Hartford Fire Insurance Co. v. Westinghouse Electric Corp.

450 N.W.2d 183, 1990 Minn. App. LEXIS 32, 1990 WL 1701
CourtCourt of Appeals of Minnesota
DecidedJanuary 16, 1990
DocketC0-89-1032
StatusPublished
Cited by11 cases

This text of 450 N.W.2d 183 (Hartford Fire Insurance Co. v. Westinghouse Electric Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hartford Fire Insurance Co. v. Westinghouse Electric Corp., 450 N.W.2d 183, 1990 Minn. App. LEXIS 32, 1990 WL 1701 (Mich. Ct. App. 1990).

Opinion

OPINION

CRIPPEN, Judge.

Applying the statute of limitations on real property improvements, the trial court granted summary judgment for all respondents in a suit to recover damages arising from a December 1983 generator explosion. We affirm as to causes of action connected with alleged design defects of the generator, installed in 1968, but reverse respecting causes connected with generator seal repairs in 1983.

FACTS

In 1968 respondent Westinghouse Electric Corporation (Westinghouse) designed and built a 200 ton generator for Northern States Power (NSP) at its Stillwater plant. The generator is permanently affixed to a separate foundation at 75 different points; it is housed in a separate building with three levels of access.

In June 1983, the generator’s blower fan malfunctioned, damaging various generator components. Westinghouse performed an inspection, did some repairs, recommended replacement of a neoprene rubber seal connected with the blower fan, and provided specifications for the seal. NSP ordered neoprene rubber for the seal, milled the rubber according to the specifications, and installed the seal. In December 1983, the rubber seal ruptured, causing catastrophic damage to the generator.

Several months later, NSP discovered that the rubber used for the replacement seal was Buna-S, rather than the more resistant neoprene rubber specified by Westinghouse. In the summer of 1987, NSP’s fire insurer, appellant Hartford Fire Insurance Company, commenced this action to recover claims paid to NSP. Appellant sued Westinghouse, NSP’s rubber supplier, Midwest Rubber and Supply Service Company, and Midwest’s rubber suppliers.

Regardless of when a defective real property. improvement is discovered, a cause of action must be commenced within seventeen years after substantial completion of the improvement. Minn.Stat. § 541.051, subd. 1 and 2 (1984). 1 Because the action was commenced approximately 19 years after the generator was installed, the trial court granted summary judgment on counts 1 through 3 of the complaint regarding design defects of the 1968 installation. Counts 4 through 7 of the complaint state causes of action against Westinghouse related to its conduct in 1983. Counts 8 through 15 state related causes of action against Midwest and their suppliers. The court concluded that the 1983 work on the generator constituted an improvement to real property requiring commencement of a suit within two years after discovery of a defect in the improvement. Minn.Stat. § 541.051,' subd. 1 (1986). Appellant challenges both of the trial court’s limitation decisions.

ISSUES

1. Does the 1968 installation of the generator constitute an improvement to real property?

2. Does the 1983 installation of a generator seal constitute an improvement to real property?

ANALYSIS

1. The 1968 installation.

There are two ingredients to an improvement to real property: 1) perma *186 nence and 2) an increase in usefulness or capital value. Kloster-Madsen, Inc. v. Tafi’s Inc., 303 Minn. 59, 63, 226 N.W.2d 603, 607 (1975). Under this test, permanently affixed items of equipment, including their component parts, are improvements to real property. See, e.g., Sartori v. Harnischfeger Corp., 432 N.W.2d 448 (Minn.1988) (70 ton removable crane); Pacific Indem. Co. v. Thompson-Yaeger, Inc., 260 N.W.2d 548 (1977) (installation of a furnace); Thorp v. Price Bros. Co., 441 N.W.2d 817 (Minn.Ct.App.1989) (movable plant equipment, here a concrete molding machine), pet. for rev. denied (Minn. Aug. 15, 1989); Farnham v. Nasby Agri-Sys-tems, Inc., 437 N.W.2d 759 (Minn.Ct.App. 1989) (removable pipes in grain handling system); Citizens Sec. Mut. Ins. Co. of Red Wing v. General Elec. Corp., 394 N.W.2d 167 (Minn.Ct.App.1986) (electrical component of light fixtures), pet. for rev. denied (Minn. Nov. 26, 1986); Kemp v. Allis-Chalmers Corp., 390 N.W.2d 848 (Minn.Ct.App.1986) (electrical cables running into electrical starter compartment); and Lovgren v. Peoples Elec. Co., Inc., 368 N.W.2d 16 (Minn.Ct.App.1985) (electrical transformer vault), reversed on other grounds, 380 N.W.2d 791 (Minn.1986). Cf. Massie v. City of Duluth, 425 N.W.2d 858 (Minn.Ct.App.1988) (water slide removed every winter for storage not a real property improvement), pet. for rev. denied (Minn. Sept. 16, 1988). These precedents confirm the trial court’s decision that causes connected with the 1968 installation are time barred.

Appellant contends that prior decisions like Sartori are distinguishable here, because of evidence that the generator had a limited useful life of 30 years. This suggested distinction has no merit. Finite life is an inherent characteristic of the crane in Sartori and other permanently affixed equipment or fixtures previously found to constitute improvements to real property. At least on evidence of a 30 year useful life, we are not dealing with a fixture with so short a life as to defy the notion of permanence. See Thorp, 441 N.W.2d at 820 (useful life not a factor to consider when determining whether a machine or system constitutes an improvement to real property).

Appellant further argues that application of the statute to the 1968 generator installation defies equal protection of the law because installers of unattached machinery would not be protected by the statute of limitations. The supreme court has said that corrective amendments to section 541.051 “close[d] the door to objection to the statute on equal protection grounds.” Calder v. City of Crystal, 318 N.W.2d 838, 843 (Minn.1982). See also, Sartori, 432 N.W.2d at 453-54 (upholding the statute on a due process challenge). It is not our prerogative to question these settled matters of law.

Respondent Westinghouse contends that a cause of action arising out of the 1968 installation is precluded by a limitation in the original contract for sale of the generator or by the four year statute of limitations for breach of sales contracts contained in UCC section 336.2-725.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brude v. Breen
2017 SD 46 (South Dakota Supreme Court, 2017)
Allianz Insurance Co. v. PM Services of Eden Prairie, Inc.
691 N.W.2d 79 (Court of Appeals of Minnesota, 2005)
Merritt v. Mendel
690 N.W.2d 570 (Court of Appeals of Minnesota, 2005)
Pereira v. Rheem Manufacturing Co.
5 Mass. L. Rptr. 477 (Massachusetts Superior Court, 1996)
Williams v. Tweed
520 N.W.2d 515 (Court of Appeals of Minnesota, 1994)
Anderson Ex Rel. Anderson v. City of Coon Rapids
491 N.W.2d 917 (Court of Appeals of Minnesota, 1992)
Horvath v. Liquid Controls Corp.
455 N.W.2d 60 (Court of Appeals of Minnesota, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
450 N.W.2d 183, 1990 Minn. App. LEXIS 32, 1990 WL 1701, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hartford-fire-insurance-co-v-westinghouse-electric-corp-minnctapp-1990.