Value Plus Flooring, LLC v. Don O. Johnson, LLC

CourtCourt of Appeals of Wisconsin
DecidedJune 24, 2025
Docket2024AP000213
StatusUnpublished

This text of Value Plus Flooring, LLC v. Don O. Johnson, LLC (Value Plus Flooring, LLC v. Don O. Johnson, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Value Plus Flooring, LLC v. Don O. Johnson, LLC, (Wis. Ct. App. 2025).

Opinion

COURT OF APPEALS DECISION NOTICE DATED AND FILED This opinion is subject to further editing. If published, the official version will appear in the bound volume of the Official Reports. June 24, 2025 A party may file with the Supreme Court a Samuel A. Christensen petition to review an adverse decision by the Clerk of Court of Appeals Court of Appeals. See WIS. STAT. § 808.10 and RULE 809.62.

Appeal No. 2024AP213 Cir. Ct. No. 2021CV217

STATE OF WISCONSIN IN COURT OF APPEALS DISTRICT III

VALUE PLUS FLOORING, LLC,

PLAINTIFF,

V.

DON O. JOHNSON, LLC AND DON JOHNSON’S CUMBERLAND MOTORS, LLC,

DEFENDANTS-CROSS-CLAIM PLAINTIFFS-THIRD-PARTY PLAINTIFFS-APPELLANTS,

NORTHWEST BUILDERS, INC.,

DEFENDANT,

GRIES ARCHITECTURAL GROUP INC.,

THIRD-PARTY DEFENDANT-RESPONDENT. No. 2024AP213

APPEAL from a judgment of the circuit court for Barron County: MAUREEN D. BOYLE, Judge. Affirmed.

Before Stark, P.J., Hruz, and Gill, JJ.

Per curiam opinions may not be cited in any court of this state as precedent

or authority, except for the limited purposes specified in WIS. STAT. RULE 809.23(3).

¶1 PER CURIAM. Don O. Johnson, LLC, and Don Johnson’s Cumberland Motors, LLC (collectively, “Johnson”), appeal from a circuit court’s order granting summary judgment to Gries Architectural Group, Inc., and dismissing Johnson’s third-party breach of contract claim against Gries. Johnson argues that the circuit court erred by concluding that Johnson was required to provide expert testimony in response to Gries’ summary judgment motion to support Johnson’s claim that Gries breached a contract by failing to meet the standard of care owed by Gries in providing architectural and structural engineering services. We affirm.

BACKGROUND

¶2 The underlying dispute in this case involves an allegedly defective tile floor installed by Value Plus, LLC, as part of Johnson’s construction of a new automotive dealership. Prior to the dispute, Johnson retained Gries to provide “architectural and structural engineering services for the construction of” the dealership. Moreover, Johnson expected that Gries would be “both the architect and [Johnson’s] representative for the construction” and that Gries would “address any warranty problems.” Johnson also hired Northwest Builders, Inc., as the “construction manager.” Northwest Builders contracted with Value Plus to install the dealership flooring.

2 No. 2024AP213

¶3 Prior to being hired by Johnson, Gries submitted a proposal that stated Gries would, among other things, “provide design” for the dealership, “provide master site plan operations,” prepare drawings and specifications, “complete all construction documents and submit” them for governmental approval, “[a]ssist” the construction manager in the development of a list of qualified subcontractors, “provide administration of the Contract for Construction,” and “be your representative during construction until final payment to the contractor is due.” The proposal further stated that Gries would “[r]eview change orders and submit [them] to [Johnson] with recommendations” and that Gries would “[r]eview and approve payment applications and acquire lien waivers.” The proposal was accepted by Johnson, and Gries does not expressly deny that the proposal was a contract between it and Johnson.

¶4 During construction of the dealership, an issue arose with the installed tile flooring. Value Plus argued that the problems with the tile were the result of alternative tile being used for construction, which was ultimately selected for the project without Value Plus’s input. After Northwest Builders failed to pay Value Plus in full for its completed work on the dealership, Value Plus brought this lawsuit against Johnson and Northwest Builders seeking a foreclosure lien to recover the value of unpaid labor and materials it furnished for the construction. Northwest Builders then filed a breach of contract cross-claim against Johnson, alleging that it had completed additional work on the dealership, pursuant to change orders totaling nearly $250,000, for which it was never paid.

¶5 Relevant here, Johnson claimed that the tile flooring installed by Value Plus was “defective,” and it filed a third-party complaint against Gries for breach of contract and negligence on that basis. Johnson alleged that it had contracted with Gries to “provide architectural and structural engineering services

3 No. 2024AP213

for the construction” of the dealership. Johnson further alleged that Gries had agreed to “lead the process of coordinating specifications for the project,” administer “the construction contract,” and act as Johnson’s “representative during construction.” According to Johnson, Gries’ “actions or inactions in breach of its contractual obligations … led to the installation of a defective floor” and that the installation of the defective floor caused it damages. Johnson sought dismissal of Value Plus’s claims against it, removal of the lien against the dealership property, and judgment against Gries to the extent Value Plus “recovers any judgment from” Johnson. The specific third-party claims alleged against Gries made no mention of the lien or the $250,000 in additional work Northwest Builders claimed to have performed pursuant to change orders.

¶6 Gries denied Johnson’s allegations and moved for summary judgment on the third-party claims. Gries argued that Johnson had failed to provide any evidence from an expert to rebut Gries’ expert witness’s opinion that Gries’ performance regarding the tile flooring met the standard of care for architectural services. Gries stated in its motion that its expert witness “opine[d] that the work Gries performed met the standard of care of architectural services and that the issues related to the tile installation were due to [Value Plus’s] poor workmanship.” Moreover, according to Gries’ motion, Johnson’s and Northwest Builders’ experts “agree[d] that [Value Plus] did not install the tile in a manner consistent with the construction documents and that the tile damage was caused by [Value Plus’s] failure to comply with the project specifications.” Furthermore, none of the experts “opine[d] that Gries fell below the standard of care or that there [was] a causal connection between Gries’ conduct and the tile issues and incorrect installation.”

4 No. 2024AP213

¶7 In response, Johnson argued that Gries’ motion for summary judgment ignored “the other contractual obligations Gries owed to Johnson”— namely, Gries’ obligation to “provide services related to the construction of the” dealership “in addition to architectural services.” According to Johnson, Gries’ duties included addressing lien and warranty issues, reviewing and approving payment applications, reviewing change orders, and informing Johnson whether the alternative tile proposed was appropriate.

¶8 Johnson stated that “[i]nstead of fulfilling these obligations, … Gries attended some meetings, sent some emails, and then stopped doing anything to resolve” the tile issue or the lien. For example, Gries never “conducted any testing” of the tile flooring or attempted to “get the defective floor corrected.” Johnson alleged that it “relied on Gries to let” Johnson “know if the alternative tile proposed (and ultimately installed) … was appropriate.” Johnson alleged that Gries informed Johnson that the alternative tile was “equal but less expensive” than the original tile.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Estate of Rille Ex Rel. Rille v. Physicians Insurance Co.
2007 WI 36 (Wisconsin Supreme Court, 2007)
Racine County v. Oracular Milwaukee, Inc.
2010 WI 25 (Wisconsin Supreme Court, 2010)
Herkert v. Stauber
317 N.W.2d 834 (Wisconsin Supreme Court, 1982)
Dean Medical Center v. Frye
439 N.W.2d 633 (Court of Appeals of Wisconsin, 1989)
C.L. v. Olson
422 N.W.2d 614 (Wisconsin Supreme Court, 1988)
Yahnke v. Carson
2000 WI 74 (Wisconsin Supreme Court, 2000)
Broome v. State Department of Corrections
2010 WI App 176 (Court of Appeals of Wisconsin, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
Value Plus Flooring, LLC v. Don O. Johnson, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/value-plus-flooring-llc-v-don-o-johnson-llc-wisctapp-2025.