Donahue v. Republic National Distributing Company, LLC

CourtDistrict Court, E.D. Louisiana
DecidedJanuary 27, 2020
Docket2:16-cv-13948
StatusUnknown

This text of Donahue v. Republic National Distributing Company, LLC (Donahue v. Republic National Distributing Company, LLC) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Donahue v. Republic National Distributing Company, LLC, (E.D. La. 2020).

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF LOUISIANA

JOSHUA DONAHUE ET AL. CIVIL ACTION

VERSUS NO: 16-13948

REPUBLIC NATIONAL DISTRIBUTING SECTION: “H” COMPANY, LLC ET AL.

ORDER AND REASONS Before the Court are Defendant Makar Installations, Inc.’s (“Makar”) Motion for Summary Judgment (Doc. 279) and Motion to Strike (Doc. 352). The Court heard Oral Argument on Makar’s Motion for Summary Judgment on January 16, 2020. On January 17, 2020, the Court issued an Order granting Makar’s Motion for Summary Judgment with reasons to follow. For the following reasons, Defendant Makar’s Motion for Summary Judgment is GRANTED, and the Motion to Strike is DENIED.

BACKGROUND This action arises out of injuries suffered by Plaintiff Joshua Donahue (“Donahue”) while working in Defendant Republic National Distributing Company, LLC’s (“Republic”) warehouse. In 2015, Republic contracted with W&H Systems, Inc. (“W&H”) for the construction of a new conveyer system at its liquor distribution warehouse. As part of this project, W&H contracted with Steele Solutions, Inc. (“Steele”) to design and install a new mezzanine in the warehouse. Steele, in turn, subcontracted with Makar for the installation of the Steele-designed mezzanine. W&H was responsible for installing the conveyer system that would run through the new mezzanine. W&H subcontracted with Defendant Darana Hybrid, Inc. (“Darana”) to perform electrical work on the conveyer system. Darana had a contract with Defendant American ManPower Services, Inc. (“AMPS”) whereby AMPS provided laborers to Darana to complete the electrical installation. Donahue was employed by AMPS for this project. Makar began construction of the Steele-designed mezzanine on May 4, 2015 and completed the installation on May 15, 2015. The design called for the new mezzanine to be constructed approximately three feet higher than an older, pre-existing mezzanine and a few feet apart from it. The guardrails of the older mezzanine extended several inches higher than the floor of the new mezzanine. Above the mezzanines, however, was an unguarded and fixed overhead ceiling fan. The distance between the floor of the new mezzanine and the ceiling fan was less than seven feet. The exact location of the ceiling fan, in terms of whether and to what extent it hung over the new mezzanine, is in dispute. Toward the end of Makar’s installation job, its project supervisor, Antonio Torres (“Torres”), was struck in the head by the blades of the fan while he was standing on the new mezzanine. Torres testified that he was on his knees on the floor of the new mezzanine, picking up supplies and material, when he stood straight up. He was struck by the edge of the fan blades, knocking back his head and knocking off his hard hat. He was then struck again, directly in the head right along his hairline on his forehead. He was standing flat on the mezzanine’s floor, not near the mezzanine’s edges, when it happened. He did not realize that he was under a fan when he stood up and was struck. He was standing not under the fan’s motor, but along the sides of its blades. He recalls that the entirety of the fan was directly above the new mezzanine—not necessarily in the middle of the mezzanine, but not along its edges either. He also recalls that there was no fan over the old mezzanine. Torres testified that, at the time of his injury, the new mezzanine’s perimeter had a yellow railing around it. There were no gaps in the railing for the soon- to-be-installed conveyer system to run through. The fan was turned on every day that Makar was on the job site. Torres, who is approximately 5’9” and who was wearing 1” thick steel-toed boots when he was struck, had repeatedly asked Republic employees and representatives to turn the fan off, but it was never turned off. Neither Torres, nor any other Makar employee, knew where the fan switch was located. In fact, the first time that the fan was turned off was the day after Torres’ injury, which was also the last day that Makar was on the job site. Torres testified that on that day, he told Republic representatives that “the damage had already been done,” but that the fan should still be removed because it nevertheless posed a hazard. On the day of his injury, Torres called Makar’s owner, Gilbert Makaryk, and notified him of the incident. Makaryk spoke with W&H’s project manager, David Sweitzer, about Torres’ injury the same day.1 Sweitzer then spoke with Steele about the injury within hours of it happening. He also spoke with Torres. After Makar completed construction of the Mezzanine and departed Republic’s warehouse, Donahue and other AMPS laborers began to work on the electrical installation for the conveyor system. Gaps had been made in the

1 Doc. 330-2 at 73–76. Defendant Makar asserts in its brief that Makaryk also spoke directly with Steele Solutions about the fan and Torres’ injury. Doc. 346 at 8. Makar cites to pages 35 and 36 of Makaryk’s deposition testimony, but it failed to provide these pages to the Court. The Court was unable to locate the referenced deposition transcript pages anywhere else in the record. yellow railing that encircled the new mezzanine’s perimeter to allow access for the conveyer system. At the time of Donahue’s injury, all but one of the gaps in the railing had been filled by the conveyor system. The remaining gap was located along the edge of the new mezzanine that was adjacent to the old mezzanine. The new mezzanine had stairs at one end that led directly to the ground floor, but Donahue and other workers customarily descended to the ground floor by traversing from the new mezzanine to the old mezzanine. The old mezzanine also had stairs to the ground floor, and Donahue testified that it was more convenient to use the stairs of the old mezzanine because they were closer. The location of the single remaining gap in the new mezzanine’s railing was the access point for traversing between the two mezzanines. Donahue testified that the two mezzanines were only six inches apart, but large enough for someone to fall between them.2 He would place one foot on the floor of the new mezzanine, place his other foot on the top of the old mezzanine’s rail, and then hop down about three to four feet to the ground of the old mezzanine. From there, he would take the stairs to the ground floor. On July 29, 2015, Donahue had been on his knees on the floor of the new mezzanine installing a wire. He finished, stood up, and went toward the gap in the railing so he could descend to the ground floor by way of the old mezzanine. Donahue had one foot on the floor of the new mezzanine and began to move forward to place his other foot on top of the handrail of the older mezzanine when he was struck in the head by one of the fan blades. Donahue had worked at the site for approximately two months before his injury, and he

2 Torres testified that the gap was three feet wide and that only a tall person would be able to make that jump. testified that the fan was off the entire time he was there. This time, however, the overhead fan was turned on. Donahue suffered numerous injuries and brought suit against Republic, W&H, Daranda, AMPS, Makar, and Steele, among others, for negligence. The Parties have since settled many claims. Remaining are Donahue’s claims for negligence against Makar, Steele’s crossclaim against Makar for contractual indemnity, and Steele’s third-party demand against Cincinnati Insurance Company for reimbursement of litigation expenses.

LEGAL STANDARD “The court shall grant summary judgment if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.”3 “As to materiality . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Little v. Liquid Air Corp.
37 F.3d 1069 (Fifth Circuit, 1994)
Engstrom v. First National Bank of Eagle Lake
47 F.3d 1459 (Fifth Circuit, 1995)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Oxley v. Sabine River Authority
663 So. 2d 497 (Louisiana Court of Appeal, 1995)
Cormier v. Honiron Corp.
771 So. 2d 193 (Louisiana Court of Appeal, 2000)
Morgan v. Lafourche Recreation Dist. No. 5
822 So. 2d 716 (Louisiana Court of Appeal, 2002)
Boudreaux v. Banctec, Inc.
366 F. Supp. 2d 425 (E.D. Louisiana, 2005)
Roy Bufkin, Jr. v. Felipe's Louisiana, LLC
171 So. 3d 851 (Supreme Court of Louisiana, 2014)
Milbert v. Answering Bureau, Inc.
120 So. 3d 678 (Supreme Court of Louisiana, 2013)
Harbor Construction Co. v. Board of Supervisors
69 So. 3d 498 (Louisiana Court of Appeal, 2011)
Badon v. R J R Nabisco Inc.
224 F.3d 382 (Fifth Circuit, 2000)
Lafont v. Chevron, U.S.A., Inc.
593 So. 2d 416 (Louisiana Court of Appeal, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
Donahue v. Republic National Distributing Company, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/donahue-v-republic-national-distributing-company-llc-laed-2020.