Honeywell International, Inc.

CourtArmed Services Board of Contract Appeals
DecidedAugust 1, 2017
DocketASBCA No. 57779
StatusPublished

This text of Honeywell International, Inc. (Honeywell International, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Honeywell International, Inc., (asbca 2017).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Honeywell International, Inc. ) ASBCA No. 57779 ) Under Contract No. W911Sl-08-F-013 l )

APPEARANCES FOR THE APPELLANT: Terry L. Albertson, Esq. Robert J. Sneckenberg, Esq. Crowell & Moring, LLP Washington, DC

APPEARANCES FOR THE GOVERNMENT: Jeffrey P. Hildebrant, Esq. Air Force Deputy Chief Trial Attorney Marvin Kent Gibbs, Esq. Senior Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE MELNICK

This is the quantum phase of this appeal involving a delivery order (DO) issued to Honeywell International, Inc. (Honeywell) under an Energy Savings Performance Contract (ESPC). Among other things, the DO required the delivery of two solar arrays. In prior summary judgment decisions the Board invalidated the portions of the DO that had recognized the value of Solar Renewable Energy Certificates (SRECs) associated with the arrays' generation. SRECs could not be included among government cost savings that would justify payment under the contract. Honeywell Int'!, Inc., ASBCA No. 57779, 13 BCA ,-i 35,380. Nevertheless, because Honeywell delivered the arrays to the government, the Board recognized Honeywell was entitled to a quantum valebant or quantum meruit recovery for the goods and services received by the government. Honeywell Int'!, Inc., ASBCA No. 57779, 15-1BCA~36,121.

The Board has since held a hearing to address quantum and awards it as discussed in the following decision.

BACKGROUND AND FINDINGS OF FACT 1

1. On 9 July 2008 the United States Army issued the DO identified above under ESPC No. DE-AM01-99EE73683 (later renumbered DE-AM36-99EE73683) (the Super ESPC) awarded by the Department of Energy to Honeywell. 15-1 BCA i-1 36, 121 at 176,338; 13 BCA ,-i 35,380 at 173,607. Through ESPCs, contractors provide the

1 Some of the citations are to the portions of prior summary judgment decisions finding that the matter is not in dispute. government with energy conservation measures (ECMs) in exchange for a share of the government's energy savings. 42 U.S.C. § 8287. ESPCs guarantee savings to agencies and dictate payment schedules based upon them. 42 U.S.C. § 8287(a). ESPCs may last for a period of up to 25 years, and a multiyear ESPC is governed by FAR Part 17 .1. 42 U.S.C. § 8287(a)(l ), (a)(2)(D)(iii).

2. This DO acquired services for Fort Dix, New Jersey, with payments eventually scheduled over 21 years (app. supp. R4, tab 2 at 9, tab 10 at 9.) 2 13 BCA ~ 35,380 at 173,607. Relevant here are two solar arrays. The original DO's requirements have been designated Phase I and included a roof mounted unit. The second solar array, Phase II, was added through a modification. 15-1 BCA ~ 36, 121 at 176,338. Phase II was approximately the same size as the Phase I unit and was to be ground mounted adjacent to a controlled humidity warehouse building (R4, tab 16 at 4; tr. 177). Each array would produce 700 kW DC peak production (R4, tab 16 at 3-4). All of the electricity was to be used by Fort Dix, eliminating any need for net metering in support of its sale outside that grid (id. at 4 ).

3. The DO calculated the annual energy savings to the government resulting from the arrays by adding the value of the electricity produced by them to the sales value of the SRECs they generated. SRECs are transferable certificates (here issued by New Jersey) representing the environmental benefits or attributes of one megawatt-hour of solar energy produced by a generator connected to the state's electrical grid. Using contractually specified values for electricity and SRECs over time, Honeywell guaranteed certain annual savings from the ECMs. The DO then scheduled annual payments to Honeywell from the government based upon those savings. The DO provided that Honeywell could sell the SRECs for the government. 15-1BCA~36,121at176,338. Honeywell understood that if the government's savings in any years were lower than Honeywell's guarantee, Honeywell would bear the cost (tr. 30-31).

4. The Super ESPC required five previously formatted schedules to be submitted by Honeywell for inclusion in the DO, identified as D0-1 through D0-5 (ex. B-1, tab 12 at 80-82). D0-1 lists Honeywell's Estimated Annual Cost Savings for each year, followed by its Proposed Guaranteed Annual Cost Savings for each year and Annual Contractor Payments. For example, as ultimately amended after modification for Phase II, D0-1 estimates $3,293,434 in government cost savings for Year 2, guarantees the lower amount of $3,196,924 in government savings that year, which would then provide Honeywell with a slightly lower $3, 196,923 payment. D0-1 lists escalation rates used to determine cost savings, including a 2.8 percent rate for electricity. (App. supp. R4, tab 10 at 7) This is confirmed elsewhere in the DO, which states that the current blended electric rate is $0.1406/kWh, escalating at 2.8 percent (R4, tab 4 at 5). The DO explains that this rate was determined from a review of cost escalations as far back as 1970 (id. at 48-49). After

2 The original schedules included in appellant's supplemental Rule 4, tab 2, contained pages that were cut off. Appellant provided complete pages in its supplemental Rule 4, tab 10. 2 addition of Phase II, the DO provides that expected savings from SRECs would be valued at $0.405/kWh for the first five years, and $0.2025/kWh for years six though ten (R4, tab 16).

5. Schedule D0-2 lists each of the ECMs and provides financial data regarding them. Thus, for the first solar array (Phase I), the schedule states that Honeywell's direct costs, called Total Implementation Expense, are $5,188,721. That figure is $4,248,275 for the Phase II modification. Schedule D0-2 provides a 25 percent markup for each phase (broken into an 18 percent overhead rate and 7 percent profit rate) leading to an Implementation Price of $6,485,90 l for the Phase I array and $5,304,278 for Phase II. (App. supp. R4, tab 10 at 8; tr. 35)

6. Schedule D0-3 contains a cash flow worksheet identifying a 6.19 percent interest rate for the financing of the initial DO, and an 8.95 percent rate for Phase II. It also breaks into components each year's government payment identified on D0-2. D0-3 also identifies other performance expenses included within each year's payment. (App. supp. R4, tab 10 at 9)

7. Schedule D0-4 provides the first year energy and cost savings expected from each ECM (app. supp. R4, tab 10 at 10).

8. Schedule D0-5 is titled "'Annual Cancellation Ceiling Schedule." It presents two columns of figures for years one through twenty. The first column is titled "Outstanding Capital Investment." The second is titled "Total Cancellation Ceiling." Note 2 of the schedule states that "Cancellation Ceilings for each time period specified ... establish the maximum termination liability for that time period." It continues that "[a]ctual total termination costs will be negotiated." Note 1 of the schedule provides that "Outstanding Capital Investment" is a "fixed subset of Total Cancellation Ceiling [which] [c]onstitutes the remaining unamortized principal on total Amount Financed for each time period specified above plus any prepayment charges, as negotiated for the delivery order award." Note 3 permits the contractor to "attach a monthly Financing Termination Liability Schedule which must correspond to the annual amounts submitted .. .in each year for Outstanding Capital Investment." (App. supp. R4, tab 10 at 11) This latter document was just a monthly version ofD0-5 (tr. 74).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Urban Data Systems, Inc. v. The United States
699 F.2d 1147 (Federal Circuit, 1983)
The United States v. Amdahl Corporation
786 F.2d 387 (Federal Circuit, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
Honeywell International, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/honeywell-international-inc-asbca-2017.