Heights at Issaquah Ridge Owners Ass'n v. Burton Landscape Group, Inc.

148 Wash. App. 400
CourtCourt of Appeals of Washington
DecidedJanuary 20, 2009
DocketNo. 61604-8-I
StatusPublished
Cited by37 cases

This text of 148 Wash. App. 400 (Heights at Issaquah Ridge Owners Ass'n v. Burton Landscape Group, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Heights at Issaquah Ridge Owners Ass'n v. Burton Landscape Group, Inc., 148 Wash. App. 400 (Wash. Ct. App. 2009).

Opinion

Grosse, J.

¶1 In determining whether parties agreed to arbitrate a dispute, a court first considers whether there is a valid arbitration agreement and, if so, whether the parties’ dispute is within the scope of that agreement. Once it is determined that both criteria have been met, the court’s authority is substantially constrained and, as here, relegates questions of the timeliness of claims to the arbiter. We reverse and remand to the trial court to compel arbitration.

FACTS

¶2 Derus Wakefield I, LLC, as owner, entered into a contract (General Contract) with Sacotte Construction, Inc., to act as the general contractor for construction of a [403]*403condominium project, known as “Trillium Heights at Issaquah Ridge.” Sacotte in turn entered into subcontracts with Burton Landscape Group; Time to Time Construction, Inc.; The Concrete Way, Inc.; and Mark Brooks Construction, among others, to perform specified portions on the project. Each of the subcontracts incorporated the disputes provision of the General Contract, which required that all disputes be arbitrated.

¶3 The project was completed, and the owners established a homeowners association, “The Heights at Issaquah Ridge Owners Association” (Association). Thereafter, substantial defects were discovered and the Association commenced an action in King County Superior Court against Derus, the owner, on May 27, 2005. Derus filed a third-party complaint against Sacotte, the general contractor, in January 2006. On April 4, 2007, the three parties entered into a settlement agreement that included, among other things, an assignment of Derus’ claims against Sacotte to the Association and an assignment of Sacotte’s claims against the project subcontractors to the Association.

¶4 As Sacotte’s assignee, the Association sought to arbitrate the claims against the subcontractors. All but the four subcontractors named above agreed to arbitrate. The Association filed a motion to compel arbitration. The trial court denied the motion and the Association appeals.

ANALYSIS

¶5 Courts resolve the threshold legal question of arbitrability of the dispute by examining the arbitration agreement without inquiry into the merits of the dispute. If the dispute can fairly be said to invoke a claim covered by the agreement, any inquiry by the courts must end. Washington State has a strong public policy favoring arbitration [404]*404of disputes.1 Questions of arbitrability are reviewed de novo.2

¶6 The General Contract required that any dispute arising out of that contract be resolved by arbitration. Paragraph 4.5.1 stated, “Any controversy or Claim arising out of or related to the Contract, or the breach thereof, shall be settled by arbitration.” The General Contract further defined “claim” as

a demand or assertion by one of the parties seeking, as a matter of right, adjustment or interpretation of Contract terms, payment of money, extension of time or other relief with respect to the terms of the Contract. The term “Claim” also includes other disputes and matters in question between the Owner and Contractor arising out of or relating to the contract. Claims must be made by written notice.
Time Limits on Claims. Claims by either party must be made within 21 days after occurrence of the event giving rise to such Claim or within 21 days after the claimant first recognizes the condition giving rise to the Claim, whichever is later. Claims must be made by written notice. . . .

“Arbitration pursuant to this paragraph may be initiated by written notice by either party to the other.” Each of the subcontracts provided for resolution of disputes as set forth in the General Contract.3

¶7 The sole issue before the trial court was whether there was a valid agreement to arbitrate. RCW 7.04A-.070(1) provides in pertinent part:

[405]*405Unless the court finds that there is no enforceable agreement to arbitrate, it shall order the parties to arbitrate. If the court finds that there is no enforceable agreement, it may not order the parties to arbitrate.

The trial court found the 21-day notice requirement in the contract to be a “predicate requirement to enforcement and enforceability of the arbitration clause.” The court further stated that it was not ruling on the merits, but on “procedural pre-requisites.”

¶8 Washington courts apply a strong presumption in favor of arbitration. In Peninsula School District No. 401 v. Public School Employees of Peninsula, the Washington Supreme Court clearly articulated the principles of arbitrability, setting forth the limitation of a trial court’s discretion when ruling on a motion to compel arbitration:

“Although it is the court’s duty to determine whether the parties have agreed to arbitrate a particular dispute, the court cannot decide the merits of the controversy, but may determine only whether the grievant has made a claim which on its face is governed by the contract.”[4]

Any doubts should be resolved in favor of coverage, and further, all questions upon which the parties disagree are presumed to be within the arbitration provisions unless negated expressly or by clear implication. 5

¶9 Thus, whether or not time limits act as a bar to arbitration should be decided by the arbitrator as a threshold question. As noted in Yakima County Law Enforcement Officers Guild v. Yakima County.

[Qluestions of procedural arbitrability, those “concerning the procedural prerequisites to arbitration,” should be resolved by an arbitrator. . . .
[406]*406The arbitrator should decide “allegation of waiver, delay, or a like defense to arbitrability.”[7]

flO Federal courts have also interpreted time limits within which to bring a claim to arbitration to be under the purview of the arbitrator. In an action where a contractor sought arbitration of its dispute with a hospital, the United States Supreme Court in Moses H. Cone Memorial Hospital v. Mercury Construction Corp. held as a matter of law:

[A]ny doubts concerning the scope of arbitrable issues should be resolved in favor of arbitration, whether the problem at hand is the construction of the contract language itself or an allegation of waiver, delay, or a like defense to arbitrability.[8]

¶11 Similarly, in Howsam v. Dean Witter Reynolds, Inc., the contract required a demand for arbitration be made within six years of the date of occurrence.9 There, the court held the limitation to be an issue of procedural arbitrability for the arbitrator to decide rather than one of substantive arbitrability for the court.10

¶12 The arbitration clause found in the parties’ contract is broad and encompasses those claims pleaded here by the Association.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Baionne Coleman, V. Impact Public Schools
Court of Appeals of Washington, 2024
Faten Anwar, V. Exam Master, Corp.
Court of Appeals of Washington, 2023
Joel Berman, V. Tierra Real Estate Group, Llc
Court of Appeals of Washington, 2022
Key Bank, V. Ginger Atherton
Court of Appeals of Washington, 2022
Htp, Inc. v. Jc Aviation Investments, Llc
Court of Appeals of Washington, 2021
Midtown Limited Partnership v. Thomas F. Bangasser
Court of Appeals of Washington, 2020
Estate Of Dr. Michael Romney v. Franciscan Medical Group
199 Wash. App. 589 (Court of Appeals of Washington, 2017)
Terence Butler v. Randall Thomsen
Court of Appeals of Washington, 2016
Brinkley v. Monterey Financial Services, Inc.
242 Cal. App. 4th 294 (California Court of Appeal, 2015)
Brinkley v. Monterey Fin. Servs., Inc.
196 Cal. Rptr. 3d 1 (California Court of Appeals, 4th District, 2015)
Naumes, Inc. v. City Of Chelan
Court of Appeals of Washington, 2014
Longwell Arbors, Llc v. Cpi Pool Funding
Court of Appeals of Washington, 2014

Cite This Page — Counsel Stack

Bluebook (online)
148 Wash. App. 400, Counsel Stack Legal Research, https://law.counselstack.com/opinion/heights-at-issaquah-ridge-owners-assn-v-burton-landscape-group-inc-washctapp-2009.