Hemond v. Frontier Communications of America, Inc.

2015 VT 67, 123 A.3d 1176, 199 Vt. 272, 2015 Vt. 67, 2015 Vt. LEXIS 45
CourtSupreme Court of Vermont
DecidedApril 17, 2015
DocketNo. 14-236
StatusPublished
Cited by15 cases

This text of 2015 VT 67 (Hemond v. Frontier Communications of America, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hemond v. Frontier Communications of America, Inc., 2015 VT 67, 123 A.3d 1176, 199 Vt. 272, 2015 Vt. 67, 2015 Vt. LEXIS 45 (Vt. 2015).

Opinion

[274]*274¶ 1.

Reiber, C.J.

Defendant Frontier Communications of America, Inc. appeals decisions denying its cross-claims for indemnity against three codefendants, Stantec Consulting, Inc., Turner Electric Corporation, and Graybar Electric Company.1 Frontier asserts that it is entitled to implied indemnification from all three codefendants and express indemnity from Graybar, and the court erred in granting summary judgment because there are disputed questions of fact. We affirm.

¶ 2. This case stems from an electrocution injury suffered by plaintiff Michael Hemond in 2006 while employed as a lineman and operating an electrical switch on equipment owned by Frontier. The switch, known as Switch 14E, was located at an electrical substation in Richford, Vermont. The switch was installed as part of a reconstruction of the Richford substation. The plans for this upgrade included the removal of an oil-break switch and installation of an air-break switch at that location. As explained in Hemond II, 2015 VT 66, ¶ 2 n.2, Switch 14E is a unitized switch, which means it shares a common pole with Switch 14W. The switch is opened and closed using a vertical steel operating pipe. When the pipe is rotated the blades of the switch open. A switch is opened to interrupt the flow of electricity through the line. When the line is carrying a load of electricity, an electrical arc can form as electricity attempts to conduct through the air. The air-break switch is manufactured with optional insulating components, but none were installed at Switch 14E. When Mr. Hemond operated the switch, an electrical arc formed, flashed over the support structure, and electrocuted Mr. Hemond.

[275]*275¶ 3. Mr. Hemond and his wife filed suit. In addition to Frontier, the suit named several other defendants including: Stantec, a consulting firm that provided services to Frontier in connection with the reconstruction of the Richford substation; Turner, the manufacturer of the switch; and Graybar, the distributor of the switch. The suit alleged, among other things, negligence in the design, manufacture, installation, and construction of the substation, negligent selection and installation of the switch, and defective manufacture, design, and distribution of the switch.

¶ 4. As relevant to this case, Frontier filed cross-claims for implied indemnification against Stantec, Graybar, and Turner, and for express indemnification against Turner. Those codefendants filed for either dismissal or summary judgment on Frontier’s claims for indemnification. The following facts were included in Stantec’s statement of undisputed facts and not disputed by Frontier. The upgrade to the transmission lines and distribution facilities was overseen by Frontier’s employee Andy Letourneau, an electrical engineer. Mr. Letourneau was responsible for development and design as well as oversight of construction and maintenance, and safety. Michael Sullivan, another Frontier employee, assisted Mr. Letourneau. Mr. Letourneau made the decision to remove the oil-break switch at the Richford substation, and to order the Turner air-break switch without an interrupter for use. The decision to incorporate air-break switches without load interrupters was made before Stantec was hired. With respect to the Richford upgrade, Stantec was hired to provide conceptual drawings to be used before the Public Service Board (PSB) showing whether the equipment fit within spatial requirements. Stantec provided conceptual drawings and submitted them to the PSB.

¶ 5. Frontier ordered the Turner switch through its local distributor, Graybar. Mr. Sullivan filled out the switch-specification sheet from Graybar and it was transmitted to Turner. Frontier began construction on the Richford substation in July 2003. Frontier followed a standard design that it had used on two other substations.

¶ 6. Following a hearing, the court issued a written decision. The court explained that it was treating the motions to dismiss as motions for summary judgment. The court entered an order in June 2011 granting summary judgment for Stantec and Turner on Frontier’s claim of implied indemnification. In a subsequent order, [276]*276the court also granted summary judgment to Graybar on the implied-indemnity claim and to Turner on Frontier’s claim for express indemnity.2

¶ 7. Frontier filed a motion to reconsider, raising both substantive and procedural arguments. As to procedure, Frontier argued that the court violated its procedural rights by treating the motions to dismiss as motions for summary judgment without notifying the parties in advance of the changed status of the motion and giving them a reasonable opportunity to submit additional materials. See V.R.C.P. 12(c) (explaining that if matters outside pleadings are considered, motion is treated as one for summary judgment and parties are “given reasonable opportunity to present all material” relevant to motion). The court concluded that any error was harmless. The court noted that the sole fact considered by the court outside of the pleadings was that Frontier’s engineer chose the switch, and that the plaintiffs’ complaint was based on that choice. The court explained that consideration of this fact did not prejudice Frontier because Frontier did not dispute this fact, and even in its motion to reconsider, did not deny that it had previously conceded that its engineer had selected the switch. Therefore the court concluded that any failure to provide an opportunity to respond was harmless.

¶ 8. Frontier also challenged the substance of the court’s decision on the implied and express indemnity. The court denied this motion, concluding that there was no error of law. Frontier appeals these decisions.

¶ 9. We review a grant of summary judgment de novo, applying the same standard as the trial court. Progressive Cas. Ins. Co. v. MMG Ins. Co., 2014 VT 70, ¶ 10, 197 Vt. 253, 103 A.3d 899. Summary judgment will be granted where there is no genuine dispute as to any material fact and the moving party is entitled to judgment as a matter of law. V.R.C.P. 56(a). In determining whether there is a dispute of fact, this Court accepts as true the allegations made by the nonmoving party, but conclusory allegations without supporting facts are insufficient to sustain a claim for indemnity. White v. Quechee Lakes Landowners’ Ass’n, 170 Vt. 25, 28, 742 A.2d 734, 736 (1999).

[277]*277¶ 10. The court’s summary judgment decisions at issue in this appeal involve the right to indemnity. “Vermont law ordinarily bars actions for contribution between joint tortfeasors, but the right to indemnity is an exception to this rule.” Chapman v. Sparta, 167 Vt. 157, 159, 702 A.2d 132, 134 (1997) (citation omitted). A right to indemnity exists either where there is an express agreement between the parties or where indemnity can be implied due to the circumstances. Id. Frontier alleged both types of indemnity in this case.

I. Implied Indemnity

¶ 11. On appeal, Frontier first argues that the court erred in denying its claim for implied indemnification against Stantec, Turner, and Graybar.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2015 VT 67, 123 A.3d 1176, 199 Vt. 272, 2015 Vt. 67, 2015 Vt. LEXIS 45, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hemond-v-frontier-communications-of-america-inc-vt-2015.