Honeywell International, Inc.

CourtArmed Services Board of Contract Appeals
DecidedSeptember 24, 2015
DocketASBCA No. 57779
StatusPublished

This text of Honeywell International, Inc. (Honeywell International, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Honeywell International, Inc., (asbca 2015).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of-- ) ) Honeywell International, Inc. ) ASBCA No. 57779 ) Under Contract No. W911Sl-08-F-013 l )

APPEARANCES FOR THE APPELLANT: Teriy L. Albertson, Esq. Robert J. Sneckenberg, Esq. Crowell & Moring, LLP Washington, DC

APPEARANCES FOR THE GOVERNMENT: Lt Col James H. Kennedy III, USAF Air Force Chief Trial Attorney Marvin Kent Gibbs, Esq. Jeffrey P. Hildebrant, Esq. Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE MELNICK ON CROSS-MOTIONS FOR SUMMARY JUDGMENT

This is a successor to a decision issued on 7 August 2013 granting partial summary judgment for the government. Previously, the Board invalidated provisions of a delivery order (DO) issued to Honeywell, Inc. (Honeywell) under an Energy Savings Performance Contract (ESPC). The invalidated terms had counted the value of Solar Renewable Energy Certificates (SRECs) as government utility cost savings, and calculated the portion of Honeywell's payment schedule for solar arrays based upon those savings. The Board also invalidated a provision of the DO that had authorized Honeywell to sell SRECs for the government. See Honeywell International Inc., ASBCA No. 57779, 13 BCA if 35,380.

After discussing settlement, the parties now return with further cross-motions for summary judgment. Honeywell seeks quantum valebant damages for the reasonable value of the goods and services it provided pursuant to the invalidated provisions of the DO. The government seeks summary judgment on the ground that the conditions permitting such an award do not exist here. Honeywell's motion is granted and the government's motion is denied. STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

The following background and facts are not in dispute:

1. Section 8287 of Title 42 of the United States Code (the ESPC statute) authorizes federal agencies to enter into ESPCs. Under these agreements, contractors incur the cost of providing energy conservation measures (ECMs) to government agencies, providing energy savings in exchange for a share of the value of those savings. An ESPC guarantees savings to an agency and establishes a payment schedule based upon it. 42 U.S.C. § 8287(a)(2)(B).

2. On 25 February 1999, the Department of Energy (DOE) awarded Honeywell Contract No. DE-AM01-99EE73683 (later renumbered DE-AM36-99EE73683), an indefinite-delivery/indefinite-quantity ESPC through which agencies could issue DOs for ECM services in six Mid-Atlantic states (ex. B-1, tabs 10, 11; tr. 1/68-69 1) (the Super ESPC). 13 BCA ,-r 35,380 at 173,606-07. This appeal arises from DO No. W911Sl-08-F-0131, which sought services under the Super ESPC for Fort Dix, New Jersey (comp!. ,-r 17, answer ,-r 17a; R4, tab 1). Id. at 173,607. Among the items required by the DO were two solar arrays. The first was roof mounted and originally designated by the DO as ECM 11.1. (R4, tab 1 at 21, tab 4 at 34; compl. ,-r 17, answer ,-r 17c; app. mot. at 3; gov't mot. at 1) Id. The original DO's requirements are designated Phase I. The other array was added through Modification No. P00004 and was ground mounted. (R4, tab 16 at 3; compl. ,-r 18, answer ,-r,-r 18a-l 8b; app. mot. at 6; gov't mot. at 2) Id. It is designated Phase II. The contracting officers who awarded the DO and its modifications possessed unlimited contracting warrants (R4, tab 1 at 1, tab 4 at 1, 3; gov't 1st mot., Edler decl., Edgar decl. 2 ; app. mot. at 6-7). Id.

3. New Jersey mandates that its utilities produce a percentage of their electricity from renewable sources. It permits them to accomplish that requirement by, among other things, acquiring SRECs. SRECs are certificates issued by the state representing the environmental benefits or attributes of one megawatt-hour of solar energy produced by a facility connected to the State's electrical distribution system. SRECs are transferable and there is a market for them. See Honeywell, 13 BCA ,-r 35,380 at 173,607.

4. Honeywell and the government agreed in the DO that the government's annual energy savings resulting from the solar arrays would be the value of the electricity produced by them, plus the value of the SRECs they generated. The DO assumed specific values for the SRECs over time. (R4, tab 4 at 4, 82-83, 109, tab 33; gov't pt mot. at 1-2;

1 The cited transcript is of the oral argument held 13 February 2013 for the parties' first set of dispositive motions. 2 "Gov't pt mot." refers to the government's initial motion to dismiss received 2 August 2012.

2 app. pt resp. at 6 3) 13 BCA ~ 35,380 at 173,607. Based upon the DO's assumptions, Honeywell guaranteed certain annual savings from the ECMs, and the DO scheduled annual payments to Honeywell based upon those savings (R4, tab 4 at 6, 83, 109). Id. The government was to finance part of its payments for the solar arrays from the proceeds of SREC sales. Id. at 173 ,609. The DO also authorized Honeywell to sell the SRECs for the government and retain 10% of their value (R4, tab 4 at 4). Id. at 173,607.

5. All Phase I work, including the solar array, was completed by Honeywell and accepted by the government sometime between 8 June and 25 September 2009, and payments have been made toward it (compl. ~,-[ 30-32, answer~~ 30-32; app. mot. at 6; gov't mot. at 2). 13 BCA ~ 35,380 at 173,608. On 1 October 2009, the Army transferred administrative authority for the DO to the Department of the Air Force after Fort Dix became a joint base with McGuire Air Force Base (R4, tab 18; compl. ~ 5, answer,-[ Sb; app. mot. at 7; gov't mot. at 2). Id. In April 2010, the Phase II solar array was supplied by Honeywell as designed, completed on time, and installed as required. However, the government has not connected it to the base electrical grid, tested it, or accepted it. (compl. ~~ 33-36, answer~~ 33-36; app. mot. at 7; gov't mot. at 2). Id. The government has not declared the array defective and has not rejected it (compl. ~ 37, answer~ 37).

6. On 22 March 2011, Honeywell submitted a certified claim to the Air Force contracting officer, contending the government breached the DO by refusing to inspect and accept the Phase II work, failing to pay interest owed for late payments, and failing to pay an invoice for $2,741,963.06 (R4, tab 50). The contracting officer's final decision rejected the claim on the ground that the solar array portion of the DO was "voidable" because it violated federal property disposition and miscellaneous receipt statutes (R4, tab 53). 13 BCA ~ 35,380 at 173,608. Honeywell appealed that decision to this Board. Its complaint sought a ruling that it was entitled to payment for both phases, and that Phase II must be accepted. Alternatively, it sought a declaration that the government had received the benefit of the installation of the arrays and that Honeywell should be compensated for the value of those benefits.

7. On 7 August 2013, the Board granted partial summary judgment to the government, invalidating the DO's inclusion of SREC sales revenues among ECM savings and to finance Honeywell's payments, as well as its grant of authority to Honeywell to sell SRECs. 13 BCA ,-[ 35,380 at 173,608-13. The Board found that revenues from SREC sales are not cognizable energy savings under the ESPC statute. Id. at 173,609-10. The Board also held that the relevant contracting officers lacked authority to permit Honeywell to sell SRECs under General Services Administration property disposal regulations. Id. at

3 "App.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

International Data Products Corp. v. United States
492 F.3d 1317 (Federal Circuit, 2007)
Prestex Inc. v. The United States
320 F.2d 367 (Court of Claims, 1963)
Urban Data Systems, Inc. v. The United States
699 F.2d 1147 (Federal Circuit, 1983)
The United States v. Amdahl Corporation
786 F.2d 387 (Federal Circuit, 1986)
Barrett Refining Corporation v. United States
242 F.3d 1055 (Federal Circuit, 2001)
Barrett Refining Corp. v. United States
45 Fed. Cl. 166 (Federal Claims, 1999)
Yosemite Park & Curry Co. v. United States
582 F.2d 552 (Court of Claims, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
Honeywell International, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/honeywell-international-inc-asbca-2015.