Housing Vermont v. Goldsmith & Morris

685 A.2d 1086, 165 Vt. 428, 1996 Vt. LEXIS 123
CourtSupreme Court of Vermont
DecidedAugust 23, 1996
Docket95-292
StatusPublished
Cited by18 cases

This text of 685 A.2d 1086 (Housing Vermont v. Goldsmith & Morris) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Housing Vermont v. Goldsmith & Morris, 685 A.2d 1086, 165 Vt. 428, 1996 Vt. LEXIS 123 (Vt. 1996).

Opinion

Morse, J.

Defendant Goldsmith and Morris Architects (Goldsmith) appeals from a judgment in favor of plaintiff Housing Vermont in an *429 architectural malpractice action. Goldsmith claims that the court erred in construing the contract between the parties and in imposing discovery sanctions. We affirm for the most part, but reverse the award of discovery sanctions.

Housing Vermont, a nonprofit corporation that develops affordable housing, is the assignee of claims originally brought by the Riverside Housing Partnership. Riverside owns the Salmon Run housing project, the development at issue. The Salmon Run Project was initiated by the Davis Company in the summer of 1987. Davis Company secured the resources the project required, including architectural and engineering services, building permits, financing, and an option on the site. It sold the project to Riverside in November of 1988. As a component of the sale, the Davis Company assigned its rights under all contracts related to the project to Riverside, including rights to the architectural design services of defendant Goldsmith and Morris Architects, and to the services of Krebs and Lansing, a civil engineering firm.

Located in a ravine, the Salmon Run site was very steep and technically difficult to develop. At the crux of this case is the question of responsibility for producing the final grading plan for the space immediately surrounding the buildings, an area known as the courtyard. Goldsmith contends that Krebs and Lansing was responsible for the final grading plan while Housing Vermont claims that the plan was Goldsmith’s responsibility.

Goldsmith produced a site plan, “SP-1”, which contained grading information and was, in fact, used to construct the grades in the courtyard. The steep slopes depicted in SP-1 proved to be unstable and had to be redesigned and stabilized at substantial additional cost. At trial, the court found that Goldsmith was responsible for producing the final grading plan, and concluded that SP-1 did not meet the standard of care required of architects in producing final grading plans. The court awarded Housing Vermont judgment in the amount of $100,469.92 plus prejudgment interest and costs. Upon Housing Vermont’s motion, the court also imposed discovery sanctions in the amount of $14,446 for Goldsmith’s failure to admit certain matters of proof.

I.

Goldsmith’s primary claim is that the trial court erred in finding that it was responsible for producing the final grading plan for the courtyard area. The agreement between Goldsmith and Riverside *430 was initially formalized in a letter and an American Institute of Architects (ALA) document called a “Standard Form of Agreement Between Owner and Architect.” These documents obligated Goldsmith to produce a site plan for construction. Subsequently the agreement was modified to provide Goldsmith with extra compensation for “grading plans to date.” Goldsmith claims that nothing on the face of these documents obligated it to create a final grading plan and that the court must have erroneously relied on parol evidence to support its finding that Goldsmith was responsible for the plan. Goldsmith contends as well that construction of contract terms is a question of law, and claims that we must analyze the contract without giving any deference to the trial court’s interpretation.

We note first that the parol evidence argument was not made before the trial court. Indeed, the record reveals that Goldsmith’s own examination of witnesses elicited some of the evidence in question, and that Goldsmith did not object to its admission at trial. Thus this claim is waived. See Morais v. Yee, 162 Vt. 366, 372, 648 A.2d 405, 410 (1994) (argument not made before trial court will not be considered on appeal).

Furthermore, although Goldsmith is correct that, generally speaking, construction of contract terms is a matter of law, Ianelli v. Standish, 156 Vt. 386, 389, 592 A.2d 901, 903 (1991), where the meaning of a contract is uncertain, the intent of the parties becomes a question of fact. United Ry. Supply & Serv. Ltd. v. Boston & Maine Corp., 148 Vt. 454, 457, 535 A.2d 325, 327 (1987); Gardner v. West-Col, Inc., 136 Vt. 381, 385, 392 A.2d 383, 386 (1978). Thus, the trial court’s finding that Goldsmith was responsible for the grading plan is entitled to substantial deference. See Mullin v. Phelps, 162 Vt. 250, 260, 647 A.2d 714, 720 (1994) (trial court’s findings of fact reviewed only for clear error).

A review of the record reveals that the court’s finding is supported by both testimonial and documentary evidence. The court found, based on expert testimony, that an architectural document is not stamped with the seal of the architect unless it is true, complete and ready to use for construction. SP-1 was stamped with Goldsmith’s seal. When SP-1 was delivered in final form, defendant also signed a “Design Architect’s Certification and Acknowledgement,” which stated that upon the knowledge, belief and professional judgment of Goldsmith, soil- and ground conditions would not impair the structural soundness of the project. In addition, Larry Williams, who worked for Housing Vermont’s predecessor in title, testified that Goldsmith was *431 responsible for designing the grading plan for the courtyard and had assured him that the grades depicted on SP-1 would work. Other testimony indicated that Goldsmith knew that SP-1 was being used for construction purposes and did nothing to intervene or to suggest that the plan was preliminary and not suitable as a basis for construction. Bearing in mind that the credibility of witnesses and the persuasive effect of evidence are for the trial court to determine, this evidence is more than adequate to sustain the court’s finding. Roy v. Poquette, 147 Vt. 332, 333, 515 A.2d 1072, 1073 (1986); see also Mullin, 162 Vt. at 260, 647 A.2d at 720 (finding will not be disturbed unless appellant can show there is no credible evidence to support it).

Thus, even if it had not been waived, defendant’s parol evidence argument would fail. The parol evidence rule bars the admission of evidence of a prior or contemporaneous oral agreement that varies or contradicts the terms of a written agreement. New England Educ. Training Servs., Inc. v. Silver St. Partnership, 156 Vt. 604, 609, 595 A.2d 1341, 1344 (1991). None of the evidence the court considered contradicted the terms of the ALA document or the subsequent written modification. Instead the evidence contradicted the construction of the contract that defendant advanced, a construction that the trial court rejected.

Likewise, defendant’s promissory estoppel argument must fail.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Berol Dewdney and Cordelia Dewdney v. Ralph E. Duncan, IV
2025 VT 26 (Supreme Court of Vermont, 2025)
Reconciled It v. Bouchett
Vermont Superior Court, 2024
Maine Mutual Fire Insurance v. Tinker
2005 VT 35 (Supreme Court of Vermont, 2005)
LoPresti v. Rutland Regional Health Services, Inc.
2004 VT 105 (Supreme Court of Vermont, 2004)
Bergeron v. Boyle
2003 VT 89 (Supreme Court of Vermont, 2003)
Von Turkovich v. APC CAPITAL PARTNERS, LLC
259 F. Supp. 2d 314 (D. Vermont, 2003)
Hoeker v. Department of Social & Rehabilitation Services
765 A.2d 495 (Supreme Court of Vermont, 2000)
Luneau v. Peerless Insurance
750 A.2d 1031 (Supreme Court of Vermont, 2000)
In re Appeal of Herrick
742 A.2d 752 (Supreme Court of Vermont, 1999)
Investment Properties, Inc. v. Lyttle
739 A.2d 1222 (Supreme Court of Vermont, 1999)
Southface Condominium Owners Ass'n v. Southface Condominium Ass'n
733 A.2d 55 (Supreme Court of Vermont, 1999)
Ben & Jerry's Homemade, Inc. v. La Soul, Inc.
983 F. Supp. 504 (D. Vermont, 1997)
BayBank v. Vermont National
First Circuit, 1997
Baybank v. Vermont National Bank
118 F.3d 30 (First Circuit, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
685 A.2d 1086, 165 Vt. 428, 1996 Vt. LEXIS 123, Counsel Stack Legal Research, https://law.counselstack.com/opinion/housing-vermont-v-goldsmith-morris-vt-1996.