Higginbotham v. U.S. Industries, Inc.

584 F. Supp. 1273, 1982 U.S. Dist. LEXIS 17699
CourtDistrict Court, S.D. Mississippi
DecidedAugust 11, 1982
DocketCiv. A. Nos. J80-0177(N), J80-0178(N)
StatusPublished

This text of 584 F. Supp. 1273 (Higginbotham v. U.S. Industries, Inc.) is published on Counsel Stack Legal Research, covering District Court, S.D. Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Higginbotham v. U.S. Industries, Inc., 584 F. Supp. 1273, 1982 U.S. Dist. LEXIS 17699 (S.D. Miss. 1982).

Opinion

MEMORANDUM OPINION

WALTER L. NIXON, Jr., Chief Judge.

These consolidated wrongful death actions were filed by the lawful heirs of Billy Robert Higginbotham and Clement F. Durham against the defendant, U.S. Industries, Inc., d/b/a Con-Plex, Division of U.S. Industries, . Inc. (Con-Plex), in the Circuit Court of Franklin County, Mississippi, and were removed to this Court by the defendant.

Each group of plaintiffs seek damages from the defendant for personal injuries [1275]*1275and death of their deceased husband and father who lost their lives- on April 13, 1974, when they drowned in the Homochitto River as the result of the collapse of two bridge spans into the river on Mississippi State Highway 33, which had been constructed by the defendant for the Mississippi State Highway Department and accepted by the Department approximately two months prior to the collapse. The bodies of the two deceased were found many miles downstream several days after they were seen in the river following the collapse of the bridge during one of the almost annual floods of the Homochitto River which was traversed by the bridge in question, which connected Franklin and Wilkinson Counties as part of State Highway 33.

As a result of a previous flood of the Homochitto on December 6, 1971, major sloughing occurred on the north bank of the river, requiring closing of the bridge to traffic. The State Highway Department (the Department), which knew that the stream of the Homochitto was moving in a northerly direction and that the soil of the north embankment was easily erodible, undertook to have the three-addition span in question constructed from the north bank to connect to the existing span so that the bridge could be re-opened to traffic. The Department and the Federal Highway Administration, which was funding 100 percent of the project under its Emergency Relief Program, compromised on the design and budget for the addition to the bridge, which both agencies thought would overcome the then existing erosion problem.

The Bridge Division of the Department designed a three-span extension or' addition to be added onto the north abutment of the present bridge, and these plans were circulated throughout the Department’s Project Office, District Office, and Central Office in Jackson. The plans and specifications were examined and approved at each one of these levels and were also circulated through the Federal Highway Administration and examined and approved by the engineers of that agency. These plans were then sent out for competitive bids, and the defendant, Con-Plex, together with other contractors, bid the project on the basis of the plans, as required, inasmuch as a bidding contractor was not permitted to make any reservations or exceptions for the Department’s plans; otherwise, its bid would be rejected.

. Con-Plex bid the job for a total price of $349,834.94, was awarded the contract, which it signed on March 1, 1973, agreeing to construct the three new 100-foot spans. The defendant was required to and did post a bond guaranteeing that it would complete the project in strict compliance with the plans and specifications furnished by the Department, and agreed to perform the construction under the direct supervision and to the full satisfaction of the Department’s inspectors.

The three new 100-foot spans were to be added onto the north end of the existing bridge, with no part of these three spans to actually be over the river stream or bed, but rather entirely over the north embankment of the river. At the time of preparation of the plans, the pilings beneath the north end of the then existing “old bridge” were located on the edge of the embankment jhst north of the river bed and were designated Bent 5. The three new concrete spans were to be supported by three sets of new pilings, to be driven 100 feet apart and extending north from the north end of the old bridge over the north embankment of the river. The first set of new pilings to be driven north of the existing bridge was designated Bent 6, and the next two sets to the north thereof as Bents 7 and 8, respectively. The ground elevation extending north from Bent 5 of the existing bridge to Bent 8 was approximately 134 feet at the time of the bidding, and was generally level.

Inasmuch as the pilings beneath Bent 5 were almost in the river stream at the time of the bidding, the plans required the contractor to drive eight additional pilings beneath Bent 5, which already had eleven piles beneath it, and to reinforce all these nineteen pilings by encasement with a solid [1276]*1276concrete skirt. The plans further provided for driving eleven steel pilings into the solid embankment at Bents 6 and at 7, and fourteen pilings at the north end of the newly constructed addition at Bent 8, with approximately three feet of all these pilings to be exposed above ground level and all to be capped with ten feet of concrete. As originally designed, none of the pilings under Bents 6, 7 or 8 were to be exposed to the flow of the river or were to be reinforced by a solid concrete encasement or apron (as was Bent 5) or cross-bracing.

After being awarded the contract and before commencing work on the project, Con-Plex officials visited the site at least three times and found that conditions had greatly changed since their previous visits prior to bidding the project. As a result of these visits or inspections, and before commencing any work on the bridge project, Con-Plex wrote the Department Project Engineer on May 9, 1973 (Exhibit P-13), notifying him that “physical conditions at the site had changed greatly since the date of bidding; that is, that the designated area of the detour bridge, which was to be built in connection with this project, was completely washed away” and that “... physical conditions continue to change daily as more of the approach continues to slide into the river, which is cutting against the tow of the approach embankment.” In this letter, Con-Plex further advised the Department that as of the date that it made its bid on April 24, 1973, the embankment was in place to the abutment of the existing bridge and that there were minor cracks within two to three feet of the abutment end; but that on May 1, upon viewing the bridge site, it was found that the area adjacent to the abutment had slid into the river for about fifteen feet beyond the abutment, and that beyond that area approximately another twenty-five feet of large cracks were beginning to appear in the embankment; that on May 4, the embankment had subsided for a distance of approximately forty feet behind the abutment, with cracks approximately twenty-five feet beyond that point; and on May 8, the embankment had subsided for approximately fifty feet behind the abutment, with cracks in the embankment sixty-five to one hundred fifteen feet behind the abutment. Con-Plex noted that the foregoing observations indicated “a progressive deterioration of the work area” and it made various observations and requests.

In its foregoing letter, the defendant stated that in order to perform the required work on the project, it would require a work bridge over the area and any subsequent areas where existing embankment had eroded and would continue to erode from conditions beyond its control; and that a seven-span work bridge would be required to perform the work on the existing abutment and to erect prestress beams, which would cost $5,943.00 per span, with the understanding that any further slides would require additional spans to be erected at the above cost.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Davis v. Henderlong Lumber Company
221 F. Supp. 129 (N.D. Indiana, 1963)
Holmes v. T. M. Strider & Co.
189 So. 518 (Mississippi Supreme Court, 1939)
Ryan v. Feeney & Sheehan Building Co.
145 N.E. 321 (New York Court of Appeals, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
584 F. Supp. 1273, 1982 U.S. Dist. LEXIS 17699, Counsel Stack Legal Research, https://law.counselstack.com/opinion/higginbotham-v-us-industries-inc-mssd-1982.