Heckaman v. Northern Pacific Railway Co.

20 P.2d 258, 93 Mont. 363, 1933 Mont. LEXIS 29
CourtMontana Supreme Court
DecidedJanuary 30, 1933
DocketNo. 6,963.
StatusPublished
Cited by38 cases

This text of 20 P.2d 258 (Heckaman v. Northern Pacific Railway Co.) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Heckaman v. Northern Pacific Railway Co., 20 P.2d 258, 93 Mont. 363, 1933 Mont. LEXIS 29 (Mo. 1933).

Opinion

*372 MR. JUSTICE MATTHEWS

delivered the opinion of the court.

Appeal from a judgment awarding M. C. Heckaman damages for losses suffered when, on June 7, 1929, his place of business in Wibaux was flooded by reason, as he alleges, of the insufficiency of the openings in the embankment maintained by the Northern Pacific Railway Company, to permit the passage of the flood waters of Beaver Creek.

The Northern Pacific Railroad was built through eastern Montana in 1880, and passes through Wibaux from east to west crossing Beaver Creek at right angles within the corporate limits. The stream, normally but 3 or 4 feet in width, flows from south to north through a channel capable of carrying a large volume of water and defined by banks approximately 5 feet above the level of the center of the stream, on each side of which are benches gradually, rising to an elevation of about 5 feet higher than the banks of the present channel. The town is built upon ground approximately 15' feet above the center of the channel of the stream, whose valley is 4,000 feet in width. To the west of the town the ground rises sharply to form what is known as Beaver Hill.

Beaver Creek drains an area of 342 square miles above Wibaux and in this area has approximately twenty tributaries; this area is hilly, broken, practically barren of trees, dry and arid, and, consequently, is subject to torrential rains locally known as “cloudbursts.”

•Starting at the eastern edge of the valley the railroad embankment was constructed on an upgrade to’ cross Beaver Hill without tunneling, and, where it intersects the channel *373 of Beaver Creek, it had an elevation of nearly 15 feet; here a “pile trestle,” 137.4 feet long, was constructed, not necessarily because of the necessities of the stream, but rather for economy and speed in completing the line.

• In 1884 the central piles were removed for a space of 44 feet and a “Howe Truss Span” installed, at which time the track was raised about 3 feet to lessen the grade at Beaver Hill. In 1896 this span was replaced by a 70-foot steel bridge with 20-foot approaches, all set on concrete piers, and by 1898 the space, diagonally, from the bottom of the bridge piers to the top of the approach piers was filled in and the surface “rip-rapped” and the spaces under the trestle to the east and west were filled in solid. Thus, since 1898 the embankment crossing the stream has been pierced by an opening 65 feet in width at the bottom, and something over a hundred feet in width at the top, and 15 to 20 feet in height.

In 1912, on demand of the citizens of Wibaux for relief from the danger of a grade street crossing, the defendant constructed a viaduct on Wibaux iStreet, the main street of the town, 35 feet wide at the bottom and 70 feet wide at the top, the roadbed of which was 9 feet above the level of the center of the channel of Beaver Creek. While not intended for that purpose, the viaduct formed a spillway for flood waters not accommodated by the bridge opening.

During the early morning hours of June 7, 1929, the watershed of Beaver Creek suffered four or five practically simultaneous “cloudbursts” at points ranging from 5 to 25 miles above Wibaux; the ensuing flood swept away fences and buildings, destroyed a vast amount of property, and drove families from their homes. At points far above Wibaux the flood came down Beaver Creek in a veritable “wall of water.” At a point a mile and a half above the town, the stream head was 2,040 feet wide and 13 feet deep at the center.

The openings in the embankment were insufficient to permit this vast amount of water to pass down the channel; reaching the embankment it steadily rose until 4 or 5 feet deep in the viaduct, and finally inundated the town. 'The floor of plaintiff’s place of business was 15 feet above the bottom *374 of the creek channel; the flood waters stood more than 5 feet deep in the building. This condition was not relieved until six hours later when the pressure of the water carried away large sections of the embankment and it passed down the channel; the surface of the water then sank “like an elevator going down.”

Figuring the volume of water at a cross-section above the town and a like cross-section at plaintiff’s building, an expert for the defendant declared that, had no embankment existed, the water would have stood 18 inches in plaintiff’s building, thus conceding that the water was raised more than 3% feet by reason of the maintenance of the embankment.

The complaint alleges that in May and June of almost every year, to the knowledge of the defendant, Beaver Creek rose in its flow and volume to several thousand times its usual flow and would usually rise “right to its flood plane, i. e. the valley level at Wibaux,” and that, in the exercise of reasonable prudence, the defendant would have known, and did know, that, in all human probability, a flood the size of that which did occur, would come; that the bridge opening was reduced less than the width of the ordinary channel of the stream and was insufficient to permit the free flow of water “in ordinary seasonably recurring high water ’ ’; and that, on determining these facts, it was the duty of the defendant to widen the opening, which duty it failed to perform.

The defendant interposed three defenses: That, as the embankment had existed since 1898 in the condition it was in at the time of the damage, the negligence charged dated back to the time of construction, and plaintiff’s action was barred by the statute of limitations; that, as plaintiff acquired his property with knowledge of the existence of the embankment, he cannot recover; and, third, that the flood of 1929, was unprecedented, an act of God, for which defendant could not be held liable.

These questions were urged on motion for judgment of non-suit, on motion for a directed verdict, and on motion for a new trial, and are here presented by proper assignments of error.

*375 1. The solution to the first and second questions is found in the answer to the question, When did plaintiff’s cause of action accrue?

The time when a cause of action for injury to real property is deemed to accrue becomes material in two connections: First, as bearing upon a right to bring the action where a change of ownership by sale or devolution intervenes between the cause and the effect; and, second, as fixing the point from which the statute of limitations is to be measured, the principle in both classes of cases being, of course, identical. If the cause of action accrued upon the construction of the embankment and bridge, it was because some damage then resulted to the land therefrom, and it follows that then the plaintiff took the land in its damaged condition and at its depreciated value. (5 L. R. A. (n. s.) 379, note; and see Briggs v. Great Northern Ry. Co., 92 Mont. 463, 15 Pac. (2d) 840.) If no cause of action arose upon the construction, it was because the land was not then damaged, and, hence the plaintiff took it free from any right of the defendant to invade his legal rights in the property. (New York, C. & St. L. R. Co. v. Hamlet Hay Co., 149 Ind. 344, 47 N. E. 1060, 1061, 49 N. E. 269.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ritland v. Rowe
861 P.2d 175 (Montana Supreme Court, 1993)
Barrett v. Holland & Hart
845 P.2d 714 (Montana Supreme Court, 1992)
Rouse v. Anaconda-Deer Lodge County
817 P.2d 690 (Montana Supreme Court, 1991)
Northern Montana Hospital v. Knight
811 P.2d 1276 (Montana Supreme Court, 1991)
Shupak v. New York Life Insurance
780 F. Supp. 1328 (D. Montana, 1991)
Thayer v. Hicks
793 P.2d 784 (Montana Supreme Court, 1990)
Kitchen Krafters, Inc. v. Eastside Bank
789 P.2d 567 (Montana Supreme Court, 1990)
E.W. v. D.C.H.
754 P.2d 816 (Montana Supreme Court, 1988)
Blasdel v. Montana Power Co.
640 P.2d 889 (Montana Supreme Court, 1982)
Walton v. City of Bozeman
588 P.2d 518 (Montana Supreme Court, 1978)
Deeds v. United States
306 F. Supp. 348 (D. Montana, 1969)
Dutton v. Rocky Mountain Phosphates
438 P.2d 674 (Montana Supreme Court, 1968)
Johnson v. St. Patrick's Hospital
417 P.2d 469 (Montana Supreme Court, 1966)
Harrer v. Northern Pacific Railway Company
410 P.2d 713 (Montana Supreme Court, 1966)
Vaughn v. Langmack
390 P.2d 142 (Oregon Supreme Court, 1964)
Richland County v. Anderson
291 P.2d 267 (Montana Supreme Court, 1955)
Meine v. Ferris
247 P.2d 195 (Montana Supreme Court, 1952)
Charvoz v. Bonneville Irr. Dist.
235 P.2d 780 (Utah Supreme Court, 1951)
Doney v. Beatty
220 P.2d 77 (Montana Supreme Court, 1950)

Cite This Page — Counsel Stack

Bluebook (online)
20 P.2d 258, 93 Mont. 363, 1933 Mont. LEXIS 29, Counsel Stack Legal Research, https://law.counselstack.com/opinion/heckaman-v-northern-pacific-railway-co-mont-1933.