Renshaw v. Samuels

324 N.W.2d 117, 117 Mich. App. 649
CourtMichigan Court of Appeals
DecidedJuly 12, 1982
DocketDocket 55095
StatusPublished
Cited by10 cases

This text of 324 N.W.2d 117 (Renshaw v. Samuels) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Renshaw v. Samuels, 324 N.W.2d 117, 117 Mich. App. 649 (Mich. Ct. App. 1982).

Opinion

M. J. Kelly, J.

Plaintiff, Leroy Renshaw, commenced this action against defendants Regional Construction Company (Regional) and Walter P. Samuels to recover $27,188 owed to plaintiff for work done on Samuels’ construction project. Pursuant to the mechanics’ lien act, MCL 570.1 et seq.; MSA 26.281 et seq., the builders’ trust fund act, MCL 570.151; MSA 26.331, and the court rule governing garnishment, GCR 1963, 738.13, the trial court rendered judgment in plaintiff’s favor against defendant Samuels and also awarded $2,-900 in attorney fees. Defendant Samuels appeals as of right, GCR 1963, 806.1.

In 1977, Samuels, a general partner of a limited partnership which owns the Carman Flint Shop *652 ping Center, hired Regional to perform various construction projects in the shopping center. These projects were funded through a loan by City National Bank of Detroit. Samuels arranged for the lender to make payments to Regional every 30 days. However, the payments were not to be made unless both the lender and Samuels inspected the work and Samuels personally approved the disbursement. As a further condition of payment, Regional was required to submit a sworn statement listing all subcontractors that had provided labor or materials for the projects. The statements certified that the subcontractors listed were all the people who had worked on the projects. The payments were to apply to both material and labor employed on the jobs.

Among the subcontractors employed by Regional was plaintiff Renshaw and his company. According to Renshaw, he met Samuels’ architect but did not meet either Samuels or defendant’s supervisor, Joe DeLeo. While working on the various projects, Renshaw kept men on the job, visited the shopping center once a day in a truck with his firm’s name written on it, and obtained building permits for the project in his own name. Renshaw worked on eight different jobs within the shopping center, billing Regional for over $149,000 in labor and material. When he only received $122,000 in payment, Renshaw commenced this action against defendants to recover the remaining $27,188. Approximately one month prior to trial, plaintiff filed a mechanics’ lien for labor done on the shopping center.

On November 20, 1978, a partial summary judgment for $25,717.15 was entered against Regional. Pursuant to that judgment, a writ of garnishment was issued against Samuels. Samuels answered *653 that any debt owed by Samuels to Regional was offset by claims he had against Regional. According to Samuels, he refused to pay $19,808.90 to Regional because of claimed or suspected setoffs arising out of the shopping center projects.

During the trial, plaintiff testified that the entire $27,188 was for labor because he used the money paid by Regional to pay his own subcontractors and materialmen. Plaintiff further testified that he had performed several small jobs for Samuels and had been paid for those jobs by Samuels. Plaintiff also introduced a list of setoffs claimed by Samuels against Regional. According to plaintiff, this list was an admission against defendant’s interest. The court admitted the list of setoffs. Finally, plaintiff testified that he never saw the sworn statements concerning payment of subcontractors submitted by Regional to Samuels.

The trial court found that the sworn statements submitted by Regional were defective because they did not contain the names of a number of subcontractors including plaintiff. The court reasoned that the sworn statements were defective and never qualified as "sworn statements” under MCL 570.4; MSA 26.284; therefore, plaintiff was free to file a mechanics’ lien until the day of trial. The court awarded plaintiff $12,799.31 in unpaid labor and $1,279.92 as an unpaid 10% contract fee. The plaintiff was also given $2,900 in attorney fees under the mechanics’ lien statute. The court also concluded that plaintiff was entitled to the balance of the $27,188 under a theory of garnishment of Regional’s claims against Samuels and as part of the trust fund created in monies still held by Samuels under the builders’ trust fund act. The court refused to allow Samuels to claim a setoff against these funds because he failed to introduce *654 evidence supporting the claimed setoff. Defendant appeals the trial court’s rulings.

I

On appeal, defendant argues that the trial court erred when it subjected the property to a mechanics’ lien for labor done by plaintiff. Relying on MCL 570.4; MSA 26.284, defendant argues that the sworn statements submitted by Regional, which did not list plaintiff as a subcontractor, prevent plaintiff from filing the mechanics’ lien after payments in reliance on those statements were made. Plaintiff counters by arguing that defendant should have verified the statements to insure their accuracy. Plaintiff contends that because his name was not contained in the list of subcontractors, the sworn statements do not bar his mechanics’ lien.

The mechanics’ lien statute, MCL 570.1 et seq.; MSA 26.281 et seq., establishes an elaborate procedure to. ensure that subcontractors are paid for material and labor. The statute provides that subcontractors have a lien upon any building they have provided labor or material for if within 90 days of providing material or labor they serve upon the owner a written notice of the material or labor. MCL 570.1; MSA 26.281. The statute further provides that a notice for labor may be served after the 90-day period so long as it is served prior to the owner receiving a sworn statement, MCL 570.4; MSA 26.284, from the contractor. MCL 570.1; MSA 26.281. The statute also provides:

"The owner, part owner, or lessee may at any time retain from any moneys due or to become due to the original contractor, an amount sufficient to pay all *655 demands owing or unpaid to any subcontractor, material-man or laborer, who has recorded and served the notice in manner and form as provided in section 1 of this act. The original contractor shall, whenever any payment of money shall become due from the owner, part owner, or lessee, or whenever he desires to draw any money from the owner, part owner or lessee on such contract, make out and give to the owner, part owner, or lessee, or his agent, a statement under oath of the number and names of every subcontractor or laborer in his employ, and of every person furnishing materials, giving the amount, if anything, which is due or to become due to them, or any of them, for work done or materials furnished, and the owner, part owner, or lessee, or his agent, may retain out of any money then due or to become due to the contractor, an amount sufficient to pay all demands that are due or to become due to such subcontractors, laborers, and material men, as shown by the contractor’s statement, and pay the same to them according to their respective rights, and all payments so made shall, as between such owner, part owner, or lessee, and such contractor, be considered the same as if paid to such original contractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kriegish v. Lipan (In Re Kriegish)
275 B.R. 838 (E.D. Michigan, 2002)
Horton v. Verhelle
588 N.W.2d 144 (Michigan Court of Appeals, 1998)
Norcross Co. v. Turner-Fisher Associates
418 N.W.2d 418 (Michigan Court of Appeals, 1987)
Blow v. Blow
350 N.W.2d 890 (Michigan Court of Appeals, 1984)
Bishop Distributing Co. v. Safeco Title Insurance
344 N.W.2d 593 (Michigan Court of Appeals, 1983)
J & I Service Station, Inc v. Wash Wagon of Michigan, Inc
327 N.W.2d 518 (Michigan Court of Appeals, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
324 N.W.2d 117, 117 Mich. App. 649, Counsel Stack Legal Research, https://law.counselstack.com/opinion/renshaw-v-samuels-michctapp-1982.