Fairlee v. Forcier Aldrich & Associates

CourtVermont Superior Court
DecidedNovember 8, 2018
Docket211-12-17 Oecv
StatusPublished

This text of Fairlee v. Forcier Aldrich & Associates (Fairlee v. Forcier Aldrich & Associates) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fairlee v. Forcier Aldrich & Associates, (Vt. Ct. App. 2018).

Opinion

Fairlee v. Forcier Aldrich & Associates, 211-12-17 Oecv (Harris, J., Nov. 8, 2018) [The text of this Vermont trial court opinion is unofficial. It has been reformatted from the original. The accuracy of the text and the accompanying data included in the Vermont trial court opinion database is not guaranteed.]

STATE OF VERMONT SUPERIOR COURT CIVIL DIVISION Orange Unit Docket No. 211-12-17 Oecv

Town of Fairlee, Plaintiff

v.

Forcier Aldrich & Associates, Aldrich & Elliot, P.C., ENTRY ORDER Engineering Ventures, Inc, Paragon Construction, Inc., Keymont Construction, Inc., Newstress, Inc., Defendants

Factual and Procedural Background

Pending and ripe for decision before the court is a motion to dismiss filed by the Defendant Newstress, Inc. and efforts to amend the complaint, under the Town’s Motions to Amend the Compliant filed by the Town of Fairlee on February 26, 2018 and October 22, 2018. (Technically the reply briefing period on the Town’s second motion to amend has not run, but the court addresses the motion(s) to amend in this entry order for the reasons stated below). The court is not addressing the Engineering Venture’s Inc.’s motion for summary judgment at this time as the reply brief filing period has not run as this order is being finalized.

This case involves the deterioration of the roof of a concrete municipal water storage tank in Fairlee, Vermont. The relevant procedural posture of the case is as follows. The Town of Fairlee (hereinafter “Town”) filed this 13-count lawsuit against six defendants involved in various aspects of the design and construction of the water storage tank. The Town filed its Complaint on December 15, 2017. Defendant Newstress, Inc. (hereinafter “Newstress”) moved to dismiss the products liability, breach of warranty, and Consumer Protection Act (CPA) claims against it on February 12, 2018. The Town moved to amend the Complaint on February 26, 2018 by adding a negligence cause of action against Newstress and on that date filed its Opposition to Newstress’s Motion to Dismiss. Newstress replied to the Town’s Opposition on March 21, 2018 and objected to the Town’s Motion to Amend the Complaint. Although one set of Defendants1 has stated its nonobjection to the Motion to Amend the Complaint2, the motion is still opposed by the Newstress, the defendant as to whom the new proposed count is directed.

1 Forcier Aldrich & Associates, Inc. and Aldrich & Elliott, P.C. 2 It is unclear if this non-opposition was filed with respect to the Town’s first or second motion to amend the complaint. Since the party to which the proposed amendments are offered (Newstress) objects to both motions to amend, they ae taken up on the merits. As alleged in the Town’s Complaint and relevant here, the Town is a municipality located in Orange County, Vermont. Defendant Keymont Construction, Inc. (hereinafter “Keymont”) is a New Hampshire corporation located in Laconia, New Hampshire that does construction work in Vermont, which includes concrete construction work. Defendant Newstress is a New Hampshire corporation with a principal business office in Epson, New Hampshire. In 2003, the Town decided to embark on a building project which included the water storage tank that is the subject of this dispute. Defendant Paragon Construction, Inc. (hereinafter “Paragon”) was the designated general contractor for the project by written agreement dated June 11, 2003. On or about that date, Defendant Forcier Aldrich & Associates, Inc. and its successor Aldrich & Elliott, P.C. (hereinafter “Aldrich”) recommended that the Town adopt Change Order No. 1, which modified the design of the roof of the water storage tank from using cast-in-place concrete to using precast, hollow-core concrete planks and a topping layer of reinforced concrete that would go over the planks, with a resulting price reduction. Aldrich allegedly represented to the Town that the water storage tank would function for at least 75 years, even with modifications pursuant to Change Order No. 1, and the Town allegedly relied on this assertion when entering into the agreement with Paragon.

According to the Complaint, Paragon assumed responsibility for the construction of the water storage tank, but engaged subcontractors to perform certain aspects of the project. Paragon subcontracted with Keymont to construct the roof with the planks and slab. Keymont, in turn, submitted to Newstress, the plank manufacturer, certain material so that it could obtain shop drawings for the planks. Newstress submitted shop drawings and materials for the approval of the planks to Keymont, Paragon, Engineering Ventures, P.C. (hereinafter “Engineering Ventures”) and Aldrich before manufacturing the planks. Ultimately, Newstress manufactured the planks that were used to construct the water storage tank, sold, and delivered them to Keymont, and Keymont constructed the water storage tank using the planks.

According to the Complaint, construction of the roof was completed by 2004. In or around 2014, however, the Town became aware of small cracks that appeared on the exterior part of the concrete roof of the water storage tank. On or about October 1, 2014, a civil engineer, Timothy Schaal of Schaal Engineering, P.C., inspected the water storage tank roof and concluded that the defects were not a structural concern at that time. During the summer of 2015, a dive team entered the water storage tank to perform a scheduled cleaning and observe the roof. The dive team observed that sections of concrete from the underside of the roof’s planks had fallen into the water storage tank. On October 13, 2015, Mr. Schaal investigated the water storage tank a second time, this time in the presence of representatives from Aldrich and Newstress, and observed “extensive spalling” of the bottom of one plank, exposing the pre- stressed steel cables that run through the planks. The adjacent plank also showed significant cracks and sections of that plank had also started to spall. Minor to significant cracking was observed in six other planks and as a result, these planks were deemed likely to be compromised in the future. Mr. Schaal concluded that due to the planks’ condition, the water storage tank roof had failed and that a permanent repair would be required to avoid total failure if the roof collapsed, which he stated would occur. The Complaint alleges that if the water storage roof had collapsed, the water storage tank would have been unusable and caused injury to the town, including the total cessation of functioning of the Town’s water system and fire department.

The Town’s Complaint alleges three causes of action against Newstress. Count 11 asserts a breach of warranty claim against Newstress, alleging that Defendant “expressly and/or impliedly” warranted that its planks were free of defects and were merchantable and fit for the purpose for which they were going to be used, and that as a result of the planks’ failure, 2 Newstress is in breach of both express and implied warranties. Count 12 asserts a product liability claim against Newstress, alleging that the defective planks have caused, and will continue to cause, the Town to suffer serious harm. Count 13 asserts a CPA claim against Newstress, alleging that Newstress represented that the planks were acceptable and would function as intended for at least 75 years, that the Town was reasonable to rely on the representation, that the representations were false, and that the Town’s reliance on the false representations caused, or contributed to the causes of, the water storage tank’s roof failure and resulting damages.

I. Motion to Amend Complaint to Add Negligence Claim As an initial matter, the Court will address the Town’s Motions to Amend the Complaint. As noted, the Town seeks to amend the Complaint to add a negligence claim against Newstress (Count 14).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Rathe Salvage, Inc. v. R. Brown & Sons, Inc., and Brown
2012 VT 18 (Supreme Court of Vermont, 2012)
Prive v. Vermont Asbestos Group
2010 VT 2 (Supreme Court of Vermont, 2010)
EBWS, LLC v. Britly Corp.
2007 VT 37 (Supreme Court of Vermont, 2007)
BEACHWALK VILLAS COND. ASSOC. INC. v. Martin
406 S.E.2d 372 (Supreme Court of South Carolina, 1991)
Care Display, Inc. v. Didde-Glaser, Inc.
589 P.2d 599 (Supreme Court of Kansas, 1979)
Lincoln Pulp & Paper Co., Inc. v. Dravo Corp.
436 F. Supp. 262 (D. Maine, 1977)
Union School District No. 20 v. Lench
365 A.2d 508 (Supreme Court of Vermont, 1976)
Perkins v. Windsor Hospital Corp.
455 A.2d 810 (Supreme Court of Vermont, 1982)
Bevins v. King
465 A.2d 282 (Supreme Court of Vermont, 1983)
Kinney v. Goodyear Tire & Rubber Co.
367 A.2d 677 (Supreme Court of Vermont, 1976)
Paquette v. Deere and Co.
719 A.2d 410 (Supreme Court of Vermont, 1998)
University of Vermont v. W.R. Grace & Co.
565 A.2d 1354 (Supreme Court of Vermont, 1989)
Elkins v. Microsoft Corp.
817 A.2d 9 (Supreme Court of Vermont, 2002)
VT AGENCY OF NATURAL RESOURCES v. Towns
724 A.2d 1022 (Supreme Court of Vermont, 1998)
Smith v. Urethane Installations, Inc.
492 A.2d 1266 (Supreme Judicial Court of Maine, 1985)
Gochey v. Bombardier, Inc.
572 A.2d 921 (Supreme Court of Vermont, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
Fairlee v. Forcier Aldrich & Associates, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fairlee-v-forcier-aldrich-associates-vtsuperct-2018.