Finley P. Smith, Inc. v. Schectman

132 So. 2d 460
CourtDistrict Court of Appeal of Florida
DecidedAugust 30, 1961
Docket2205, 2206
StatusPublished
Cited by16 cases

This text of 132 So. 2d 460 (Finley P. Smith, Inc. v. Schectman) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Finley P. Smith, Inc. v. Schectman, 132 So. 2d 460 (Fla. Ct. App. 1961).

Opinion

132 So.2d 460 (1961)

FINLEY P. SMITH, INC., Appellant,
v.
Mary SCHECTMAN, Appellee.
FINLEY P. SMITH, INC., Appellant,
v.
Seymour SCHECTMAN, Appellee.

Nos. 2205, 2206.

District Court of Appeal of Florida. Second District.

August 30, 1961.

*461 Frank M. Hamilton, Fleming, O'Bryan & Fleming, Fort Lauderdale, for appellant.

Charles Desmond Crowley, Fort Lauderdale, for appellees.

ALLEN, Acting Chief Judge.

These appeals were instituted as two suits at law by Mary Schectman and her husband, Seymour Schectman, for damages for personal injuries received when an automobile, operated by Mrs. Schectman, and owned by her husband who was a passenger therein, went out of control after traveling over a rough spot in the pavement which was under construction by the defendant corporation. The trial resulted in a jury verdict in favor of the plaintiff wife for $2,000 and a verdict for the plaintiff husband of $7,000. The appeals have been consolidated pursuant to stipulations of the parties.

Dunn Construction Company entered into a contract with the State Road Department whereby Dunn, through its subcontractors, was to construct or "four-lane" a portion of U.S. Highway #1, in Martin County. The construction covered a stretch of highway 8.5 miles in length and the accident occurred on a portion of the highway under construction.

The highway was formerly a two-lane highway running north and south. In constructing the additional two lanes it was necessary to install several drainage culverts. Dunn Construction subcontracted with Finley P. Smith, Inc., to perform the portion of highway construction involved in this suit. A culvert had been constructed by pouring concrete into a wooden form which had required a large excavation across the highway. Traffic was detoured until the concrete had cured and the forms *462 were removed. The excavation was filled in and topped with limerock.

The limerock was rolled and traffic was reopened in order to further pack the limerock and fill dirt before concrete was poured.

The plaintiffs were traveling south, Mrs. Schectman was driving and Mr. Schectman was asleep in the back seat of the automobile when it went out of control on the rough stretch of road, thereby injuring the plaintiffs.

Mrs. Schectman testified that she did not see the area where the culvert had been installed; that she does not grip the steering wheel tightly while driving but does hold it lightly; and that when the car hit the depressed rough stretch it went out of control and the next thing she remembers is when she awoke after the accident.

McKeever Simmons, the only eyewitness, testified that Mrs. Schectman passed him at an approximate speed of 30 to 35 miles per hour while he was traveling 25 miles per hour; that the accident occurred when he was 100 to 150 feet behind the plaintiffs' automobile; that plaintiffs' vehicle hit some holes in the road, veered to the left and landed in the ditch. Simmons stated that the culvert fill portion was 15 to 20 feet wide; that there were some holes 9 to 12 inches deep, some of which were 6 inches wide; and that it was difficult to see this portion until you were "right up on it."

It appears from the record that Deputy Johnson testified that there were "pot-holes" in the road caused by the rain and the traffic and that he braced himself when traveling that portion of the highway.

The facts adduced in the trial of these two consolidated cases nearly parallel the facts in the case of Smith Engineering & Construction Co. v. Cohn, Fla. 1957, 94 So.2d 826, 828. In this case the Supreme Court held that where a contract to repair a highway required the contractor to keep the highway open for traffic while work was being done, the contractor was liable for damages sustained when a truck overturned as a result of negligence of the contractor in replacing a portion of a roadbed which, together with pavement, had been removed for installation of temporary culverts.

In the above case the plaintiff observed a sign which read "road under construction," then proceeded about one mile and observed a break in the pavement. He brought his truck to a stop and studied the road and, while it was unpaved for about twelve feet, it appeared safe. He turned to the center of the road and proceeded over the unpaved area. The tractor part of the truck crossed the break without difficulty but the trailer turned over on its side and carried the tractor over on the road. The Court, in its opinion, said:

"The Company was a road contractor and at the time of the accident was under contract with the State Road Department, to repair this particular sector of Highway 20. The contract required that the Company keep the road open for traffic while the work was being done. It appears that the break in the pavement was caused by the installation of temporary culverts to divert water from the permanent culvert which was being extended. The pavement and roadbed had been removed for this purpose but the roadbed was replaced at the time and the road surfaced and packed with tractors and clay placed on the surface. A heavy rain had recently fallen but the driver of the truck testified that the roadbed appeared in good condition so he proceeded across.
* * * * * *
"The complaint was grounded on negligence of appellant, the jury found it negligent which was not controverted, its contract with the State Road Department required it to keep the road in such condition while being repaired as traffic could pass over it. *463 The following cases conclude the point against the contention of appellant: Price v. Parks, 127 Fla. 744, 173 So. 903; Briscoe v. Worley, Okl., 253 P.2d 145; Morgan Hill Paving Co. v. Fonville, 218 Ala. 566, 119 So. 610; Holmes v. T.M. Strider & Co., 186 Miss. 380, 189 So. 518, 123 A.L.R. 1190."

This court affirmed the lower court in M.J. Carroll Contracting Company v. Pine, Fla.App. 1958, 103 So.2d 685, 688, another action brought against a road contractor for alleged negligence in a highway construction job. In the opinion we quoted from a concurring opinion of Mr. Justice Davis in the case of H.E. Wolfe Construction Co. v. Ellison, 1936, 127 Fla. 808, 174 So. 594, 602, where Mr. Justice Davis stated:

"`* * * The general rule to the foregoing effect is thus succinctly stated by the Supreme Court of Alabama [Kearns v. Mobile Light & R. Co., 196 Ala. 99, 71 So. 993, 994] as follows: "It must of course be conceded that, as a general rule, the sufficiency of signals or barriers to give reasonable warning of or security against existing danger, especially with respect to their character, number, and arrangement, is a question of fact for the jury."'"

The defendant was a subcontractor of Dunn Construction Company whose contract with the State Road Department of Florida required that the road under construction be kept in such condition that traffic could pass over it and that there should be a safe passageway at all times for traffic and that all necessary precautions should be taken for the protection of the work and safety of the public.

The issues were submitted to a jury and the jury's determination of the factual situation was in favor of the plaintiffs below, appellees here.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Silver Palm Properties, Inc. v. Sullivan
541 So. 2d 624 (District Court of Appeal of Florida, 1988)
Baysal D. Riddle v. Exxon Transportation Company
563 F.2d 1103 (Fourth Circuit, 1977)
Janes v. Baptist Hospital of Miami, Inc.
349 So. 2d 672 (District Court of Appeal of Florida, 1977)
Zilber Cab Company v. Capeletti Brothers, Inc.
303 So. 2d 360 (District Court of Appeal of Florida, 1974)
National Bank of Melbourne & Trust Co. v. Batchelor
266 So. 2d 185 (District Court of Appeal of Florida, 1972)
Cheek v. Long
235 So. 2d 349 (District Court of Appeal of Florida, 1970)
Tuggle v. Government Employees Insurance Co.
207 So. 2d 674 (Supreme Court of Florida, 1968)
Lamb v. Jones
202 So. 2d 810 (District Court of Appeal of Florida, 1967)
Raymond Parker v. Loren Wideman
380 F.2d 433 (Fifth Circuit, 1967)
Miami Beach First National Bank v. Borbiro
201 So. 2d 571 (District Court of Appeal of Florida, 1967)
Clemons v. Clark
172 So. 2d 242 (District Court of Appeal of Florida, 1965)
Mahr v. General Telephone Co.
163 So. 2d 285 (Supreme Court of Florida, 1964)
Brookbank v. Mathieu
152 So. 2d 526 (District Court of Appeal of Florida, 1963)
Paradis v. Thomas
150 So. 2d 457 (District Court of Appeal of Florida, 1963)
Cudd v. Great American Insurance Company
202 F. Supp. 237 (W.D. Louisiana, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
132 So. 2d 460, Counsel Stack Legal Research, https://law.counselstack.com/opinion/finley-p-smith-inc-v-schectman-fladistctapp-1961.