Horton v. Verhelle

588 N.W.2d 144, 231 Mich. App. 667
CourtMichigan Court of Appeals
DecidedDecember 18, 1998
DocketDocket 198929
StatusPublished
Cited by11 cases

This text of 588 N.W.2d 144 (Horton v. Verhelle) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Horton v. Verhelle, 588 N.W.2d 144, 231 Mich. App. 667 (Mich. Ct. App. 1998).

Opinions

Saad, J.

In this construction lien case, defendant Michigan Homeowner Construction Lien Recovery Fund appeals as of right and defendants RBK Corporation, Clark Foundation Company, Darling Builders Supply Co., Roger D. Hunnicutt, Hunnicutt Plumbing & Heating, and Stahl & Sons, Inc., (RBK et al.) cross appeal from a judgment disposing of the various parties’ claims pursuant to motions for summary disposi[671]*671tion. The principal issue in this case is whether defendant lien fund is obligated to make payments to subcontractors and suppliers1 who were not paid by their general contractor and who are unable to foreclose on their construction liens. On summary disposition, the trial court ruled that plaintiff Randy Horton, a subcontractor, and RBK et al. were entitled to payments. We affirm in part, reverse in part, and remand for further proceedings.

i

FACTS AND PROCEEDINGS

Defendants Richard and Lois Verhelle hired defendant Daniel Hughes, a general contractor, in July 1993 to build a house. Hughes contracted with plaintiff and the other defendants (all subcontractors) to work on the project, which was completed by the end of the year. The Verhelles paid Hughes all but $31,663.30 of the contract price, which they planned to pay at the closing. The Verhelles made their payments pursuant to documents Hughes submitted to them, which purportedly were sworn statements and waivers of lien. The authenticity, accuracy, and legal effect of these documents and payments are now in dispute. Hughes did not appear for the closing and failed to pay plaintiff and the other defendants in full. Various parties, including plaintiff and RBK et al. moved for summary disposition. The court allowed the Verhelles to pay the balance due to the court and it discharged all liens against their property pursuant to MCL 570.1203(1); MSA 26.316(203)(1). It ordered the lien [672]*672fund to pay plaintiff and RBK et al. pursuant to MCL 570.1203(3); MSA 26.316(203)(3) and allowed the other defendants (who were not lien fund members) to recover a pro-rata share of the contract balance paid to the court.

n

THE SUBCONTRACTORS’ RIGHTS TO RECOVER FROM THE LIEN

FUND

The lien fund contends that the trial court erred in granting summary disposition to plaintiff and RBK et al. The trial court’s ruling on a motion for summary disposition is reviewed de novo. Pinckney Community Schools v Continental Casualty Co, 213 Mich App 521, 525; 540 NW2d 748 (1995). A motion brought under MCR 2.116(C)(10) tests the factual support for a claim. In ruling on such a motion, the trial court must consider not only the pleadings, but also depositions, affidavits, admissions, and other documentary evidence, MCR 2.116(G)(5), and must give the benefit of any reasonable doubt to the non-moving party, being liberal in finding a genuine issue of material fact. Summary disposition is appropriate only if the court is satisfied that it is impossible for the nonmoving party’s claim to be supported at trial because of a deficiency that cannot be overcome. Morganroth v Whitall, 161 Mich App 785, 788; 411 NW2d 859 (1987).

A

EFFECT OF SUBCONTRACTORS’ FAILURE TO FILE TIMELY NOTICES OF FURNISHING

The parties appear to agree that the liens of plaintiff and RBK et al. cannot attach to the Verhelles’ property. A lien cannot attach to a residential struc[673]*673ture to the extent payments have been made if the owner files an affidavit with the court indicating that the owner has paid the contractor, has not colluded with any person to obtain a payment from the lien fund, and has cooperated, and will cooperate, with the Department of Licensing and Regulation in defense of the lien fund. MCL 570.1203(1); MSA 26.316(203)(1). It is not contested that the Verhelles have complied with this provision. Because this provision precludes plaintiff and RBK et al. from recovering on their liens, they could recover from the lien fund if they proved, inter alia, that they would be entitled to a lien but for subsection 203(1), that the owner paid the contractor or subcontractor who retained or used the proceeds without paying them, that they were members of the fund, that they complied with any applicable licensing acts, and that the contractor or subcontractor with whom they contracted was licensed if required by law to be licensed. MCL 570.1203(3); MSA 26.316(203)(3).

If the subcontractors seeking payment from the lien fund are able to satisfy these statutory prerequisites, the Attorney General, who defends the fund, may assert any defense to a lien claim that would have been available to the owner. MCL 570.1203(5); MSA 26.316(203)(5). One available defense is the subcontractor’s failure to provide a timely notice of furnishing. One of the requirements for establishing a valid lien is that a subcontractor provide a notice of furnishing to the owner or his designee and to the general contractor named in the notice of commencement within twenty days after furnishing the first labor or material on the job. MCL 570.1109(1); MSA 26.316(109)(1). Plaintiff and RBK et al. did not timely [674]*674serve their notices of furnishing. However, their failure to provide timely notices of furnishing defeats their rights to liens for work performed before the service of the notices of furnishing only to the extent that the owner made payments to the contractor pursuant to a contractor’s sworn statement or a waiver of lien. MCL 570.1109(6); MSA 26.316(109)(6).2 At issue is whether the Verhelles made payments pursuant to sworn statements or waivers of lien when they paid Hughes. The lien fund maintains that the owners did so, but RBK et al. contend that the purported sworn statements and waivers were legally defective and therefore cannot defeat their claims. As a matter of law, we agree with RBK et al. that payments made pursuant to defective documents would not defeat their claim. In the case of the sworn statements, we affirm summary disposition because there is no question of fact that the documents are defective. In the case of the waivers of lien, we reverse summary disposition with respect to Darling Builders Supply and Hunnicutt Plumbing & Heating because there is no question of fact that valid waivers of lien were provided. However, in the case of RBK and Clark Foundation, we remand for further proceedings to resolve the question of fact concerning the waivers’ validity.

VALIDITY OF SWORN STATEMENTS

A sworn statement is a notarized form that lists the subcontractors, suppliers, and laborers with whom the contractor contracted, the work they provided, [675]*675the price of their contracts, the amounts paid on the contracts, and the balance due on the contracts. MCL 570.1110(4); MSA 26.316(110)(4). The contractor must provide a sworn statement to the owner when payment is due the contractor from the owner, when the contractor requests payment from the owner, or when the owner demands a sworn statement. MCL 570.1110(1); MSA 26.316(110)(1). The subcontractor must provide a sworn statement to the contractor when payment is due the subcontractor or when the subcontractor requests payment from the contractor and must provide a sworn statement to the owner if the owner demands one. MCL 570.1110(2), (3); MSA 26.316(110)(2), (3). The statements must be in substantially the same form as outlined in the statute.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Muzafer Isovska v. Leana Fitzpatrick
Michigan Court of Appeals, 2025
Marcus Hargrave v. Oak Park Partners LLC
Michigan Court of Appeals, 2025
C Zane Lee Batton v. Auto Owners Insurance
Michigan Court of Appeals, 2023
Big L Corp. v. Courtland Const. Co.
757 N.W.2d 852 (Michigan Supreme Court, 2008)
Big L Corp. v. Courtland Construction Co.
750 N.W.2d 628 (Michigan Court of Appeals, 2008)
Ganrude v. Weber
2000 SD 96 (South Dakota Supreme Court, 2000)
MPC Cashway Lumber Co. v. Hull
606 N.W.2d 392 (Michigan Court of Appeals, 2000)
Smith v. Globe Life Insurance
597 N.W.2d 28 (Michigan Supreme Court, 1999)
Horton v. Verhelle
588 N.W.2d 144 (Michigan Court of Appeals, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
588 N.W.2d 144, 231 Mich. App. 667, Counsel Stack Legal Research, https://law.counselstack.com/opinion/horton-v-verhelle-michctapp-1998.