Harbor Construction Co. v. Board of Supervisors

69 So. 3d 498, 2010 La.App. 4 Cir. 1663, 2011 La. App. LEXIS 577, 2011 WL 1836686
CourtLouisiana Court of Appeal
DecidedMay 12, 2011
DocketNo. 2010-CA-1663
StatusPublished
Cited by3 cases

This text of 69 So. 3d 498 (Harbor Construction Co. v. Board of Supervisors) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harbor Construction Co. v. Board of Supervisors, 69 So. 3d 498, 2010 La.App. 4 Cir. 1663, 2011 La. App. LEXIS 577, 2011 WL 1836686 (La. Ct. App. 2011).

Opinion

JOAN BERNARD ARMSTRONG, Chief Judge.

11Defendant, The Board of Supervisors of Louisiana State University and Agricultural and Mechanical College (LSU), appeals from a judgment of the trial court awarding its contractor, Harbor Construction Company, Inc. (Harbor), direct expenses of $17,225.07 and overhead expenses of $33,828.90 sustained as a result of a work stoppage ordered by LSU. For the reasons that follow, we affirm the judgment of the trial court.

Following a bench trial on the merits, the trial court found the following facts:

Following a competitive bid process, LSU chose Harbor to replace acid basin tanks located at the LSU Clinical Sciences Research Building in New Orleans. On July 22, 2004, LSU instructed Harbor to stop work on the project, when Harbor severed a sewer pipe located six feet below the work site. Harbor was allowed to resume work on November 11, 2004. The sewer pipe is not shown on the site plan LSU provided to Harbor, nor is it referenced in LSU’s plans or specifications for the contract. The trial court found as a fact that neither the contract nor any change order placed a burden on Harbor to discover the existence [ aof underground pipes. It held as a matter of law that Harbor had no duty to check the plans and specification furnished to it by LSU to determine if they were accurate and sufficient before proceeding with the execution of the contract. Furthermore, Harbor was entitled to rely on the accuracy and sufficiency of the plans and its only obligation was to perform in accordance with those plans. The trial court concluded that Har[500]*500bor proved its damages by a preponderance of the evidence adduced at the trial.

In reviewing the factual findings of a trial court, an appellate court is limited to a determination of manifest error. Stobart v. State through Dept. of Transp. and Development, 617 So.2d 880 (La.1993). Where there is a conflict in the testimony, reasonable evaluations of credibility and reasonable inferences of fact should not be disturbed on review, even though the appellate court may feel that its own evaluations and inferences are as reasonable. Where there are two permissible views of the evidence, the fact finder’s choice between them cannot be manifestly erroneous or clearly wrong. When findings are based on determinations regarding the credibility of witnesses, the manifest error — clearly wrong standard demands great deference to the trier of fact’s findings. Where documents or objective evidence so contradict a witness’s story, or the story itself is so internally inconsistent or implausible on its face, that a reasonable fact finder would not credit the witness’s story, the court of appeal may well find manifest error or clear wrongness even in a finding purportedly based upon a credibility determination. But where such factors are not present, and a fact finder’s finding is based on its |adecision to credit the testimony of one or more witnesses, that finding can virtually never be manifestly erroneous or clearly wrong. Rosell v. ESCO, 549 So.2d 840, 844-845 (La.1989).

If trial court legal errors have tainted the fact finding process, the verdict below is not reviewed under the manifest error standard and, if the record is complete, the appellate court may make a de novo review of the record and determine the preponderance of the evidence. Rosell v. ESCO, 549 So.2d 840, 844 fn. 2 (La.1989); Gonzales v. Xerox Corp., 254 La. 182, 320 So.2d 163 (1975).

It is our duty to review LSU’s legal arguments de novo, and to apply the manifest error standard to its claims of factual error. LSU argues that the trial court’s judgment was legally erroneous because the plaintiff had a contractual duty to discover underground utilities not shown on the construction drawings. LSU contends that this contractual duty also precludes application of La. R.S. 9:27711 to relieve it of that alleged contractual duty. LSU also claims that the trial court erroneously found that Harbor performed its work in accordance with the contract, erroneously did not find that the delays and damages were caused by Harbor’s breach of the contract, and erroneously awarded damages that were not probed by a preponderance of the evidence. These latter claims will be reviewed under the manifest error standard of review.

|4The trial court received testimony from Thomas Foret, Harbor’s project manager in 2003 and 2004; Joseph Skinner, Harbor’s owner and president; Robert S. Parker, Jr., LSU’s director of purchasing2; and Michael James May, LSU’s construction coordinator.

The contract form entered into by LSU and Harbor on August 28, 2003 incorpo[501]*501rates by reference “the Drawings, Specifications, Addenda Number(s) 2, Information for Bidders and General Conditions, Proposal Form, Specific Conditions and Advertisement for Bids”. Mr. Foret testified that he had been in the construction business since 1975, moving up from a position in the construction crew to foreman, general foreman, and ultimately to project manager. He assisted Mr. Skinner in the preparation of Harbor’s bid for the LSU project, reviewing the bid documents, including plans and specifications, prepared by Wink, Inc., LSU’s engineering firm. Mr. Foret testified without contradiction that Harbor took no part in the preparation of those bid documents, plans or specifications.

Mr. Skinner testified that the purpose of the site plans prepared by LSU was to show the things that should be taken into consideration by the contractor when bidding the job. He stated that an owner does not expect a bidding contractor to show up for an inspection of the jobsite with a shovel and a backhoe. He identified the plans and specifications for the LSU job, and testified without contradiction that the sewer pipe shown on the plan was the only sewer line shown and was not |fithe sewer line that was severed. Mr. Skinner also testified that the owner should designate any underground obstructions on the site plan. According to Mr. Skinner’s testimony, had the bid package required Harbor to locate all existing sewer and electrical lines, he would not have bid on the project.

Mr. Foret described the LSU project as removal of existing acid-waste tanks, construction of a new concrete vault, and installation of new acid-waste tanks and double-insulated piping to and from the tanks. The hole to be dug would be twelve feet with a sub-base.

In preparing Harbor’s bid, Mr. Foret and Mr. Skinner made a visual inspection of the job site, at which Mr. Skinner told the general superintendent to ask where the building’s footings were located, since they might be in the way of the construction. As a civil engineer, Mr. Skinner knew the building would have to have footings. Mr. Skinner, Mr. Foret, and the superintendent probed to see if there were footings and located them. Mr. Foret noted that building footings constituted an obstruction to the project, reducing the available work area.

Mr. Skinner testified that there was not adequate space between Perdido Street and the sidewalk and the building’s footings to perform the work. This required a reconfiguration of the work, according to Mr. Skinner, from placement of two 1250 gallon tanks to one 2,000 gallon tank. This reconfiguration was performed with a Wink, Inc. engineer. Mr. Foret testified that he requested a soil report during the “bid walk”, but, receiving none, went forward in the preparation and submission of the bid. Mr. Skinner confirmed that Harbor never received a | (¡geotechnical report on the project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Doucette v. Guient
208 So. 3d 444 (Louisiana Court of Appeal, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
69 So. 3d 498, 2010 La.App. 4 Cir. 1663, 2011 La. App. LEXIS 577, 2011 WL 1836686, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harbor-construction-co-v-board-of-supervisors-lactapp-2011.