Henry Rawson Jr. and Susan Rawson v. Oxea Corporation, Dashiell Corporation, and Mundy Maintenance and Services LLC

557 S.W.3d 17
CourtCourt of Appeals of Texas
DecidedDecember 22, 2016
Docket01-15-01005-CV
StatusPublished
Cited by3 cases

This text of 557 S.W.3d 17 (Henry Rawson Jr. and Susan Rawson v. Oxea Corporation, Dashiell Corporation, and Mundy Maintenance and Services LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Henry Rawson Jr. and Susan Rawson v. Oxea Corporation, Dashiell Corporation, and Mundy Maintenance and Services LLC, 557 S.W.3d 17 (Tex. Ct. App. 2016).

Opinion

Opinion issued December 22, 2016

In The

Court of Appeals For The

First District of Texas ———————————— NO. 01-15-01005-CV ——————————— HENRY RAWSON JR. AND SUSAN RAWSON, Appellants V. OXEA CORPORATION, DASHIELL CORPORATION, AND MUNDY MAINTENANCE AND SERVICES LLC, Appellees

On Appeal from the 190th District Court Harris County, Texas Trial Court Case No. 2015-07842

MEMORANDUM OPINION

In this appeal, we determine whether the trial court correctly granted

summary judgment to Oxea Corporation based on the protections afforded under

Chapter 95 of the Civil Practice and Remedies Code, which shields property owners from liability to contractors, subcontractors, and their employees in certain

circumstances. The summary judgment disposed of the negligence claims brought

by Henry Rawson Jr., a contractor’s employee, who was injured while working on

Oxea’s property.1 The summary judgment also disposed of a loss-of-consortium

claim asserted by Rawson’s wife, Susan. On appeal, the Rawsons identify seven

issues, attacking different aspects of the trial court’s summary-judgment. Because

Oxea carried its summary-judgment burden of establishing that the protections of

Chapter 95 apply to Henry Rawson’s claims, and Rawson did not meet his

summary-judgment burden of offering evidence sufficient to raise a genuine issue

of material fact regarding the exception to Chapter 95’s protections, we affirm the

trial court’s judgment.

Background

Oxea owns a chemical plant in Baytown, Texas. It also owns an electrical

substation located across the road that supplies power to the plant. The chemical

plant acquired the substation from the power company in 2003. The substation is a

structure comprised of steel beams, attached to a concrete foundation, and contains

electrical equipment. The substation has two transformers: Transformer One and

Transformer Two. Each transformer supplies electricity to different parts of the

1 Rawson also sued Dashiell Corporation and Mundy Maintenance and Services LLC. After this appeal was filed, the Rawsons settled their claims with Dashiell Corporation and Mundy Maintenance. This Court granted the Rawsons’ motions to dismiss their appeal against Dashiell and Mundy Maintenance.

2 plant. Power comes into the substation through transmission lines at 138,000 volts.

The transformers then reduce the power to 12,470 volts for distribution into the

plant through other lines running from the substation. Two power lines run to the

plant from Transformer One and two lines run to the plant from Transformer Two.

On Saturday, June 9, 2012, a raccoon entered the substation and caused an

electrical short, tripping breakers and shutting off power to the part of the plant

powered by Transformer One. The short circuit also damaged two insulators in the

substation. The insulators attach bare metal electrical conductors, individually

known as a “bus” or a “bus bar,” to the steel beam support structure that runs into

the concrete foundation. The insulators also prevent electricity from flowing from

the electrically-charge busses into the steel support-beam structure and down into

the ground.

Alvin Kocurek, an Oxea employee, was called to the plant to address the

power outage. At that time, Kocurek had worked at the plant for 37 years. He was

a journeyman electrician and “point person” for the substation. It was determined

that, if power was turned back on to the plant from Transformer One without

replacing the insulators, power would flow into the substation’s steel support

structure and down to the ground, causing severe damage to the substation.

Because Oxea had a formal policy prohibiting its employees from working

on electrical equipment with a voltage exceeding 600 volts, Oxea personnel could

3 not replace the insulators. The insulators needed to be replaced by an outside

contractor with the necessary skills to work on high-voltage lines.

While waiting for the insulators to be replaced, power needed to be restored

to the entire plant. The plant had been designed so that it could be powered by

only one of the transformers. This could be accomplished by tying the electrical

lines that ran from Transformer Two to the lines inside the plant that normally

received power from Transformer One. Kocurek and a team, which included other

Oxea employees, met to devise a procedure to tie the lines together and to switch

the power from Transformer Two to energize the lines within the plant that were

normally powered by Transformer One. However, in devising the procedure, Oxea

also needed to “isolate” the work area, where the insulators would be replaced,

from the energy source. In other words, the procedure for switching the power in

the plant also needed to prevent the area where the work on the insulators would be

performed from being energized with electricity.

Kocurek prepared a hand-written procedure for switching the power from

Transformer Two to the lines inside the plant that were normally energized by

Transformer One. He also intended for the procedure to isolate the work area from

being energized on the Transformer One side where the insulators would be

replaced. In preparing the switching procedure, Kocurek consulted the plant’s

4 “one-line diagram,” which shows all the electrical circuits coming to and going

from different apparatuses in the plant.

Kocurek would later explain in his affidavit how the power switch was

accomplished:

14. The plant was designed so that, if necessary, it could run off of a single transformer. The plant had several areas that needed to be energized from Transformer No. 2 once Transformer No. 1 shut down. In order to energize these areas, it was necessary to close various switches inside of the plant to tie these areas together. This is mainly conducted through switch gear located inside of block houses.

15. Inside of the Oxea plant, we had four blockhouses. We checked the breakers in all four block houses so we could assess the condition of the plant. We determined that we would need to conduct switching at two of these block houses, the Area 2 and the VA Cooling Tower block houses. This would allow us to tie together power lines to restore electricity to the portions of the plant which had lost power. The switch gear in the block houses are sometimes referred to a “line switch.” The switch gear are housed inside of large cubicles inside of the block house that permit them to be safely operated from a handle outside of the enclosure without exposing the operator to direct contact with the switch gear mechanism or energized lines or equipment. This switch gear allowed us to switch the flow of power to different areas of the plant. . . .

....

21. In the substation, we had opened up all the knife switches located in the substructure that normally received power from the No. 1 transformer. . . .

Even though power was restored to the plant, the insulators still needed to be

replaced before Transformer One could be re-energized. Since acquiring the

substation, Oxea had used a contractor, Dashiel Corporation, and its subsidiary,

5 Dacon Corporation, to work on the high-voltage equipment at the facility. Henry

Rawson was employed by Dacon as a high-voltage lineman. When Dacon

received the request from Oxea, Rawson agreed to go to the substation to replace

the insulators.

After arriving at the substation, Kocurek reviewed with Rawson what Oxea

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
557 S.W.3d 17, Counsel Stack Legal Research, https://law.counselstack.com/opinion/henry-rawson-jr-and-susan-rawson-v-oxea-corporation-dashiell-texapp-2016.