Hawk Isolutions Group, Inc. v. Morris

288 S.W.3d 758, 2009 Mo. App. LEXIS 641, 2009 WL 1375696
CourtMissouri Court of Appeals
DecidedMay 19, 2009
DocketED 91409
StatusPublished
Cited by9 cases

This text of 288 S.W.3d 758 (Hawk Isolutions Group, Inc. v. Morris) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hawk Isolutions Group, Inc. v. Morris, 288 S.W.3d 758, 2009 Mo. App. LEXIS 641, 2009 WL 1375696 (Mo. Ct. App. 2009).

Opinion

OPINION

GLENN A. NORTON, Judge.

Hawk iSolutions Group, Inc. (“Plaintiff’) appeals the judgment awarding it $14,459.65 for services performed under a contract with Aliona Morris (“Defendant”). 1 Plaintiff argues that the trial court erred in awarding the amount prayed for in its original petition rather than the amount requested in its amended petition. Plaintiff also argues that the trial court erred in failing to award prejudgment interest. We reverse and remand with instructions.

I. BACKGROUND

Plaintiff is in the business of providing computer and information technology products, software, and associated on-going support services to its customers. In November 2006, Plaintiff and Defendant entered into a contract to provide Defendant with computer equipment, products and services, including installation services. The total contract amount for the equipment, products, and fifty pre-paid service hours totaled $46,215.00. Defendant does not dispute that Plaintiff performed all of its obligations under the contract by December 15, 2006. Defendant also does not dispute that she asked Plaintiff to perform additional services, such as repairs and website registration. The total cost of all services provided to Defendant was $51,896.74.

According to the contract, Defendant agreed to pay Plaintiff 50% of the contract price as a down payment, 25% of the price after delivery of the equipment and the remaining 25% when Plaintiff completed installation. Defendant paid $21,482.50 to Plaintiff upon signing the contract. She paid an additional $10,000.00 on December 5, 2006. She made several other small payments over the next five months, leaving an unpaid balance of $20,141.39.

Plaintiff filed a petition against Defendant claiming breach of contract and quantum meruit on August 15, 2007. It was allowed to file an amended petition restating the same claims on December 17, 2007. The amended petition prayed for $20,141.39 plus interest at the statutory rate of 9% from January 15, 2007. Plaintiffs original petition only requested judgment in the amount of $14,459.65 plus prejudgment interest. In particular, the original petition did not request amounts owed based on the additional services Plaintiff performed in response to Defendant’s requests.

During the bench trial on Plaintiffs claims, in addition to testimony on the issue of amounts owed, Plaintiff presented and the trial court admitted into evidence several exhibits. In particular, the trial court admitted Plaintiffs Exhibit B, a spreadsheet listing amounts owed under the contract and for the additional services Defendant requested. When presenting *761 her defense, Defendant, acting pro se, asked Plaintiffs witness why the amount changed from the original petition. The trial court sustained Plaintiffs objection to Defendant’s question, stating that the parties should “deal with the petition as amended.” The court also told Defendant that she could not refer to the “old petition.” The only evidence offered at trial of a figure similar to $14,459.65 came from Exhibit B, which listed the amount owed under the original contract (not including the additional services requested by Defendant) as $14,570.14.

When Defendant testified on her own behalf, she stated that she agreed she owed Plaintiff money, and she believed she owed about $10,000.00. She did not make any claims that Plaintiff was not entitled to payment. Rather, she explained that she wanted to negotiate with Plaintiff so that she can pay what she owes.

In its judgment in favor of Plaintiff, the trial court awarded Plaintiff $14,459.65 and did not address Plaintiffs request for prejudgment interest. The trial court denied Plaintiffs motion to amend, alter or clarify the court’s judgment to change the award to the amount prayed for in its amended petition and to add prejudgment interest. This appeal follows.

II. DISCUSSION

A. Standard of Review

We review the judgment in a bench-tried case under the principles set forth in Murphy v. Carron, 536 S.W.2d 30, 32 (Mo.banc 1976). Heskett v. Director of Revenue, 62 S.W.3d 103, 105 (Mo.App. S.D.2001). We will affirm the trial court’s judgment unless there is no substantial evidence to support it, it is against the weight of the evidence, or it erroneously declares or applies the law. Murphy, 536 S.W.2d at 32.

B. The Trial Court Erred in Awarding the Amount Prayed For in Plaintiffs Original Petition Rather than the Amount Prayed For in Plaintiffs Amended Petition

In its first point, Plaintiff argues that the trial court erred in only awarding the amount prayed for in its original petition ($14,459.65) rather than the amount prayed for in its amended petition ($20,-141.39). We agree.

Neither party disputes that Plaintiff is entitled to at least $14,459.65, which appears to represent the amount owed under the contract. 2 As to the additional services, Defendant presented no evidence disputing Plaintiffs evidence that she requested and Plaintiff performed the services. To recover on a theory of quantum meruit, a plaintiff must plead and prove “that it provided to defendant materials or services at the request or with the acquiescence of defendant, that those materials or services had a certain reasonable value, and that defendant despite demands of plaintiff, has failed and refused to pay the reasonable value of those materials and labor.” Berra v. Papin Builders, Inc., 706 S.W.2d 70, 73 (Mo.App. E.D.1986).

Here, the record demonstrates that Plaintiff proved the following: (1) it provided additional services to Defendant at Defendant’s request; (2) the additional services had a certain reasonable value of $5,571.25; (3) it made a demand on Defendant for payment for the services; and (4) Defendant failed and refused to pay the reasonable value of the services. Because *762 the trial court’s judgment does not include the value of the additional services, the award of only $14,459.65 is against the weight of the evidence.

In addition, Plaintiff is correct in arguing that generally, “an amendment to a pleading abandons any prior pleadings not referred to or incorporated into the new pleading.” Beckmann v. Miceli Homes, Inc., 45 S.W.3d 533, 543 (Mo.App. E.D.2001). 3 Since an amended pleading supersedes the pleading which preceded it, “an abandoned pleading is not considered for any purpose in the case; it becomes a mere ‘scrap of paper’ insofar as the case is concerned.” Value Lumber Co. v. Jelten, 175 S.W.3d 708, 713 (Mo.App. S.D.2005) (internal citations omitted).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carmed 45, LLC v. Wesley Adam Huff
Missouri Court of Appeals, 2021
Dave McNeill v. City of Kansas City, MO
459 S.W.3d 509 (Missouri Court of Appeals, 2015)
Village of Big Lake v. BNSF Railway Co.
433 S.W.3d 460 (Missouri Court of Appeals, 2014)
Comens v. SSM St. Charles Clinic Medical Group, Inc.
335 S.W.3d 76 (Missouri Court of Appeals, 2011)
Mitchell v. Residential Funding Corp.
334 S.W.3d 477 (Missouri Court of Appeals, 2011)
Koppe v. Campbell
318 S.W.3d 233 (Missouri Court of Appeals, 2010)
Johnson v. Larson
2010 SD 20 (South Dakota Supreme Court, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
288 S.W.3d 758, 2009 Mo. App. LEXIS 641, 2009 WL 1375696, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hawk-isolutions-group-inc-v-morris-moctapp-2009.