Heights at Issaquah Ridge Owners Ass'n v. Burton Landscape Group, Inc.
Opinion
¶1 In determining whether parties agreed to arbitrate a dispute, a court first considers whether there is a valid arbitration agreement and, if so, whether the parties’ dispute is within the scope of that agreement. Once it is determined that both criteria have been met, the court’s authority is substantially constrained and, as here, relegates questions of the timeliness of claims to the arbiter. We reverse and remand to the trial court to compel arbitration.
FACTS
¶2 Derus Wakefield I, LLC, as owner, entered into a contract (General Contract) with Sacotte Construction, Inc., to act as the general contractor for construction of a [403] condominium project, known as “Trillium Heights at Issaquah Ridge.” Sacotte in turn entered into subcontracts with Burton Landscape Group; Time to Time Construction, Inc.; The Concrete Way, Inc.; and Mark Brooks Construction, among others, to perform specified portions on the project. Each of the subcontracts incorporated the disputes provision of the General Contract, which required that all disputes be arbitrated.
¶3 The project was completed, and the owners established a homeowners association, “The Heights at Issaquah Ridge Owners Association” (Association). Thereafter, substantial defects were discovered and the Association commenced an action in King County Superior Court against Derus, the owner, on May 27, 2005. Derus filed a third-party complaint against Sacotte, the general contractor, in January 2006. On April 4, 2007, the three parties entered into a settlement agreement that included, among other things, an assignment of Derus’ claims against Sacotte to the Association and an assignment of Sacotte’s claims against the project subcontractors to the Association.
¶4 As Sacotte’s assignee, the Association sought to arbitrate the claims against the subcontractors. All but the four subcontractors named above agreed to arbitrate. The Association filed a motion to compel arbitration. The trial court denied the motion and the Association appeals.
ANALYSIS
¶5 Courts resolve the threshold legal question of arbitrability of the dispute by examining the arbitration agreement without inquiry into the merits of the dispute. If the dispute can fairly be said to invoke a claim covered by the agreement, any inquiry by the courts must end. Washington State has a strong public policy favoring arbitration [404] of disputes.1 Questions of arbitrability are reviewed de novo.2
¶6 The General Contract required that any dispute arising out of that contract be resolved by arbitration. Paragraph 4.5.1 stated, “Any controversy or Claim arising out of or related to the Contract, or the breach thereof, shall be settled by arbitration.” The General Contract further defined “claim” as
a demand or assertion by one of the parties seeking, as a matter of right, adjustment or interpretation of Contract terms, payment of money, extension of time or other relief with respect to the terms of the Contract. The term “Claim” also includes other disputes and matters in question between the Owner and Contractor arising out of or relating to the contract. Claims must be made by written notice.
Time Limits on Claims. Claims by either party must be made within 21 days after occurrence of the event giving rise to such Claim or within 21 days after the claimant first recognizes the condition giving rise to the Claim, whichever is later. Claims must be made by written notice. . . .
“Arbitration pursuant to this paragraph may be initiated by written notice by either party to the other.” Each of the subcontracts provided for resolution of disputes as set forth in the General Contract.3
¶7 The sole issue before the trial court was whether there was a valid agreement to arbitrate. RCW 7.04A-.070(1) provides in pertinent part:
[405] Unless the court finds that there is no enforceable agreement to arbitrate, it shall order the parties to arbitrate. If the court finds that there is no enforceable agreement, it may not order the parties to arbitrate.
The trial court found the 21-day notice requirement in the contract to be a “predicate requirement to enforcement and enforceability of the arbitration clause.” The court further stated that it was not ruling on the merits, but on “procedural pre-requisites.”
¶8 Washington courts apply a strong presumption in favor of arbitration. In Peninsula School District No. 401 v. Public School Employees of Peninsula, the Washington Supreme Court clearly articulated the principles of arbitrability, setting forth the limitation of a trial court’s discretion when ruling on a motion to compel arbitration:
“Although it is the court’s duty to determine whether the parties have agreed to arbitrate a particular dispute, the court cannot decide the merits of the controversy, but may determine only whether the grievant has made a claim which on its face is governed by the contract.”[4]
Any doubts should be resolved in favor of coverage, and further, all questions upon which the parties disagree are presumed to be within the arbitration provisions unless negated expressly or by clear implication. 5
¶9 Thus, whether or not time limits act as a bar to arbitration should be decided by the arbitrator as a threshold question. As noted in Yakima County Law Enforcement Officers Guild v. Yakima County.
[Qluestions of procedural arbitrability, those “concerning the procedural prerequisites to arbitration,” should be resolved by an arbitrator. . . .Footnotes
148 Wash. App. 400 (Heights at Issaquah Ridge Owners Ass'n v. Burton Landscape Group, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Related
Ask about Heights at Issaquah Ridge Owners Ass'n v. Burton Landscape Group, Inc. — and the 37 cases citing it.
Two-minute setup · Revoke anytime