Holmes v. T. M. Strider & Co.

189 So. 518, 186 Miss. 380, 123 A.L.R. 1190, 1939 Miss. LEXIS 217
CourtMississippi Supreme Court
DecidedJune 5, 1939
DocketNo. 33736.
StatusPublished
Cited by26 cases

This text of 189 So. 518 (Holmes v. T. M. Strider & Co.) is published on Counsel Stack Legal Research, covering Mississippi Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Holmes v. T. M. Strider & Co., 189 So. 518, 186 Miss. 380, 123 A.L.R. 1190, 1939 Miss. LEXIS 217 (Mich. 1939).

Opinion

McGehee, J.,

delivered the opinion of the court.

The question presented for decision on this appeal is whether the court below was in error in granting a peremptory instruction in favor of the appellees. It is necessary to such decision, that we consider everything to have been proven which the evidence establishes, directly or by reasonable inference, against the parties in whose favor the instruction was granted. New Orleans & N. E. R. Co. v. Jackson, 140 Miss. 375,105 So. 770; New Orleans & N. E. R. Co. v. Martin, 140 Miss. 410, 105 So. 864; Yates v. Houston & Murray, 141 Miss. 881, 106 So. 110; Lowe v. Mobile & O. R. Co., 149 Miss. 889,116 So. 601; Lee County Gin Co. v. Middlebrooks, 161 Miss. 422, 137 So. 108; Keith v. Yazoo & M. V. R. Co., 168 Miss. 519, 151 So. 916; Gravette v. Golden Saw Mill Trust, 170 Miss. 15, 154 So. 274; Masonite Corporation v. Dennis, 175 Miss. 855, 168 So. 613; and the case of Stricklin v. Harvey, 181 Miss. 606, 179 So. 345.

The appellee, T. M. Strider & Company, are road contractors. They contracted with the Highway Commission to do certain work on H. S. Highway 61, in Claiborne County, north of Port Gibson. The contract contemplated, among other things, the placing of an extra steel span 100 feet in length in a bridge across Little Bayou Pierre, immediately north of the corporate limits of Port Gibson. The appellee, in pursuance of the contract, closed the highway across the bridge and did some preliminary work on the bridge, preparatory to placing the span, when they were notified by the Highway Department to stop work on the bridge. The notice given by the Highway Department was a letter, which is here copied:

*391 “Port Gibson, Miss.
“April 17, 1937.
“Miss. PWS Docked 1043-R
“P. W. S. 176 B
“Claiborne County.
“T. M. Strider & Co.
“Port Gibson, Miss.
‘ ‘ Gentlemen:
“This is your authority to stop work on the bridge on the above numbered project. You are to replace hand rail, wheel guard, and posts and open bridge to traffic until notified to resume work.
“It is understood that the cost of replacing the above items will be paid by the State Highway Dept.,
“Very truly yours,
“F. B. Davison,
“Project Engineer”.

It was shown that the contract of the appellee, T. M. Strider & Company, was for the construction of Missis-' sippi P. W. S. Projects 168-A, 168-B and 176-B, Docket 1043-R; and that Project 176-B was for rebuilding and putting the extra steel span aforesaid in this bridge across Little Bayou Pierre, located about two blocks north of where the plaintiff and others got into the automobile, in which she was a guest, and which automobile plunged from the bridge upon striking the hand or guardrail, to a depth of about thirty feet, causing her to sustain the permanent injuries complained of and to become crippled for life, as well as causing’ the death of some of the other occupants of the car and severe injuries to some.

The appellant introduced as a witness, A. E. Alford, a patrolman of the State Plighway Department, who testified that he and two other employees of the Department assisted a crew of men who were working for appellee, T. M. Strider & Company, to replace the hand or guardrail, wheel guard, posts, etc., and to reopen the bridge for public travel on the said 17th day of April, 1937, the date on which the notice to such contractor was received from the project engineer of the Department in *392 that behalf, as contained in the letter hereinbefore quoted. This witness further testified that when the appellee contractor started to work on this bridge, prior to the notice given by the Highway Department aforesaid, the wheel guards on the bridge were bolted down and the posts were bolted to the caps and stringers, and that they were secure; that the hand or guardrails were 2x8 inches in dimension, and that the posts on which they were fastened were stationed seven or eight feet apart; that the contractor on beginning the work took down the wheel guards, hand or guardrails, and also removed 100 feet of the flooring; and that upon receipt by the contractor of the notice to stop work as aforesaid, the posts were put back, as many of them with bolts as would catch to the old sills; and the others were nailed; that these posts for the hand or guardrails were placed 19% feet apart; and to which posts the hand or guardrails were again fastened. Of course, the flooring was also replaced on that day before the bridge was reopened for public travel. He also testified that the bridge remained in that condition until the next work was done thereon, about the 25th and 26th days of May, by the contractor on a force account (that is to say, at the cost of labor and materials, plus 10%, as this Project 176-B had in the meantime been eliminated from the original contract). No change was made, however, in the hand or guardrail after it was replaced by the contractor until after the accident complained of occurred on December 13,1937.

In August, 1937, a maintenance crew of the Highway Department again changed the flooring, took up the wheel guards and replaced them, covered the floor with three or four inches of gravel, so that it extended to within about two inches of the top of the wheel guard, but did not then alter the condition of the hand or guardrail except possibly to strengthen it to some extent. This witness had occasion to go down and see the bridge after the accident occurred, and found one of the posts and two hand or guardrails torn off, and saw that there had been no change in the condition of the hand or guardrail at all *393 from the time that they were replaced by the contractor, with his assistance, and the time of the accident, as heretofore stated.

Although this witness testified that in replacing the hand or guardrails, wheel guards, etc., he was working under a Mr. Stogdell, and understood that he was then working for the appellee, Vincennes Steel Corporation, it was shown by the evidence as a whole that he was then a servant of the appellee, T. M. Strider & Company. He further said that the work was being done under the supervision of the project engineer, F. B. Davidson, of the State Highway Department. But, be that as it may, neither an engineer, the Highway Department nor the contractor, T. M. Strider & Company, had the right to authorize the replacing of this hand or guardrail in a negligent manner so as to impair the safety and lives of the traveling public having occasion to use the bridge when it was reopened for public travel. Moreover, it does not appear that either the Highway Department or the project engineer instructed that the hand or guardrail be replaced in the manner testified to. The letter of April 17, 1937, addressed by the project engineer to the contractor, T. M. Strider & Company, directed that the handrail, wheel guard and posts be replaced, and that the bridge be opened to traffic.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Higginbotham v. HILL BROS. CONST. CO., INC.
962 So. 2d 46 (Court of Appeals of Mississippi, 2006)
Rector v. Mississippi State Highway Com'n
623 So. 2d 975 (Mississippi Supreme Court, 1993)
McKay v. Boyd Const. Co., Inc.
571 So. 2d 916 (Mississippi Supreme Court, 1990)
Munn v. Algee
730 F. Supp. 21 (N.D. Mississippi, 1990)
Monroe County Elec. Power Ass'n v. Pace
461 So. 2d 739 (Mississippi Supreme Court, 1984)
Higginbotham v. U.S. Industries, Inc.
584 F. Supp. 1273 (S.D. Mississippi, 1982)
Bullock v. Fairburn
353 So. 2d 759 (Mississippi Supreme Court, 1977)
Baker v. Fryar
421 P.2d 784 (New Mexico Supreme Court, 1966)
Triplett v. American Creosote Works, Inc.
171 So. 2d 342 (Mississippi Supreme Court, 1965)
Finley P. Smith, Inc. v. Schectman
132 So. 2d 460 (District Court of Appeal of Florida, 1961)
Bowyer & Johnson Construction Co. v. White
255 F.2d 482 (Fifth Circuit, 1958)
Bowyer & Johnson Construction Company v. Joe White
255 F.2d 482 (Fifth Circuit, 1958)
King v. Mason
95 So. 2d 705 (Louisiana Court of Appeal, 1957)
Zellers v. Cloud
302 S.W.2d 467 (Court of Appeals of Texas, 1957)
Smith Engineering & Construction Co. v. Cohn
94 So. 2d 826 (Supreme Court of Florida, 1957)
Meridian Hatcheries, Inc. v. Troutman
93 So. 2d 472 (Mississippi Supreme Court, 1957)
Delgaudio v. Ingerson
110 A.2d 626 (Connecticut Superior Court, 1954)
Burris v. J. Ray McDermott & Co.
116 F. Supp. 907 (W.D. Louisiana, 1953)

Cite This Page — Counsel Stack

Bluebook (online)
189 So. 518, 186 Miss. 380, 123 A.L.R. 1190, 1939 Miss. LEXIS 217, Counsel Stack Legal Research, https://law.counselstack.com/opinion/holmes-v-t-m-strider-co-miss-1939.