Hale v. Big H Construction, Inc.

2012 UT App 283, 288 P.3d 1046, 719 Utah Adv. Rep. 17, 2012 WL 4840685, 2012 Utah App. LEXIS 293
CourtCourt of Appeals of Utah
DecidedOctober 12, 2012
Docket20100785-CA
StatusPublished
Cited by34 cases

This text of 2012 UT App 283 (Hale v. Big H Construction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hale v. Big H Construction, Inc., 2012 UT App 283, 288 P.3d 1046, 719 Utah Adv. Rep. 17, 2012 WL 4840685, 2012 Utah App. LEXIS 293 (Utah Ct. App. 2012).

Opinion

OPINION

VYOROS, Judge:

11 This case involves a dispute over a cost-plus contract to build two high-end custom homes on adjacent lots. When the builder, Big H Construction, Inc., filed a mechanies' lien on one of the homes, the owners, Charles F. Hale and Beverly I. Hale, sued Big H and its president, T. Dwayne Horsley, for breach of contract and related claims. Big H counterclaimed for nonpayment of a ten percent builder's fee. After a bench trial, the trial court awarded Big H $172,100 plus attorney fees and costs. The Hales moved unsuccessfully for a new trial and to amend the findings pursuant to rules 52(b) and 59 of the Utah Rules of Civil Procedure. The Hales appeal. We affirm.

BACKGROUND 1

€ 2 In February 2003, the Hales hired Big H to construct two custom homes on adjacent lots known as Lots 45 and 46. The parties agreed that Big H would construct the homes on a cost-plus basis with the Hales covering all reasonable costs (the Costs) plus a builder's fee equal to ten percent of the Costs. The project involved forty-seven separate subcontractors and suppliers, some of whom the Hales contracted with and paid directly over the course of construction.

13 Two of Dwayne Horsley's family members worked on the project in some capacity with Big H or the Hales or both. David Horsley, Dwayne's father and a licensed real estate agent, prepared Real Estate Purchase Contracts (REPCs) for the Hales' purchase of the Lots from the developer and their purchase of the homes from Big H. James Horsley, Dwayne's brother, negotiated the purchase of Lots 45 and 46 on the Hales' behalf and worked as a site foreman.

T4 The Hales executed an REPC for the purchase of Lots 45 and 46 from Triple Crown Estates on February 25, 2008. The REPC provided for a three percent commission to the developer's agent. David Horsley was listed as the Hales' agent, but the REPC did not provide for a commission to him. That same day, the Hales executed two separate REPCs for the Lot 45 and Lot 46 homes, with Big H listed as seller. The REPCs listed no agents for either buyers (the Hales) or sellers (Big H) and mentioned no sales commissions.

15 By late 2004, Big H had largely completed construction on the Lot 45 home. However, the parties' working relationship had deteriorated. When the Hales refused to pay anything further, Big H left the project. Approximately three months later, Big H filed a mechanies' lien on the Lot 45 home in the amount of $165,000. Big H claimed this sum approximated its builder's fee. The Hales sued. Big H counterclaimed for breach of contract and foreclosure of its me-chanies' lien.

T6 At trial, Big H offered into evidence voluminous documentation, including stacks of invoices from dozens of vendors documenting expenses and copies of cancelled checks from the Hales documenting payments. The invoices for both homes totaled more than $2.7 million. Dwayne Horsley testified about the Costs and payments that he tracked on a spreadsheet over the course of the project; Big H's expert witness testified that the Costs were reasonable. By Big H's account, the Hales owed it roughly $172,000 (although that figure varied over the course of the litigation from $165,000 to $174,000).

T7 The Hales advanced a different version of Costs incurred and payments made. They offered testimony from their accounting ex *1051 pert. The Hales' expert testified that he had reviewed all the records furnished by the Hales and Big H, and that the Hales had overpaid Big H by $116,994.77. His conclusion was based in part on "unsupported costs" and various alleged overpayments and underpayments. However, the trial court found much of the Hales' evidence-including their expert's testimony-unreliable, and relied instead mainly on the evidence offered by Big H. The trial court found that Costs of $1,721,000 had been incurred and paid for by the Hales on the Lot 45 home, entitling Big H to a builder's fee of $172,100. 2

T8 The trial court entered judgment for Big H in the amount of $172,100 for its builder's fee, $94,463 in prejudgment interest, and $342,240.84 in attorney fees and costs. It denied the Hales' subsequent motion for a new trial or to amend the court's findings of fact, The Hales timely appeal.

ISSUES AND STANDARDS OF REVIEW

T9 First, the Hales contend that the trial court erred in ruling that Big H met its burden at trial because it relied on estimates rather than an actual accounting of Costs. "Whether the trial court calculated the damages award within the framework dictated by the [contract] ... is a question of law," Traco Steel Erectors, Inc. v. Comtrol, Inc., 2009 UT 81, ¶ 21, 222 P.3d 1164, which we review for correctness, see State v. Pena, 869 P.2d 932, 936 (Utah 1994), holding modified by State v. Levin, 2006 UT 50, 144 P.3d 1096. However, "an appeal from the types of properly admitted evidence upon which the trial court applies" the damages formula is "an appeal from a question of fact," Traco, 2009 UT 81, ¶ 33, 222 P.3d 1164. "In all actions tried upon the facts without a jury, ... [flindings of fact ... shall not be set aside unless clearly erroneous, and due regard shall be given to the opportunity of the trial court to judge the credibility of the witnesses." Utah R. Civ. P. 52(a). A finding is clearly erroneous "'only if the finding is without adequate evidentiary support or induced by an erroneous view of the law.'" State v. Walker, 743 P.2d 191, 193 (Utah 1987) (quoting Wright & Miller, Federal Practice & Procedure § 2585 (1971). Therefore, we will not disturb a finding unless it is "against the clear weight of the evidence, or if [we] otherwise reach[ ] a definite and firm conviction that a mistake has been made." Id.

110 Second, the Hales contend that the trial court included in its calculation other "improper and unreasonable costs," including duplicate and mistaken invoices, and both overpayments and underpayments by Big H. This question involves a finding of fact that we review for clear error. See Traco, 2009 UT 81, ¶¶ 17, 33, 222 P.3d 1164.

T11 Third, the Hales challenge the trial court's finding that the Hales were not entitled to an offset based on Big H's alleged failure to perform work in a good and workmanlike manner. This challenge presents a mixed question of law and fact. "It is therefore reviewed under a clearly erroneous standard for questions of fact and a correctness standard for questions of law." Tooele Assocs. Ltd. Partnership v. Tooele City Corp., 2011 UT 04, ¶ 16, 247 P.3d 371.

112 Fourth, the Hales assert that the trial court erred by including the cost of the land in its calculation of the builder's fee, arguing that doing so runs afoul of the Utah Real Estate Licensing and Practices Act, see Utah Code Ann. §§ 61-2-1 to -24 (Lexis Publishing 2000) (current version at id. §§ 61-2f-101 to -512 (LexisNexis 2011 & *1052 Supp. 2012)). 3

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lomsanidze v. Musayev
2025 UT App 81 (Court of Appeals of Utah, 2025)
New Star General v. Dumar
2025 UT 14 (Utah Supreme Court, 2025)
Sunrise Home Health and Hospice v. Nye
2025 UT App 62 (Court of Appeals of Utah, 2025)
Capozzoli v. Madden
2024 UT App 176 (Court of Appeals of Utah, 2024)
J. Bird v. Lynn Wardley
Tenth Circuit, 2024
In re Harding Trust
2023 UT App 81 (Court of Appeals of Utah, 2023)
Bad Ass Coffee v. Royal Aloha
2020 UT App 122 (Court of Appeals of Utah, 2020)
Linebaugh v. Gibson
2020 UT App 108 (Court of Appeals of Utah, 2020)
Gukeisen v. Department of Public Safety
2020 UT App 32 (Court of Appeals of Utah, 2020)
Seamons v. Wiser
2020 UT App 33 (Court of Appeals of Utah, 2020)
LeFevre v. Mackelprang
2019 UT App 42 (Court of Appeals of Utah, 2019)
Sauer v. Sauer
2017 UT App 114 (Court of Appeals of Utah, 2017)
State v. Gailey
2016 UT 35 (Utah Supreme Court, 2016)
Brasher v. Christensen
2016 UT App 100 (Court of Appeals of Utah, 2016)
Crane-Jenkins v. Mikarose, LLC
2016 UT App 71 (Court of Appeals of Utah, 2016)
M.J. v. Wisan
2016 UT 13 (Utah Supreme Court, 2016)
Meyer v. Aposhian
2016 UT App 47 (Court of Appeals of Utah, 2016)
Express Recovery Services Inc. v. Reuling
2015 UT App 299 (Court of Appeals of Utah, 2015)
Stearns Lending Inc. v. Pyle
2015 UT App 252 (Court of Appeals of Utah, 2015)
High Desert Estates LLC v. Arnett
2015 UT App 196 (Court of Appeals of Utah, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
2012 UT App 283, 288 P.3d 1046, 719 Utah Adv. Rep. 17, 2012 WL 4840685, 2012 Utah App. LEXIS 293, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hale-v-big-h-construction-inc-utahctapp-2012.