Haines & Kibblehouse, Inc. v. Balfour Beatty Construction, Inc.

789 F. Supp. 2d 622, 2011 U.S. Dist. LEXIS 58599, 2011 WL 2149750
CourtDistrict Court, E.D. Pennsylvania
DecidedJune 1, 2011
DocketCivil Action 08-5505
StatusPublished
Cited by3 cases

This text of 789 F. Supp. 2d 622 (Haines & Kibblehouse, Inc. v. Balfour Beatty Construction, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Haines & Kibblehouse, Inc. v. Balfour Beatty Construction, Inc., 789 F. Supp. 2d 622, 2011 U.S. Dist. LEXIS 58599, 2011 WL 2149750 (E.D. Pa. 2011).

Opinion

MEMORANDUM

DALZELL, District Judge.

Plaintiff Haines & Kibblehouse, Inc. (a Pennsylvania corporation) (“H & K”) seeks declaratory relief and judgment in this diversity action against Balfour Beatty Construction, Inc. (a Delaware corporation with its principal place of business in Atlanta, Georgia) (“Balfour”) in an amount in excess of $1 million. Compl. ¶ 143, 150, 158, 165, 178. Balfour moves to dismiss the case for failure to state a claim and/or to stay litigation pursuant to Fed.R.Civ.P. 12(b)(6) and Fed.R.Civ.P. 12(b)(7). 1

As will be seen, given the unusual procedural posture, we must embark on an extended analysis of relatively arcane areas of law in order to decide this motion.

I. Factual Background

Balfour was the general contractor for the Commonwealth of Pennsylvania’s Department of Transportation (“PennDOT”) for the construction of the Route 222 Bypass project (the “Project”). Compl. ¶ 13. On March 15, 2004, Balfour entered into a contract with PennDot to furnish work, labor, materials and services for the construction of the Project. Id. ¶ 15. Balfour’s contract with PennDot involved about $57.7 million (the “Prime Contract”). Id. ¶ 16. On April 21, 2004, Balfour entered into a subcontract with H & K in the initial amount of $13,399,897.20 (the “Subcontract”). Id. ¶ 17. The Prime Contract included a special provision for project milestones. Id. ¶ 18.

The special provision required that all Project construction would be completed on or before July 7, 2006 or Balfour would be subject to PennDot’s assessment of road user liquidated damages. Id. ¶ 19. Because PennDot did not issue the “Notice to Proceed” on the Project by the date the Prime Contract anticipated, PennDot granted a seventy-three-day extension to the Project milestone date. Id. ¶ 21. This extension revised the Project milestone date from July 7, 2006 to September 19, 2006. Id. ¶ 22.

H & K avers that Balfour knew that if Balfour failed to complete the predecessor work and did not provide H & K with unrestricted access to the worksite, H & K could not complete the work it was contracted to do and this would result in H & K’s increased costs and expenses for which *626 Balfour would be held accountable. Id. ¶36. H & K also avers that at no time prior to entering into the Subcontract did Balfour inform H & K that Balfour would be making unilateral changes to the sequence or durations of predecessor work that would directly affect H & K’s work, but, instead, expressly and impliedly agreed “to efficiently progress the work.” Id. ¶43 [sic].

H & K claims that Balfour “failed to commence, prosecute and complete the predecessor activities” in the prescribed sequences and within the specific time-frame agreed to with H & K and upon which H & K based its pricing. Id. ¶ 63. When Balfour notified H & K to proceed with its subcontract work, Balfour had not completed the predecessor work and had not yet procured the materials to complete the work H & K agreed to do. Id. ¶ 65. H & K claims that Balfour’s failure to complete the predecessor work with diligence and with sufficient manpower and equipment, as well as its denial of full access to the site to H & K interfered with the planned sequence of operations by H & K and caused H & K to incur additional costs. Id. ¶ 68.

As of November of 2005, the Project was significantly behind schedule, the necessary predecessor work needed for H & K’s placement of subbase and paving remained incomplete, and Balfour allegedly had made many unilateral changes to the schedule and sequence for the remaining work. Id. ¶ 92. Although the Project was supposed to be completed in late 2006, it was not completed until late 2007. Id. ¶ 96. Balfour has not yet fully paid H & K for the impacts of its poor scheduling on H & K’s work. Id. ¶ 98. H & K claims that Balfour has also failed to make a claim to PennDot for the increased costs of H & K completing its work, including, but not limited to, the increase in the unit prices for the work H & K performed. 2 Id. ¶ 99.

H & K believes that as of September 19, 2006 PennDot began assessing liquidated damages against Balfour. Id. ¶ 111. PennDot never assessed damages against H & K. Id. ¶ 113. H & K estimates that the minimum impact of Balfour’s failings on H & K’s work exceeded ten million dollars. Id. ¶ 117.

II. Procedural History

The crux of this motion to dismiss will be found in the relationship between H & K and the courts rather than the relationship between the parties. On September 18, 2006, H & K filed a complaint against Balfour in the Montgomery County Court of Common Pleas. Balfour removed that case to federal court at C.A. No. 06-4807 3 and filed a motion to dismiss. Judge Golden dismissed without prejudice all of H & K’s claims except H & K’s claim for declaratory relief. Judge Golden remanded that claim back to state court on June 7, 2007. In doing so, Judge Golden relied upon Balfour’s Subcontract-based defenses to the action, holding that:

The plain meaning of Article 2.2.20 is that any claim that the subcontractor (Plaintiff) has for performing extra work or arising out of a delay or any other claim, whether it be against PennDot or the Contractor (Defendant) must first be compensated by the Owner (PennDot) to the Contractor (Defendant) before Plaintiff can bring suit against the Defendant.

Haines & Kibblehouse, Inc. v. Balfour Beatty Constr., Inc., No. 06-4807, slip. op. at 4 (E.D.Pa. Jun. 7, 2007) (we shall refer to this case hereinafter as “Haines I”) (emphasis in original). H & K filed a motion for reconsideration of that Order, *627 which Judge Golden denied on July 27, 2007. Haines I, slip. op. at 1 (Jul. 27, 2007). Judge Golden also in that Order denied H & K’s request to certify the Court’s Memorandum Opinion for interlocutory appeal. Id.

H & K nevertheless on August 22, 2007 filed a Notice of Appeal from Judge Golden’s July 27, 2007 Order in the hope of standing on its complaint and securing appellate review of the four counts that Judge Golden dismissed without prejudice. MTD1, Ex. 5 (Letter brief of Sept. 5, 2007 in C.A. No. 07-3520 (3d Cir.)). H & K declared that “there is no way for H & K to cure the ‘defect’ that the District Court found in the Complaint” because the condition precedent, as Judge Golden defined it, “will never be achieved.” Id. at 3. Thus, H &

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
789 F. Supp. 2d 622, 2011 U.S. Dist. LEXIS 58599, 2011 WL 2149750, Counsel Stack Legal Research, https://law.counselstack.com/opinion/haines-kibblehouse-inc-v-balfour-beatty-construction-inc-paed-2011.