Harman Electrical Construction Co. v. Consolidated Engineering Co.

347 F. Supp. 392, 1972 U.S. Dist. LEXIS 12166
CourtDistrict Court, D. Delaware
DecidedAugust 29, 1972
DocketCiv. A. 4191, 4192
StatusPublished
Cited by10 cases

This text of 347 F. Supp. 392 (Harman Electrical Construction Co. v. Consolidated Engineering Co.) is published on Counsel Stack Legal Research, covering District Court, D. Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harman Electrical Construction Co. v. Consolidated Engineering Co., 347 F. Supp. 392, 1972 U.S. Dist. LEXIS 12166 (D. Del. 1972).

Opinion

OPINION

STAPLETON, District Judge.

These actions are presently before the Court on the motion of defendant Consolidated Engineering Co., Inc. for a stay pending arbitration pursuant to Section 3 of the Federal Arbitration Act, 9 U.S.C. § 1 et seq.

Plaintiffs, two Texas corporations, separately brought actions to collect sums assertedly due them for work performed as subcontractors in the construction of the Wilmington Tower building. The relief prayed for was the impressment of a materialman’s lien on the building pursuant to 25 Del.C. § 2701, et seq. 1 and an in personam money judgment against the defendants. The defendants were the owner of the building, American International Realty Corp. (“Realty”), a Delaware corporation, the former owner American Life Insurance Co. (“Alico”), a Delaware corporation, and the general contractor, Consolidated Engineering Co., Inc. (“Consolidated”), a Maryland corporation. The cases satisfy the jurisdictional requirements of 28 U.S.C. § 1332.

Alico filed a cross-claim against Consolidated seeking per diem damages as set forth in the contract for late completion of the structure, consequential dam *395 ages to compensate for its continuing inability to fully lease its building, which is allegedly a result of the late completion, and indemnification for any judgment it might suffer in this action.

After moving to stay, Consolidated responded with a cross-claim against Ali-co. That claim set out six grounds for recovery: (1) the construction contract was based on a mutual mistake of fact and should be “rescinded or reformed” to reflect the belief of the parties; (2) Consolidated was harmed by justifiably relying upon material misrepresentations made by Alico to induce Consolidated to agree to certain contract provisions; (3) Alico breached an express and implied warranty that the plans and specifications from which the structure would be built were free from defect; (4) Alico breached implied and express warranties by unreasonably disrupting and changing the sequence of work and providing plans that were deficient in particular ways; (5) Alico breached a promise to pay for additional work ordered by it during the course of construction; and (6) Alico has wrongfully failed to pay money, held as “retainage,” which was due to Consolidated on completion of the building.

On November 10, 1971, an order was entered upon the consent of all parties staying all proceedings in these cases until further application of any party. The settlement negotiations that followed proved unproductive and on April 20, 1972 Alico moved this Court to dissolve the stay; Consolidated then promptly moved to stay these proceedings under 9 U.S.C. § 3.

The adverse parties on this motion are the general contractor, Consolidated, and the owner, Alico; plaintiffs have not opposed the motion to stay and, indeed, support it. 2

*396 Section 3 of the United States Arbitration Act, 9 U.S.C. § 3, provides in part:

“If any suit ... be brought in any court of the United States upon any issue referable to arbitration . . . the court upon being satisfied that the issue is referable to arbitration, shall on application of one of the parties stay the trial of the action until such arbitration has been had . . . providing the applicant for the stay is not in default in proceeding with arbitration.”

In Bernhardt v. Polygraphic Co., 350 U. S. 198, 76 S.Ct. 273, 100 L.Ed. 199 (1956), the Supreme Court held that the stay provisions of § 3 apply only to those contracts of a kind specified in §§ 1 and 2 of the Act, namely those in “admiralty” or those evidencing transactions in “commerce.” This transaction comes within the statutory phrase “commerce among the several states” and meets this threshold requirement. 3 9 U.S.C. § 1; see Prima Paint Corp. v. Flood & Conklin Mfg. Co., 388 U.S. 395, 401 and n. 7, 87 S.Ct. 1801, 18 L.Ed.2d 1270 (1966). None of the parties here asserts otherwise.

Having been satisfied that “commerce” is involved, two major issues remain for our determination: first, are the issues involved referable to arbitration under the agreement of the parties and second, if so, has the applicant waived his right to demand arbitration by a default.

The understanding of the parties is evidenced by two writings. The first, the Agreement, states in part:

“The Contractor agrees ... to do all things necessary for the proper construction and completion of the work shown and described in the Specifications entitled: ‘American Life Insurance Company Building, Wilmington, Delaware, July, 1965,’ (as amended) and enumerated in the attached Schedule 1.
The said Specifications, including the General Conditions consisting of Articles 1 to 69, and the drawings enumerated in Schedule 1 together with this Agreement, constitute the Contract; the Drawings and Specifications being as fully a part thereof and hereof as if hereto attached or herein repeated.”

The second writing, the General Conditions, incorporated into the contract by the foregoing language, provides in Article 31 that:

“ . . . should either party to the Contract suffer damages because of the wrongful act or neglect of the other party or of anyone employed by him, claim shall be made in writing to the party liable within a reasonable time of the first observance of such damage and not later than the final payment, except as expressly stipulated otherwise in the case of faulty work or materials, and shall be adjusted by agreement or arbitration.”

Article 40 provides the procedure for the resolution of disputes “subject to arbitration under the Contract.”

It is argued by Alico that Article 31 makes arbitrable only tort claims arising from mishaps during the construction of the building. This is a needlessly narrow construction of the arbitration agreement and does considerable injury to the language of the relevant contract provision.

The language “suffer damages because of any wrongful act” can be applied as well to damages resulting from a contract breach. A later phrase in the same sentence demonstrates that this possible construction was in fact the one *397 the parties intended. Article 31 requires that a claim for such damages as the claimant may have suffered be made in writing “within a reasonable time and not later than the final payment,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Crawford v. West Jersey Health Systems
847 F. Supp. 1232 (D. New Jersey, 1994)
Block 175 Corp. v. Fairmont Hotel Management Co.
648 F. Supp. 450 (D. Colorado, 1986)
Farris v. Hedgepeth
374 N.E.2d 1086 (Appellate Court of Illinois, 1978)
Black v. Econo-Car International, Inc.
404 F. Supp. 600 (D. Massachusetts, 1975)
Vespe Contracting Co. v. Anvan Corporation
399 F. Supp. 516 (E.D. Pennsylvania, 1975)
Warren Bros. v. Community Building Corp. of Atlanta, Inc.
386 F. Supp. 656 (M.D. North Carolina, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
347 F. Supp. 392, 1972 U.S. Dist. LEXIS 12166, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harman-electrical-construction-co-v-consolidated-engineering-co-ded-1972.