New Star General v. Dumar

2025 UT 14
CourtUtah Supreme Court
DecidedMay 22, 2025
DocketCase No. 20230639
StatusPublished

This text of 2025 UT 14 (New Star General v. Dumar) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
New Star General v. Dumar, 2025 UT 14 (Utah 2025).

Opinion

This opinion is subject to revision before final publication in the Pacific Reporter 2025 UT 14

IN THE

SUPREME COURT OF THE STATE OF UTAH

NEW STAR GENERAL CONTRACTORS, INC., Appellee, v. DUMAR, LLC and DUANE SHAW, Appellants.

No. 20230639 Heard December 13, 2024 Filed May 22, 2025

On Direct Appeal

Seventh District Court, Grand County The Honorable Don M. Torgerson No. 200700055

Attorneys: Brian J. Babcock, Andrew L. Berne, Salt Lake City, for appellee J. Tayler Fox, John R. Richardson, Salt Lake City, for appellants

CHIEF JUSTICE DURRANT authored the opinion of the Court, in which ASSOCIATE CHIEF JUSTICE PEARCE, JUSTICE PETERSEN, JUSTICE HAGEN, and JUSTICE POHLMAN joined.

CHIEF JUSTICE DURRANT, opinion of the Court: INTRODUCTION ¶1 New Star General Contractors, Inc. (New Star) sued to enforce its construction lien on twelve condo units in a large development in Grand County after the developer, Sage Creek at Moab, LLC (Sage Creek), failed to pay for New Star’s construction work. The units’ owners, Dumar, LLC, and Duane Shaw (collectively, Dumar), challenged the lien on multiple grounds. The district court ruled that New Star could enforce its lien. Dumar appeals. NEW STAR v. DUMAR Opinion of the Court

¶2 Dumar first challenges the two sets of preliminary notices New Star filed with the state construction registry to preserve its lien rights. It asserts the first preliminary notices—filed for the whole development—could only support a lien for the sitework. And it argues the second preliminary notices—specific to Building C, the site of the twelve condos at issue here—did not list the right parcel numbers as required by Utah Code section 38-1a-501. We assume without deciding that New Star was required to file the second preliminary notices. But we conclude that, despite New Star’s failure to include the correct parcel numbers, the second preliminary notices substantially complied with the statute because a reasonably diligent search of the registry would have returned the preliminary notices. We therefore decline to analyze the first preliminary notices. ¶3 Dumar next argues New Star’s lien is invalid because New Star failed to allocate its expenses between the units and the common areas of the building. We hold that the relevant statutes do not require that allocation to establish a valid lien. ¶4 Dumar then asserts the district court miscalculated the amount it owed under the lien. We agree that the district court erred in allocating all the costs of constructing Building C to Dumar, rather than limiting Dumar’s liability to its ownership share in the development. We remand for the district court to determine the correct amount Dumar owes under the lien based on Dumar’s ownership share. ¶5 Finally, having held that the district court miscalculated the lien amount, we vacate its order dismissing Dumar’s excessive lien claim and entering an attorney fee award for New Star. We direct the district court to reconsider both issues on remand. BACKGROUND 1 ¶6 In 2017, Sage Creek contracted with New Star to develop a property in Moab. Together, they hoped to build nine condo buildings, each containing twelve units, for a total of 108 condos. New Star and Sage Creek “entered into a master agreement . . . for the entire development[,] . . . contingent upon financing being available for each building.” Then, as construction progressed, they __________________________________________________________ 1 “On appeal from a bench trial, we view the evidence in the

light most favorable to the district court’s findings.” In re W. Ins. Co., 2022 UT 38, ¶ 7 n.1, 521 P.3d 851 (cleaned up).

2 Cite as: 2025 UT 14 Opinion of the Court

amended the contract to include specifics for each building. Sage Creek financed the development with a loan from Broadmark Real Estate Management II, LLC (Broadmark), secured by a deed of trust with the development property as collateral. ¶7 In January 2018, to preserve its lien rights, New Star filed three preliminary notices with the state construction registry (first preliminary notices), listing the tax parcel numbers of the three parcels that comprised the entire development. The notices identified Sage Creek as the owner of the development and described the project as “108 NEW CONDO UNITS.” ¶8 In November 2018, Sage Creek recorded the condo declaration for the development, establishing new parcel numbers for each condo unit and describing the bounds of each unit and the common areas. The declaration divided ownership of the common areas equally between the 108 units, giving each unit a 1/108 ownership share in the development. 2 ¶9 The next month, Sage Creek and New Star signed a contract amendment for Building C. New Star then filed a second set of three preliminary notices for Building C (second preliminary notices). The notices listed the original three parcel numbers, rather than the new parcel numbers established by the condo declaration for the Building C units. ¶10 In April 2019, Dumar, LLC contracted with Sage Creek to purchase six units in Building C for $3.3 million. Dumar, LLC’s minority partner, Shaw, contracted to buy the remaining six units for $3.3 million. Each contract included an ownership interest in part of the development’s common areas, as laid out in the condo declaration. Later, Dumar negotiated a $1.65 million credit from Sage Creek, as part of a deal on a different real estate development. ¶11 Dumar closed on its purchases in late April 2019. At closing, Dumar paid off the portion of Broadmark’s loan secured by the deed of trust on Dumar’s twelve units and its interest in the common areas, releasing the deed of trust from its units.

__________________________________________________________ 2 The district court opinion appears to contain a typo, stating

that each unit owned a 0.09259% share in the development. The declaration describes a 0.9259% ownership share for each unit, consistent with the court’s finding that each unit owned 1/108 of the common areas.

3 NEW STAR v. DUMAR Opinion of the Court

¶12 In total, Building C’s construction cost about $3.9 million. Sage Creek paid New Star for some work on Building C. Dumar also paid about $2.75 million in several installments to New Star, as New Star submitted invoices for Building C to Sage Creek. New Star applied most of Dumar’s payments toward the outstanding invoices for Building C. But it sometimes applied Dumar’s payments to other parts of the development, based on direction from Sage Creek or the age of the outstanding invoices. After Dumar paid all it owed under its agreement with Sage Creek, Sage Creek ran into financial difficulties and failed to pay New Star for the rest of the work on Building C. ¶13 After Sage Creek’s default, further work on the development stalled, leaving complete only Building C and three other buildings out of the nine buildings Sage Creek and New Star had originally envisioned. New Star was paid in full for the work on the other three buildings. Broadmark foreclosed its deed of trust on the development. But because Dumar had previously paid off Broadmark’s interest in its twelve units and its share of the common areas, Broadmark’s foreclosure did not reach Dumar’s ownership interest. 3 ¶14 In June 2020, New Star filed a notice of construction lien against Dumar’s units, seeking payment of about $1.2 million. After one of New Star’s subcontractors filed suit against New Star to recover for its work on Building C, New Star filed a third-party complaint against Sage Creek and Dumar. New Star sought to enforce its contract with Sage Creek and foreclose its construction lien against Dumar. ¶15 In response, Dumar challenged the validity of the lien on several grounds. It asserted that none of New Star’s preliminary notices substantially complied with the Construction Lien Statute,4

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jouflas v. Fox Television Stations, Inc.
927 P.2d 170 (Utah Supreme Court, 1996)
Valcarce v. Fitzgerald
961 P.2d 305 (Utah Supreme Court, 1998)
Salmon v. Davis County
916 P.2d 890 (Utah Supreme Court, 1996)
Projects Unlimited, Inc. v. Copper State Thrift & Loan Co.
798 P.2d 738 (Utah Supreme Court, 1990)
View Condominium Owners Ass'n v. MSICO, L.L.C.
2005 UT 91 (Utah Supreme Court, 2005)
Arnold Industries, Inc. v. Love
2002 UT 133 (Utah Supreme Court, 2002)
Bagley v. Bagley
2016 UT 48 (Utah Supreme Court, 2016)
Laws v. Grayeyes
2021 UT 59 (Utah Supreme Court, 2021)
Hale v. Big H Construction, Inc.
2012 UT App 283 (Court of Appeals of Utah, 2012)
Zion Village Resort v. Pro Curb USA
2020 UT App 167 (Court of Appeals of Utah, 2020)
VCS, Inc. v. La Salle Development, LLC
2012 UT 89 (Utah Supreme Court, 2012)
Westgate Resorts, Ltd. v. Adel
2016 UT 24 (Utah Supreme Court, 2016)
Bonner County v. Western Insurance
2022 UT 38 (Utah Supreme Court, 2022)
Wittingham v. TNE Limited Partnership
2024 UT 23 (Utah Supreme Court, 2024)

Cite This Page — Counsel Stack

Bluebook (online)
2025 UT 14, Counsel Stack Legal Research, https://law.counselstack.com/opinion/new-star-general-v-dumar-utah-2025.