Haines & Kibblehouse, Inc. v. Balfour Beatty Construction, Inc.

553 F. App'x 246
CourtCourt of Appeals for the Third Circuit
DecidedFebruary 3, 2014
DocketNo. 11-2826
StatusPublished
Cited by1 cases

This text of 553 F. App'x 246 (Haines & Kibblehouse, Inc. v. Balfour Beatty Construction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Haines & Kibblehouse, Inc. v. Balfour Beatty Construction, Inc., 553 F. App'x 246 (3d Cir. 2014).

Opinion

OPINION

SMITH, Circuit Judge.

Haines & Kibblehouse, Inc. (“H & K”) appeals from an order of the District Court dismissing its complaint pursuant to the doctrine of judicial estoppel. For the reasons expressed below, we will affirm.

This case comes before us after traversing a complex procedural path, which the District Court aptly characterized as “lab-yrinthian.” Balfour Beatty Construction, Inc. (“Balfour”) contracted with the Commonwealth of Pennsylvania’s Department of Transportation (“PennDOT”) to be the general contractor for the construction of the Route 222 Bypass project (the “Project”). On April 21, 2004, Balfour entered into a subcontract with H & K to perform certain paving, subbase, and utility work for the Project. Although the terms of the contract between Balfour and PennDOT required that the Project be completed by September 18, 2006, significant delays pushed the eventual completion date back to late 2007.

On September 18, 2006 (the original date the Project was to be completed), H & K filed a five-count complaint against Balfour in the Court of Common Pleas of Montgomery County, Pennsylvania (“Haines /”), alleging, inter alia, that Balfour’s failure to complete certain predecessor work with diligence caused H & K to incur significant additional costs and other damages. Balfour removed Haines I to the United States District Court for the Eastern District of Pennsylvania and filed a motion to dismiss. On June 7, 2007, the District Court dismissed four of H & K’s claims without prejudice and remanded the only remaining claim, one for declaratory relief, back to state court.

The District Court’s decision to dismiss certain counts of the Haines I complaint was based on its determination that, under the terms of the Subcontract, H & K could not pursue its claims against Balfour unless (or until) Balfour first sought compensation from PennDOT — a predicate event which had not yet occurred. In reaching this decision, the District Court relied on Article 2.2.20 of the Subcontract, explaining:

The plain meaning of Article 2.2.20 is that any claim that the subcontractor [¶] & K] has for performing extra work or arising out of a delay or any other claim, whether it be against PennDot or [Balfour] must first be compensated by the Owner (PennDot) to the Contractor [Balfour] before [¶] & K] can bring suit against [Balfour].[1]

[248]*248Haines & Kibblehouse, Inc. v. Balfour Beatty Constr., Inc., No. 2:06-cv-4807, slip op. at 4, 2007 WL 8026873 (E.D.Pa. June 7, 2007) (emphasis in original).

Following entry of the dismissal order, H & K filed a motion for reconsideration and simultaneously requested permission to take an interlocutory appeal. Both requests were denied. H & K then filed a Notice of Appeal with the Third Circuit on August 22, 2007. Upon receipt of the Notice of Appeal, the Clerk of Court instructed the parties to comment on the Court’s jurisdiction, and, more specifically, to discuss whether the District Court had issued a final order subject to appellate review. In a letter brief dated September 5, 2007, H & K responded that the District Court’s dismissal was indeed final. H & K claimed that it was “ stand [ing] on the allegations in the [Haines 7] Complaint” because there was “no way for [it] to cure the ‘defect’ that the District Court found.” Further, H & K claimed that the condition precedent, as the District Court defined it, “will never be achieved” because Balfour has no legal avenue to seek compensation from PennDOT for its own breach of the Subcontract. Accordingly, H & K asserted that it “will never be able to re-file its Complaint.”

On January 30, 2008, this Court issued an order stating its intention to address the jurisdictional question during its review of the case on the merits.2 The Court, however, did not immediately issue a briefing schedule because the parties were engaged in our Circuit’s mandatory mediation program. After nearly eight months of mediation, H & K sought to terminate the mediation process and to proceed with its appeal. In response, this Court issued a briefing schedule.

Before either party submitted an appellate brief, however, H & K voluntarily dismissed its Haines I appeal and, in its place, filed a new (second) complaint in the Montgomery County Court of Common Pleas (“Haines II”).3 H & K’s complaint in Haines II named the same parties, asserted the same claims, and involved exactly the same set of facts alleged in [249]*249Haines I. On November 24, 2008, Balfour removed Haines II to United States District Court for the Eastern District of Pennsylvania, and then moved to dismiss based on claim preclusion and judicial es-toppel. Significantly, Balfour argued that H & K was barred by the doctrine of judicial estoppel from claiming that the District Court had not issued a final order in Haines I, particularly in light of H & K’s decision to stand on its complaint in the Haines I appeal and its representations to this Court that it would “never” be able to re-file its complaint.

In response, H & K argued that its representations regarding the finality of the District Court’s dismissal in Haines I were made before it discovered that Balfour had failed to include H & K’s claims in a complaint that Balfour had made to the Pennsylvania Board of Claims on July 11, 2007 (the “Board of Claims Complaint”), which H & K did not receive a copy of until September 17, 2007 (twelve days after it filed its jurisdictional letter brief in the Haines I appeal). Balfour’s Board of Claims Complaint alleged that PennDOT caused Balfour to incur additional costs and delays on the Project. The complaint, however, did not mention H & K by name, assert H & K’s claims against PennDOT, or seek payment for claims arising out of Balfour’s alleged breach of the Subcontract.

H & K claims that only after reviewing the Board of Claims Complaint “and thereafter conducting] due diligence over a 12 month period” did it determine that Balfour had waived its right to rely on Article 2.2.20 of the Subcontract. In its brief opposing Balfour’s motion to dismiss, H & K claimed that this discovery was a “watershed development” in the context of its Haines I appeal because it showed that the condition precedent articulated in the District Court’s June 2007 Order had not been met. This, H & K argued, “eviscerated the factual underpinnings” of the June 2007 Order, thereby rendering that order moot.

The District Court disagreed, and, on June 1, 2011, entered an order dismissing the Haines II complaint based on judicial estoppel. Applying the three-part test set out in Krystal Cadillac-Oldsmobile GMC Truck, Inc. v. General Motors Corp., 387 F.3d 314, 319 (3d Cir.2003), the District Court found that dismissal on the basis of judicial estoppel was appropriate because H & K took irreconcilably inconsistent positions, acted in bad faith, and no lesser sanction was appropriate. The Court rejected H & K’s argument that its discovery about the contents of Balfour’s Board of Claims Complaint somehow permitted H & K to abandon its Haines I appeal in favor of filing Haines II in state court. The Court explained:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
553 F. App'x 246, Counsel Stack Legal Research, https://law.counselstack.com/opinion/haines-kibblehouse-inc-v-balfour-beatty-construction-inc-ca3-2014.