Brude v. Breen

2017 SD 46, 900 N.W.2d 301, 2017 WL 3297727, 2017 S.D. LEXIS 102
South Dakota Supreme Court·Decided August 2, 2017·No. 28064·Published·Cited by 2 cases

Opinion

SEVERSON, Justice

[¶1.] Suzanne Brude brought suit against Shane Breen, doing business as Yellow Jacket Irrigation and Landscaping (Yellow Jacket), for negligence in constructing a retaining wall from which Brude suffered- an injury. Yellow Jacket moved for summary judgment, asserting that the claim was barred by the statute of repose. The circuit-court granted summary judgment in favor of Yellow Jacket. Brude appeals, asserting that the court erred because the ten-year limitation in the statute *303 of repose had not expired, We reverse and remand.

Background

[¶2.] In 2005, Yellow Jacket Irrigation and Landscaping contracted for and completed a landscaping project at the residence of Greg and Elizabeth Jamison. At issue in this case is landscaping that Yellow Jacket originally completed in September 2005. The area of landscaping at issue includes a patio with retaining walls on its sides and a fire pit above a section of the retaining wall. The retaining walls were repaired in 2007. At that time, Yellow Jacket fixed some stone pavers that had settled and shifted. The Jamisons and Breen have different recollections of the next time that Yellow Jacket worked on the retaining wall; it was either 2011 or 2013. The Jamisons asked Yellow Jacket to fix their patio area because some of the landscaping stones settled and leaned. Greg Jamison testified in his deposition that because the fix was fairly extensive and would require the retaining walls to be torn down and rebuilt, the Jamisons asked Yellow Jacket to make the fire pit area a little larger at the same time.

[¶3.] Suzanne Brude was at the Jamison residence on October 7, 2014. In order to retrieve some branches from the fire pit area, she stepped onto the portion of the retaining wall in front of the Jamison’s fire pit. One .of the capstones she stepped on gave way, and she fell onto the patio below. She suffered an injury that required surgery the next day. On November 6, 2015, Brude commenced this action against Shane Breen, the sole proprietor operating Yellow Jacket Irrigation and Landscaping. Yellow Jacket filed a third-party complaint against the Jamisons, contending that the Jamisons were responsible for any damages awarded to Brude. The Jamisons have since settled this matter and take no position in this appeal.

,[¶4.] On July. 29, 2016, Yellow Jacket moved for summary judgment asserting that the statutory time period to bring a claim had expired because the retaining wall and fire pit had been substantially completed more than ten years prior to the commencement of this action. See SDCL 15-2A-3. After submissions by the parties and a hearing on the motion, the circuit court granted summary judgment for Yellow Jacket. Brude appeals raising'one issue for our review. She asserts that the changes to the landscaping that occurred in either 2011 or 2013 constituted “an improvement to real property” under SDCL 15-2A-3 and therefore restarted the ten-year period to bring a claim. Thus, she claims 'that the court erred when it granted summary judgment.

Standard of Review

[¶5.] “In reviewing a grant or denial of summary judgment we must determine whether the moving party demonstrated the absence of any genuine issue of material fact and established entitlement to judgment on thé merits as a matter of law.” Clark Cty. v. Sioux Equip. Corp., 2008 S.D. 60, ¶ 8, 753 N.W.2d 406, 409 (quoting Behrens v. Wedmore, 2005 S.D. 79, ¶ 18, 698 N.W.2d 555, 565). “Those resisting summary judgment must show that they will be able to place sufficient evidence in the record at trial to support findings on all the elements on which they have the burden' of proof.” Id. (quoting Bordeaux v. Shannon Cty. Sch., 2005 S.D. 117, ¶ 14, 707 N.W.2d 123, 127). We must determine the applicability of the statute of repose to Yellow Jacket’s latest work on the retaining wall. “Because the application of a legal test to the historical facts of this case- requires us to consider legal concepts and ‘exercise judgment about the values that animate legal principles,’ we review the ... determination de novo,” Id. ¶ 10, 753 N.W.2d at 410 (quoting In re *304 Dorsey & Whitney Tr. Co., 2001 S.D. 35, ¶ 6, 623 N.W.2d 468, 471).

Analysis

[¶6.] A statute of repose is an affirmative defense, and Yellow Jacket had the initial burden of proving entitlement to it. See id. ¶ 17, 753 N.W.2d at 412. “[WJhere a defendant, by motion for summary judgment, asserts this type of affirmative defense that bars an action ‘and presumptively establishes the defense by showing the case was instituted beyond the statutory period, the burden then shifts to the plaintiff to establish the existence of material facts in avoidance of the statute.’ ” Id. (quoting Conway v. Conway, 487 N.W.2d 21, 23 (S.D. 1992)). The statute of repose at issue, SDCL 15-2A-3, provides:

No action to recover damages for any injury to real or personal property, for personal injury or death arising out of any deficiency in the design, planning, supervision, inspection, and observation of construction, or construction, of an improvement to real property, nor any action for contribution or indemnity for damages sustained on account of such injury or death, may be brought against any person performing or furnishing the design, planning, supervision, inspection, and observation of construction, or construction, of such an improvement more than ten years after substantial completion of such construction. The date of substantial completion shall be determined by the date when construction is sufficiently completed so that the owner or his representative can occupy or use the improvement for the use it was intended.

The parties agree that the initial construction of the landscaping was completed in September 2005 and that it constituted an improvement to real property at that time. Brude was injured in October 2014, and the claim was brought in November 2015. Therefore, Yellow Jacket met its initial burden of presumptively showing that the action was brought beyond the statutory period in SDCL15-2A-3. See also SDCL 15-2A-5 (providing that an injury occurring in the tenth year, after substantial completion may be brought within one year after the date on which the injury occurred but may not be brought more than eleven years after the substantial completion of construction).

[¶7.] The next question before this Court is whether Brude met her burden to establish the existence of material facts in avoidance of the statute.

Free access — add to your briefcase to read the full text and ask questions with AI

Brude v. Breen, 2017 SD 46, 900 N.W.2d 301, 2017 WL 3297727, 2017 S.D. LEXIS 102 (S.D. 2017).

2017 SD 46 (Brude v. Breen) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related