent contractor to construct a subway line below Pennsylvania Avenue. Apparently the City had retained the right to determine when shoring would be necessary to protect dwelling houses along the proposed route. It refused to authorize shoring of plaintiff’s house when the excavation was first undertaken and as a result serious damage followed. The jury decided in plaintiff’s favor and on appeal the defendant questioned the propriety of sending such a case to the jury. The Supreme Court affirmed the judgment predicating negligence on two factual grounds: (1) that the city had retained the right to determine when shoring should be done, and! (2) that the city refused or neglected to authorize shoring at the plaintiff’s residence. Stork manifests direct Pennsylvania support for the Spinozzi-Restatement view.

Furthermore, neither McGrath v. Pennsylvania Sugar Co., supra, nor Pender v. Raggs, supra, is to the contrary. In both the element of retained control was lacking, thereby leaving “as *660 sumption of control” and direction of the contractor’s labor as the sole questions for the jury’s determination. Defendant has not cited Pennsylvania cases to refute the Restatement view.

Assuming that the defendant retained control over Allegheny’s shoring operation then the instant case is well within our holding in Quinones v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

(PC) Stone v. Pfieffer
E.D. California, 2025
(PC) Petillo v. Jasso
E.D. California, 2023
(PC) Branch v. Grannis
E.D. California, 2023
(PC) Thompson v. Gomez
E.D. California, 2022
(PC) Sim v. Duran
E.D. California, 2019
Hauptman v. WMC, INC.
224 P.3d 1175 (Court of Appeals of Kansas, 2010)
Carrel v. National Cord & Braid Corp.
852 N.E.2d 100 (Massachusetts Supreme Judicial Court, 2006)
McDaniel v. Pickens
695 N.E.2d 215 (Massachusetts Appeals Court, 1998)
Madler v. McKenzie County
467 N.W.2d 709 (North Dakota Supreme Court, 1991)
Jong Hee Park v. United States Lines, Inc.
439 A.2d 10 (Court of Special Appeals of Maryland, 1982)
Toole v. United States
443 F. Supp. 1204 (E.D. Pennsylvania, 1977)
BBCI, Inc. v. Canada Dry Delaware Valley Bottling Co.
393 F. Supp. 299 (E.D. Pennsylvania, 1975)
Smith v. United States
497 F.2d 500 (Fifth Circuit, 1974)
Millard v. Municipal Sewer Authority
314 F. Supp. 1315 (E.D. Pennsylvania, 1970)
Haskins v. Point Towing Co.
421 F.2d 532 (Third Circuit, 1970)
In re the Complaint of Consolidation Coal Co.
296 F. Supp. 837 (W.D. Pennsylvania, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
330 F.2d 657, Counsel Stack Legal Research, https://law.counselstack.com/opinion/howard-jamison-administrator-of-the-estate-of-albert-tucker-deceased-v-ca3-1964.