Herkert v. Stauber

317 N.W.2d 834, 106 Wis. 2d 545, 31 A.L.R. 4th 879, 1982 Wisc. LEXIS 2525
CourtWisconsin Supreme Court
DecidedMarch 26, 1982
Docket80-816
StatusPublished
Cited by15 cases

This text of 317 N.W.2d 834 (Herkert v. Stauber) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Herkert v. Stauber, 317 N.W.2d 834, 106 Wis. 2d 545, 31 A.L.R. 4th 879, 1982 Wisc. LEXIS 2525 (Wis. 1982).

Opinion

COFFEY, J.

This is a review of a decision of the court of appeals affirming a judgment of the circuit court for Dane county, WILLIAM F. EICH presiding. The judgment awarded Herman J. Herkert, the plaintiff-respondent, $50,400 in a breach of a contract action *548 concerning a certain contract between himself and Mazer-Stauber Associates, P.C., defendants-appellants-petitioners, for the construction of housing units for the elderly. After trial, the jury returned a verdict finding that Mazer-Stauber Associates, P.C., and Guardian Corporation breached the contract with respect to their obligation to secure approval from the Farmer’s Home Administration (FmHA) for financing and awarding damages of $7,500. In a memorandum decision on motions after verdict, the trial court increased the $7,500 damage figure to $50,400 holding that these damages were proven as a matter of law and entered judgment against the defendants, both corporate and individual. The defendants appealed alleging three errors, the trial court’s refusal to instruct the jury concerning frustration of purpose; the determination of damages as a matter of law; and the entry of judgment against the individual defendants. The appellate court affirmed holding that the defendant’s failure to raise their arguments with respect to the frustration of purpose instruction and the determination of individual liability before the trial court constituted a waiver of their right to raise these issues on appeal. Further, the appellate court approved the trial court’s increase of the damage award as a matter of law.

Mazer-Stauber Associates, P.C. (M-S Associates) entered into a contract with Herkert, agreeing to design and build an 8-unit apartment building for Herkert on designated land in Poynette, Wisconsin. Herkert testified that he had become interested in the housing proj ect as a result of the promotional efforts of William Mazer, a representative of M-S Associates.

Robert Stauber and Richard Mazer, both architects, formed M-S Associates as a Michigan professional service corporation and hired William Mazer, a nonarchi-tect, as a promotional employee. The construction con *549 tract entered into between Herkert and M-S Associates was dated and signed by Robert Stauber as president of M-S Associates on September 17,1975.

The construction contract recited that the housing project would be financed through a long-term, low interest loan from the Farmers Home Administration (FmHA) of the United States Department of Agriculture and further, it expressly provided that the construction contract would become null and void should M-S Associates be unable to obtain an FmHA loan on Herkert’s behalf or other satisfactory construction financing. Among the contractual obligations of M-S Associates was the responsibility to provide “the general design criteria, architectural, engineering and construction drawings and necessary documents and information” required for a complete application for financing. The total cost of the construction project exclusive of the land was not to exceed $115,000.

Prior to the formal execution of the contract on September 17, 1975, the parties made last minute additions thereto which they have referred to as “addendums.”' Three such “addendums” were attached to the contract and each was dated and signed by William Mazer and Herman Herkert on September 16, 1975. One of these additions to the contract purported to obligate M-S Associates to sell the land on which the project was to be built to Herman Herkert for the price of $8,000. The addendum also gave Herkert an option to purchase an adjacent parcel of land for an additional $8,000. An *550 other of the additions to the contract guaranteed that Herkert’s total out-of-pocket expenses for the building construction and purchase of land would not exceed $123,000. The addendum also represented that upon completion of the project, Herkert would receive $2,900 annually from the rents collected which amount the parties referred to as a “cash flow.” At trial, conflicting testimony was presented concerning the date on which the addendums were actually signed and whether William Mazer had the authority to enter into the adden-dums on behalf of the corporation. Additionally, the trial testimony was inclusive as to whether either Richard Mazer or Robert Stauber knew that the addendums were added to the contract.

On September 18, 1975, M-S Associates filed a portion of the “pre-application” form for FmHA financing on behalf of Herkert. Shortly after the partial “pre-appli-cation” form was submitted to the FmHA, Robert Stauber resigned from M-S Associates and the corporation ceased the active practice of architecture and the former business remained only as a registered corporate entity. The responsibility for the Herkert contract was then transferred to the newly formed Guardian Corporation, with William Mazer as its president and his brother, Richard Mazer, as vice-president. Guardian Corporation continued to prepare and file the necessary documents for the FmHA loan and on January 14, 1977 the FmHA gave a preliminary concurrence on the “pre-application” form on file.

In March of 1977, FmHA advised the Guardian Corporation of an opportunity to utilize multiple funding for the apartment project by combining the resources of the Department of Housing and Urban Development (HUD) with those of the FmHA to finance an expanded 16-unit housing project rather than the 8-unit project previously agreed upon and on the drawing board. The Guardian *551 Corporation informed Herkert of the availability of this type of financing and Herkert consented to alter his original loan application from FmHA financing alone to joint HUD-FmHA financing. The Guardian Corporation notified the FmHA of their change of plans from an 8-unit to a 16-unit project and the corresponding change in the type of financing being sought. The same local FmHA office which handled the original pre-application for singular FmHA financing processed the application for the joint HUD-FmHA financing.

As a result of the parties seeking the combined HUD-FmHA financing, they were required to fulfill several additional procedural requirements which were not necessary for approval of the original FmHA financing. One of the more significant new requirements was the need to obtain a letter of approval for the 16-unit (HUD-FmHA) apartment project from the mayor or village president of the community in which the project was to be built. Guardian Corporation informed the FmHA that the approval it had requested for the project from the village council of Poynette and its president had been denied. The Guardian Corporation viewed this decision on the part of the village of Poynette authorities as a death blow to the 16-unit joint HUD-FmHA housing project and, thus, it proceeded no further on the Herkert project.

Some three and one-half months thereafter, on August 5, 1977, the FmHA informed Herkert by letter that the department would consider its file on his loan application inactive and informed him that unless action was taken on the application within fifteen days of that date, the application would be considered withdrawn. Herkert forwarded this letter to the Guardian Corporation and they failed to respond to the FmHA letter or take any other action. The FmHA, on August 20, 1977, closed its file on the Herkert application.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Value Plus Flooring, LLC v. Don O. Johnson, LLC
Court of Appeals of Wisconsin, 2025
Daniel L. Lamphere v. Ryan Hulback
Court of Appeals of Wisconsin, 2025
Reuben v. KOPPEN
2010 WI App 63 (Court of Appeals of Wisconsin, 2010)
Racine County v. Oracular Milwaukee, Inc.
2009 WI App 58 (Court of Appeals of Wisconsin, 2009)
State v. Neuaone
2005 WI App 124 (Court of Appeals of Wisconsin, 2005)
State v. Van Camp
569 N.W.2d 577 (Wisconsin Supreme Court, 1997)
Paape v. Northern Assurance Co. of America
416 N.W.2d 665 (Court of Appeals of Wisconsin, 1987)
Glamann v. St. Paul Fire & Marine Insurance
412 N.W.2d 522 (Court of Appeals of Wisconsin, 1987)
Hartford Insurance v. Wales
406 N.W.2d 426 (Wisconsin Supreme Court, 1987)
Racine Education Ass'n v. Board of Education
385 N.W.2d 510 (Court of Appeals of Wisconsin, 1986)
Herkert v. Stauber
378 N.W.2d 704 (Court of Appeals of Wisconsin, 1985)
Muschel v. Town of Molitor
365 N.W.2d 622 (Court of Appeals of Wisconsin, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
317 N.W.2d 834, 106 Wis. 2d 545, 31 A.L.R. 4th 879, 1982 Wisc. LEXIS 2525, Counsel Stack Legal Research, https://law.counselstack.com/opinion/herkert-v-stauber-wis-1982.