Brude v. Breen

2017 SD 46
CourtSouth Dakota Supreme Court
DecidedAugust 2, 2017
StatusPublished

This text of 2017 SD 46 (Brude v. Breen) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brude v. Breen, 2017 SD 46 (S.D. 2017).

Opinion

#28064-r-GAS 2017 S.D. 46

IN THE SUPREME COURT OF THE STATE OF SOUTH DAKOTA

**** SUZANNE BRUDE, Plaintiff and Appellant,

v.

SHANE BREEN d/b/a YELLOW JACKET IRRIGATION AND LANDSCAPING, Defendant, Third-Party Plaintiff, and Appellee, v.

GREGORY AND ELIZABETH JAMISON, Third-Party Defendants.

**** APPEAL FROM THE CIRCUIT COURT OF THE SECOND JUDICIAL CIRCUIT MINNEHAHA COUNTY, SOUTH DAKOTA

****

THE HONORABLE JOHN R. PEKAS Judge ****

RONALD A. PARSONS, JR. STEVEN M. JOHNSON KIMBERLY J. LANHAM of Johnson Janklow Abdallah Reiter & Parsons LLP Sioux Falls, South Dakota Attorneys for appellant.

MELANIE L. CARPENTER JORDAN J. FEIST of Woods, Fuller, Shultz and Smith, PC Sioux Falls, South Dakota Attorneys for appellee.

ARGUED MAY 30, 2017 OPINION FILED 08/02/17 #28064

SEVERSON, Justice

[¶1.] Suzanne Brude brought suit against Shane Breen, doing business as

Yellow Jacket Irrigation and Landscaping (Yellow Jacket), for negligence in

constructing a retaining wall from which Brude suffered an injury. Yellow Jacket

moved for summary judgment, asserting that the claim was barred by the statute of

repose. The circuit court granted summary judgment in favor of Yellow Jacket.

Brude appeals, asserting that the court erred because the ten-year limitation in the

statute of repose had not expired. We reverse and remand.

Background

[¶2.] In 2005, Yellow Jacket Irrigation and Landscaping contracted for and

completed a landscaping project at the residence of Greg and Elizabeth Jamison. At

issue in this case is landscaping that Yellow Jacket originally completed in

September 2005. The area of landscaping at issue includes a patio with retaining

walls on its sides and a fire pit above a section of the retaining wall. The retaining

walls were repaired in 2007. At that time, Yellow Jacket fixed some stone pavers

that had settled and shifted. The Jamisons and Breen have different recollections

of the next time that Yellow Jacket worked on the retaining wall; it was either 2011

or 2013. The Jamisons asked Yellow Jacket to fix their patio area because some of

the landscaping stones settled and leaned. Greg Jamison testified in his deposition

that because the fix was fairly extensive and would require the retaining walls to be

torn down and rebuilt, the Jamisons asked Yellow Jacket to make the fire pit area a

little larger at the same time.

-1- #28064

[¶3.] Suzanne Brude was at the Jamison residence on October 7, 2014. In

order to retrieve some branches from the fire pit area, she stepped onto the portion

of the retaining wall in front of the Jamison’s fire pit. One of the capstones she

stepped on gave way, and she fell onto the patio below. She suffered an injury that

required surgery the next day. On November 6, 2015, Brude commenced this action

against Shane Breen, the sole proprietor operating Yellow Jacket Irrigation and

Landscaping. Yellow Jacket filed a third-party complaint against the Jamisons,

contending that the Jamisons were responsible for any damages awarded to Brude.

The Jamisons have since settled this matter and take no position in this appeal.

[¶4.] On July 29, 2016, Yellow Jacket moved for summary judgment

asserting that the statutory time period to bring a claim had expired because the

retaining wall and fire pit had been substantially completed more than ten years

prior to the commencement of this action. See SDCL 15-2A-3. After submissions by

the parties and a hearing on the motion, the circuit court granted summary

judgment for Yellow Jacket. Brude appeals raising one issue for our review. She

asserts that the changes to the landscaping that occurred in either 2011 or 2013

constituted “an improvement to real property” under SDCL 15-2A-3 and therefore

restarted the ten-year period to bring a claim. Thus, she claims that the court erred

when it granted summary judgment.

Standard of Review

[¶5.] “In reviewing a grant or denial of summary judgment we must

determine whether the moving party demonstrated the absence of any genuine

issue of material fact and established entitlement to judgment on the merits as a

-2- #28064

matter of law.” Clark Cty. v. Sioux Equip. Corp., 2008 S.D. 60, ¶ 8, 753 N.W.2d 406,

409 (quoting Behrens v. Wedmore, 2005 S.D. 79, ¶ 18, 698 N.W.2d 555, 565).

“Those resisting summary judgment must show that they will be able to place

sufficient evidence in the record at trial to support findings on all the elements on

which they have the burden of proof.” Id. (quoting Bordeaux v. Shannon Cty. Sch.,

2005 S.D. 117, ¶ 14, 707 N.W.2d 123, 127). We must determine the applicability of

the statute of repose to Yellow Jacket’s latest work on the retaining wall. “Because

the application of a legal test to the historical facts of this case requires us to

consider legal concepts and ‘exercise judgment about the values that animate legal

principles,’ we review the . . . determination de novo.” Id. ¶ 10, 753 N.W.2d at 410

(quoting In re Dorsey & Whitney Tr. Co., 2001 S.D. 35, ¶ 6, 623 N.W.2d 468, 471).

Analysis

[¶6.] A statute of repose is an affirmative defense, and Yellow Jacket had

the initial burden of proving entitlement to it. See id. ¶ 17, 753 N.W.2d at 412.

“[W]here a defendant, by motion for summary judgment, asserts this type of

affirmative defense that bars an action ‘and presumptively establishes the defense

by showing the case was instituted beyond the statutory period, the burden then

shifts to the plaintiff to establish the existence of material facts in avoidance of the

statute.’” Id. (quoting Conway v. Conway, 487 N.W.2d 21, 23 (S.D. 1992)). The

statute of repose at issue, SDCL 15-2A-3, provides:

No action to recover damages for any injury to real or personal property, for personal injury or death arising out of any deficiency in the design, planning, supervision, inspection, and observation of construction, or construction, of an improvement to real property, nor any action for contribution or indemnity for damages sustained on account of such injury or death, may be

-3- #28064

brought against any person performing or furnishing the design, planning, supervision, inspection, and observation of construction, or construction, of such an improvement more than ten years after substantial completion of such construction. The date of substantial completion shall be determined by the date when construction is sufficiently completed so that the owner or his representative can occupy or use the improvement for the use it was intended.

The parties agree that the initial construction of the landscaping was completed in

September 2005 and that it constituted an improvement to real property at that

time. Brude was injured in October 2014, and the claim was brought in November

2015. Therefore, Yellow Jacket met its initial burden of presumptively showing

that the action was brought beyond the statutory period in SDCL15-2A-3. See also

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Dorsey & Whitney Trust Co. LLC
2001 SD 35 (South Dakota Supreme Court, 2001)
Bordeaux v. Shannon County Schools
2005 SD 117 (South Dakota Supreme Court, 2005)
Behrens v. Wedmore
2005 SD 79 (South Dakota Supreme Court, 2005)
Clark County v. Sioux Equipment Corp.
2008 SD 60 (South Dakota Supreme Court, 2008)
Hartford Fire Insurance Co. v. Westinghouse Electric Corp.
450 N.W.2d 183 (Court of Appeals of Minnesota, 1990)
Conway v. Conway
487 N.W.2d 21 (South Dakota Supreme Court, 1992)
CTS Corp. v. Waldburger
134 S. Ct. 2175 (Supreme Court, 2014)
Schott v. Halloran Construction Company, Inc.
2013 IL App (5th) 110428 (Appellate Court of Illinois, 2013)
Pitt-Hart v. Sanford USD Medical Center
2016 SD 33 (South Dakota Supreme Court, 2016)
Peter v. Sprinkmann Sons Corp.
2015 WI App 17 (Court of Appeals of Wisconsin, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
2017 SD 46, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brude-v-breen-sd-2017.