Hoffman v. Maffioli

80 N.W. 1032, 104 Wis. 630, 1899 Wisc. LEXIS 331
Wisconsin Supreme Court·Decided November 24, 1899·Published·Cited by 35 cases

Opinions

Oassoday, O. J.

This action was commenced June 28, 1898, to recover $2,888, with interest from June 16,1898, on [631] account for goods, wares, and merchandise sold and delivered by the plaintiff, doing business under the name of The Waukesha Stone & Quarry Company,” to the defendant, between April 23, 1898, and June 16, 1898, at the agreed 'price, and which was reasonably worth the sum stated, all of which became due and payable June 16, 1898.

The defendant answered by way of admissions and denials, and also alleged by way of counterclaim, in effect, that the defendant was a principal contractor engaged in macadamizing and paving streets, April 15, 1898, and as such principal contractor he entered into a contract with the city of Waukesha for the concreting and paving of the whole of West Main street in that city; that April 21,1898, the plaintiff, in the name of the Waukesha Stone & Quarry Company, submitted a written proposal to the defendant in the words and figures following, to wit:

“Waukesha, Wis., April 21, 1898.
“ To Mr. O. Maffioli.
“Dear Sib: We propose to furnish crushed stone at 85c. per yard of 2,500 lbs., 30 in. x é in. curbing, including corners at 31c. per lineal foot, protection curb 15 in. x 1 in. at 10c. per lineal foot, all as per specifications. Delivered on street in the city of Waukesha in such quantities as may be desired.
“ Respectfully submitted,
“ The Waukesha Stone and Quaeet Co.,
“ per Kiehl, Mngr.”

The answer also alleged that such proposal was duly accepted in writing, written thereunder by the defendant, May 1, 1898, as follows: “Accepted May 1, 1898. G. Maf-xioli ; ” that the plaintiff had neglected and failed to perform such agreement on his part, in -that he misrepresented the actual measurement and weight of stone delivered to ‘the defendant; that it was ascertained by accurate tests made May 30, 1898, of three or four loads of crushed stone [632] so delivered by the plaintiff to the defendant, and at different times, that said loads were less in weight by fifty, three hundred, and five hundred pounds, respectively, than was-represented by tickets or scale receipts , delivered by the plaintiff to the defendant; that the defendant had reason to believe, and did believe, that every.load of crushed stone delivered to the defendant by the plaintiff was far less- in weight and measurement than represented and charged by him; that the plaintiff absolutely refused to examine or correct the shortage mentioned, and refused to furnish and deliver any further crushed stone or curbing to the defendant, and continued to so refuse; that by reason of such failure, fault, and neglect on the part of the plaintiff the defendant was actually and necessarily hindered and delayed in executing and completing his paving contract, and suffered and sustained great loss of time and damage with his hired men and otherwise to the amount of $1,500. And the answer contained a further counterclaim to the effect that on account of the plaintiff’s failure and neglect to furnish crushed stone and curbing as ■ stated the defendant necessarily incurred other and further expenses in order to complete his paving contract, in that he was compelled to, and actually did, procure and purchase such crushed stone and curbing elsewhere, at greatly enhanced prices, to his damage in the sum of $1,000.

The plaintiff, by way of reply, admitted the written contract, but denied all other allegations in the respective' counterclaims.

At the close of the trial the jury returned a verdict in favor of the plaintiff, and assessed his damages at $2,957.58. Erom the judgment entered thereon the defendant brings this appeal.

There is no dispute but that the plaintiff actually delivered the amount of curbing which he claims to have delivered, nor that he furnished three car loads of crushed stone, [633] which the defendant shipped to Eockford, Illinois; nor that the stone so delivered at the contract price amounted to». $1,836.22. There is, however, a considerable dispute as to the amount of crushed stone delivered by the plaintiff to the defendant on the street in Waukesha. It appears that with each load of crushed stone s.o delivered the plaintiff furnished to the defendant, or to his superintendent, a ticket, or memorandum of the weight of the load by the plaintiff’s:, scales. The defendant gave evidence tending to prove that, by actual tests on other scales the aggregate weight of three of the loads so delivered was several hundred pounds less, than the weight represented by such tickets or memoranda. The defendant' only made such tests as to three loads. On the other hand, there is evidence on the part of the plaintiff” tending to prove that his weight of each and every load, as-represented by such tickets or memoranda, and charged to the defendant, was. substantially correct. The question as to the alleged shortage in the several loads of crushed stone seems to have been fairly submitted to the jury. The contract left each party to ascertain the weight of each load of the stone as he might be advised. In case of a dispute about-, the weight, the only way to determine the same was by submitting the question of weight to the jury. That was done as to the only loads upon which there was any conflict in the evidence. There was no error in charging the jury to-the effect that; even if there was a shortage in the three loads mentioned, yet that fact of itself was insufficient to-establish a shortage in any of the other 592 loads.

Free access — add to your briefcase to read the full text and ask questions with AI

Hoffman v. Maffioli, 80 N.W. 1032, 104 Wis. 630, 1899 Wisc. LEXIS 331 (Wis. 1899).

80 N.W. 1032 (Hoffman v. Maffioli) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Streich v. General Motors Corp.
126 N.E.2d 389 (Appellate Court of Illinois, 1955)
Pittsburgh Plate Glass Co. v. Paine & Nixon Co.
234 N.W. 453 (Supreme Court of Minnesota, 1930)
Freedom Oil Works Co. v. Williams
152 A. 741 (Supreme Court of Pennsylvania, 1930)
American Insurance Union v. Rowland
8 S.W.2d 452 (Supreme Court of Arkansas, 1928)
Brooks v. Federal Surety Co.
24 F.2d 884 (D.C. Circuit, 1928)
Inter-Southern Life Insurance v. Shutt
1 S.W.2d 901 (Supreme Court of Arkansas, 1928)
Ullman v. Bee Hive Department Store
214 N.W. 349 (Wisconsin Supreme Court, 1927)
Van Deren v. Heineke & Co.
252 P. 459 (Supreme Court of Kansas, 1927)
Weston Paper Mfg. Co. v. Downing Box Co.
293 F. 725 (Seventh Circuit, 1923)
Wickham & Burton Coal Co. v. Farmers Lumber Co.
189 Iowa 1183 (Supreme Court of Iowa, 1920)
Grand Prairie Gravel Co. v. Joe B. Wills Co.
188 S.W. 680 (Court of Appeals of Texas, 1916)
M. A. Brown Paper Box Co. v. King-Brinsmade Mercantile Co.
190 Mo. App. 584 (Missouri Court of Appeals, 1915)
Parks v. Griffith & Boyd Co.
91 A. 581 (Court of Appeals of Maryland, 1914)
Gile v. Interstate Motor Car Co.
145 N.W. 732 (North Dakota Supreme Court, 1914)
McGuire v. Old Sweet Springs Co.
79 S.E. 350 (West Virginia Supreme Court, 1913)
Rehm-Zeiher Co. v. F. G. Walker Co.
160 S.W. 777 (Court of Appeals of Kentucky, 1913)
Rotzien-Furber Lumber Co. v. Franson
143 N.W. 253 (Supreme Court of Minnesota, 1913)
Bartlett Springs Co. v. Standard Box Co.
117 P. 934 (California Court of Appeal, 1911)
Moran Bolt & Nut Manufacturing Co. v. St. Louis Car Co.
109 S.W. 47 (Supreme Court of Missouri, 1908)
A. Santaella & Co. v. Otto F. Lange Co.
155 F. 719 (Eighth Circuit, 1907)